MONTHWISE PLANNING FOR CONSTRUCTION OF GUIDE BUNDS FOR BR.NO.

375 (MANU RIVER)


Name of work:- Construction of Guide bunds for protection of Br. No. 375 (Manu River) (span 2x61.00 m) in between Manubazar-
Sabroom in conecion with Agartala- Sabroom, New BG Line Project.
Name of contractor:- Shri. Nandigiri Bhuyan .
CA No.CON/AGTL-SABROOM/2156, date.08.02.2016
Value of Remarks
works(In
SL Month. Description of Work. Crore)
Deployment of Machinery
& manpower
1 April.16 C.C Block production Mixer machine-01 and 16 0.15
manpower
2 May,16 C.C Block production Mixer machine-01 and 26 0.25
manpower
3 June,16 C.C Block production Mixer machine-01 and 26 0.25
manpower
4 July,16 C.C Block production Mixer machine-01 and 26 0.20
manpower
5 Aug,16 C.C Block production Mixer machine-01 and 26 0.20
manpower
6 Sep,16 C.C Block production Mixer machine-01 and 28 0.30
manpower
7 Oct,16 C.C Block production Mixer machine-01 and 28 0.30
manpower

8 Nov,16 C.C Block production Mixer machine-01 and 30 0.30


manpower
9 Dec,16 C.C Block production Mixer machine-01 and 30 0.30
manpower

10 Jan,17 C.C Block production Mixer machine-01 and 30 0.30


manpower

11 Feb,17 C.C Block production and const. guide bunds Mixer machine-01 and 35 0.30
manpower

12 Mar,17 C.C Block production and const. guide bunds Mixer machine-01 and 35 0.30
manpower
Total- 3.15 Crore
UPTODATE PROGRESS FROM KM.103.00 T0 114.30

1
03.00 T0 114.30