You are on page 1of 20

Gravity Sewer

Systems
UPONOR INFRASTRUCTURE
Uponor Gravity Sewer
Systems

Uponor Gravity Sewer Systems 47


Gravity Sewer
Systems

Uponor Gravity Drainage


and Sewer Systems
5.1 Introduction...............................................................................................50
Sewer System Planning & Design.......................................................................52
Sewer System Flow Design.................................................................................59
Gravity Sewer Installation – General Instructions and Supervision....................62
5.2 Uponor Sewer System Ultra Rib 2............................................................67
Approvals & Markings........................................................................................70
Ultra Rib 2 Sewer System Design.......................................................................72
Ultra Rib 2 Sewer System Installation ................................................................73
5.3 Uponor Dupplex Sewer System................................................................79
Approvals & Markings........................................................................................82
Dupplex Sewer System Design...........................................................................83
Dupplex Sewer System Installation................................................................... 84
5.4 Uponor Pre-Insulated Sewer System.......................................................87
Pre-Insulated Sewer System Design.................................................................. 90
Pre-Insulated Sewer System Installation............................................................91
5.5 Uponor PVC Sewer System.......................................................................93
Approvals............................................................................................................95
Markings ........................................................................................................... 96
PVC Gravity Sewer System Installation............................................................. 98
5.6 Uponor PE Stormwater System..............................................................103
Approvals & Markings......................................................................................106
Handling...........................................................................................................107
PE Stormwater System Design.........................................................................108
PE Stormwater System Installation................................................................... 111

48 Uponor Gravity Sewer Systems


5.7 Uponor PP Stormwater System.............................................................. 117

Gravity Sewer
Approvals & Markings......................................................................................120

Systems
PP Stormwater System Design ........................................................................121
PP Stormwater System Installation..................................................................122
5.8 Uponor Chamber Systems....................................................................... 125
Approvals..........................................................................................................129
Chambers in the Drainage Plans.......................................................................130
Uponor Chamber Range...................................................................................133
Chamber Installation.........................................................................................136
5.9 Uponor Drainage System DW.................................................................. 141
Land Drainage Principles .................................................................................143
Approvals .........................................................................................................143
Land Drain Inspection Chambers .....................................................................144
Land Drainage Design......................................................................................145
Land Drainage Plan – Drawings........................................................................146
A  Building Drainage.........................................................................................147
B  Green Area Drainage....................................................................................155
C  Highway Drainage........................................................................................160
Pipe Laying and Backfilling..............................................................................161
Land Drainage Discharge..................................................................................163
5.10 Uponor Field Drainage System ..............................................................164
Field Drainage Principles..................................................................................165

Uponor Gravity Sewer Systems 49


5.1 Introduction
Gravity Sewer
Systems

The plan regulations define the possible Uponor’s plastic storm- and wastewater
building types and geotechnical require- systems offer complete piping solutions,
ments for the site. To minimise the risk from individual house connections to
posed by the negative and unforeseeable trunk networks. Uponor has a range of
environmental effects of storm- and waste- pipe systems suitable for all network
water sewer, investments must be made in designs and applications.
safe, watertight and long-life systems.

Gravity drainage and sewer systems


• Uponor Dupplex Sewer System
• Uponor Ultra Rib 2 Sewer System
• Uponor PVC Sewer System
• Uponor PE Stormwater System
• Uponor PP Stormwater System
• Uponor Chamber System
• Uponor Chamber Packages
• Uponor Modular Chambers
• Uponor Bespoke Chambers

Land drainage
• Uponor Land Drainage System
• Uponor Field Drainage System

50 Uponor Gravity Sewer Systems


Gravity Sewer
Systems
The table below shows the relationship between the system type,
pipe size and the end-use application.

Application
Systems and pipe dimensions Storm- and wastewater sewer Stormwater drainage
Subsurface drainage
Uponor Dupplex Sewer System
160-400 mm x

Uponor PVC Sewer System


160-315 mm x

Uponor Ultra Rib 2 Sewer System


200-560 mm x

Uponor PE Stormwater System


800-1600 mm x

Uponor PP Stormwater System


110-893 mm x

Uponor Land Drainage Systems


50-315 mm x

Table 5.1.1

This introduction section covers the It also provides a background for the
general rules for the structural and flow following product sections.
design of storm- and wastewater sewers.

Uponor Gravity Sewer Systems 51


Sewer System Planning & Design
Gravity Sewer
Systems

A piping plan forms the basis of sewer pipe deformation, i.e. deflection, during
system construction. Such a plan is drawn pipe laying and backfilling is influenced
up on the basis of the pipe system's by the following factors:
functional requirements and a geologi- • pipe installation quality
cal survey of the installation site. Plastic • traffic load
pipes are flexible, functioning interac- • embedment and backfill
tively with the surrounding soil. Pipe material quality
flexibility reduces the load on the pipe, • compaction
while the earth pressure exerted on its • groundwater level
sides increases the pipe’s load carrying
capacity through interaction with the Cross-sectional dimensions and trench
surrounding soil. System design must configuration are presented in a plan
take account of the possible installation drawing, based on the pipes to be in-
of other pipe systems in the same trench, stalled in the trench, and their sizes and
as well as freeze protection and thermal soil characteristics. Common pipe trench
insulation requirements. The degree of dimensions are shown in Figure 5.1.2.

Final backfill
Final backfill
≥ 0.15 m ≥ 0.4 m
≥ 0.15 m
≥ 0.3 m ≥ 0.3 m ≥ 0.2 m
≥ 0.3 m ≥ 0.2 m
≥ 0.4 m ≥ 0.4 m
≥ 0.1 m ≥ 0.15 m
W Sw
≥ 0.15 m Ww
W Ww Sw

Figure 5.1.2. Typical pipe trench dimensions.

52 Uponor Gravity Sewer Systems


Buried pipe behaviour the pipe and its surrounding embedment

Gravity Sewer
and deflection (d) is thereby ensured.

Systems
Soil-pipe interaction exists between
the buried pipe and the embedment If the plastic pipe is supported evenly
(haunching and initial backfill) materials around the entire pipe ring (i.e. circum-
surrounding it. The nature of this inter- ference), the pipe will retain its original
action depends on the characteristics of roundness.
the pipe and surrounding material. The
behaviour of a buried plastic pipe can be When designing plastic gravity sewer
described as follows (Figure 5.1.3). systems and installing plastic piping, it
should be recognised that the embed-
Target ment materials beneath and around
In ideal conditions, the earth and ground- the pipe cannot always be placed in
water pressure are evenly distributed an entirely homogenous manner. Over
around the buried pipe (a). time, what starts off as an even load on
the pipe ring may become uneven and
Practice deviate from the pipe's ideal operating
The backfill above the pipe exerts a conditions. This causes the pipe to un-
load on its upper surface (b). In the dergo deflection, changing from round to
case of gravity sewers, maintaining the slightly oval, due to asymmetric loading
bedding at the required gradient causes with respect to the pipe ring (unevenly
loading on the under-surface of the exerted earth pressure). The deflection
pipe (c). If the pipe receives insufficient of the buried pipe increases, until the
side-support from compacted surround vertical and horizontal components of the
material, its inherent stiffness will be exerted earth pressure are in balance.
insufficient to prevent it from partially
flattening, or 'ovalling', if a load is In order to ensure a long service life,
exerted from above (b+c). This can be pipes must be placed and embedded in
avoided by compacting the material on such a way that, immediately after instal-
both sides of the pipe to form a consoli- lation, any pipe deflection due to the
dated, homogenous surrounding zone. non-homogeneity of the embedment and
Effective structural interaction between backfill materials is as low as possible.

a) b) c) b+c) d)
Compaction

Compaction

Figure 5.1.3 Buried plastic pipe behaviour. Schematic drawing.

Uponor Gravity Sewer Systems 53


As a guideline for the placement and tolerances of different plastic gravity
Gravity Sewer

consolidation of embedment materials, a sewer pipes. Tolerance is calculated as the


Systems

maximum allowable pipe deflection limit percentage change in the outside diam-
should be set for the installed pipe. The eter of the pipe, compared to the pipe’s
limit value is expressed as the maximum nominal outside diameter.
allowable percentage change in the inside
diameter, with respect to the design outer The values in the table represent the
diameter of the pipe, compared to the maximum allowable local deflection
calculated inside diameter of a perfectly 2–3 weeks after installation.
round pipe, as measured after installation.
If pipe deflection measurements carried
The deflection limit primarily depends on out as part of the pipe system’s approval
the pipe material. The maximum deflec- inspection show values in excess of the
tion values are based on the specification tolerances given in Table 5.1.4, the causes
that, if these installation instructions are of the deformation must be determined.
followed, the pipe deflection should not The typical cause is careless placement
exceed 15% during the service life of the and compaction of the pipe bedding
pipe system (50 yrs). and backfill. Based on the measurement
results and the assessment of causes of
When assessing post-installation pipe deflection, deflection monitoring should
deflection, account must be taken of the be considered on a case by case basis.
fact that the plastic pipe may be subject If long-term monitoring is required, a
to ‘ovalling’ deformation during storage. monitoring schedule must be drawn
In such a case, a degree of ovality will be up. Deflection studies show that, if the
present at the time of installation. This external loading on the pipe remains
ovality must be included in the maxi- constant, a plastic pipe typically achieves
mum post-installation deflection limit. dimensional stability within 1-2 years
Table 5.1.4 shows the maximum ovality after installation.

Maximum post-installation cross-sectional ovality and deflection tolerances for plastic gravity sewer
pipes
Pipe material Maximum Maximum cross-sectional
pipe ovality % deflection after installation %
PVC 1 8
PE 2 9
PP 2 8

Table 5.1.4

54 Uponor Gravity Sewer Systems


Installation conditions, for which iv. Mechanical compaction only at

Gravity Sewer
structural calculations are not ≥ 15 cm backfill above the pipe

Systems
required crown.
In the following installation conditions, v. Standard-Proctor compaction
where pipes of at least SN 8 stiffness density: ≥ 95 %.
are used, the load carrying capacity and 3. If the trench is supported, the trench
deflection need not be calculated. shoring must be raised as the haunching
and initial backfill compaction proceeds,
1. Depth of cover to ensure no voids are left when the
a. Min. 1.0 m for traffic loading areas shoring is removed. If this is not done,
and min. 0.8 m for pedestrian areas, the compaction will fail to meet the
yard areas etc. requirements of both demanding and
b. Max. depth of cover 6.0 m normal installation.
2. Pipe installation works must meet 4. Max. pipe diameter 1100 mm
the requirements of the 'demanding' 5. Depth of cover / pipe diameter > 2.0
or 'normal' installation categories, as 6. Bedding or backfill sand or gravel
follows: must be Class 1.
a. Demanding installation category
i. Pipe must be placed on 15 cm Ring stiffness selection – plastic
deep bedding. pipe deflection
ii. The bedding must be levelled and If the installation conditions are as
thoroughly compacted before described above, and all the related
laying the pipe. requirements are met, pipes of the SN 8
iii. Haunching and initial backfill stiffness class can be used.
along the sides of the pipe
thoroughly compacted in max. The chart on the following page shows
20 cm layers. the average deflection of the installed
iv. Mechanical compaction only at pipe (immediately after installation), as
≥ 30 cm backfill above the pipe a function of ring stiffness and of the
crown. installation's classification as demanding
v. Standard-Proctor compaction or normal. These figures are based on
density: ≥ 98 %. extensive measurement trials conducted
b. Normal installation category on installed pipes belonging to these two
i. Pipe must be placed on 15 cm ring stiffness classes.
deep bedding.
ii. The bedding must be levelled and Pipe deflection can continue increasing
thoroughly compacted before for 1–3 years after installation. Experi-
laying the pipe. ence suggests that deflection increases
iii. Haunching and initial backfill by around 1% at demanding installation
along the sides of the pipe sites and by about 2% at normal sites.
thoroughly compacted in
max. 40 cm layers.

Uponor Gravity Sewer Systems 55


Deflection curve
Gravity Sewer

14
Systems

13
Proctor values
12
Excellent > 94 %
11
Moderate 87-94 %
10 No compaction Undetermined
9
8
Deflection [%]

7
6
5
4
No compaction
3
2
Moderate
1
Excellent
0
-1
0 4 8 12 16
SN [kpa]

Diagram 5.1.5

Pipe ovality resulting from deflection af- than that of a round one. The reduction
fects pipe capacity, because the flow ca- in flow rate can be calculated using the
pacity of an oval pipe is marginally lower following table.

Flow rate reduction (%)


10

0
0 5 10 15
Ovality (%)
Diagram 5.1.6

56 Uponor Gravity Sewer Systems


Pipe supports • ensure effective fastening to structures

Gravity Sewer
When installing a sewerage system • ensure sufficiently wide brackets for

Systems
beneath a building, where there is a high plastic pipes, thereby avoiding pipe
risk of the surrounding soil subsiding, the damage.
pipes must be supported. To ensure the
sewer's stability and that it is protected Straight pipes must be supported at each
from damage, support must be provided and every socket. The bracket spacing
using pipe brackets of sufficient quality distance depends on the type of pipe,
and number. Pipes must have no angular the installation requirements and the
deformation and the gradient must earth loading. Support must be properly
remain unchanged over time. executed, to prevent pipe damage and
loosening of the pipe joints.
Support brackets must be made of
corrosion-resistant acid-proof steel. Contact the Uponor Technical Support
Because they corrode and fracture over team for further assistance, if necessary.
time, galvanised and stainless steel
brackets are insufficiently durable. Plas- Support spacing
tic brackets are also unsuitable, due to When supporting PE pipes, the distance
their plasticity: they stretch over time, between brackets must not be too great,
causing the pipe gradient to alter. as this can cause the pipe to bend. The
following tables show the bracket spacing
Key pipe support requirements: for Uponor’s systems.
• ensure that brackets are sufficiently
closely spaced The pipe support design must take differ-
• use corrosion-resistant material ent load factors, such as water pressure
• ensure a stable support system testing and pressure surges, into account.

Interior building pipes

Horizontal sewer
Vertical sewer
Pipe diameter L1 L2 L1 L2
32 0.5 m 2.0 m 1.0 m 2.0 m
50 0.5 m 2.0 m 1.5 m 2.0 m
75 1.0 m 3.0 m 2.0 m 3.0 m
110 1.0 m 3.0 m 2.0 m 3.0 m
160 2.0 m 3.0 m 2.6 m 3.0 m

L1 = distance between brackets


L2 = distance between fixed brackets

Table 5.1.7

Uponor Gravity Sewer Systems 57


Outdoor pipes
Gravity Sewer

Maximum bracket interval (guideline)


Pipe type Horizontal sewer Vertical sewer
Systems

Uponor PVC Sewer System 10 x de (max. 3.0 m) 30 x de (max. 3.0 m)


Ultra Rib 2 10 x de (max. 2.0 m) 30 x de (max. 3.0 m)
Dupplex 10 x de (max. 2.0 m) 30 x de (max. 3.0 m)
Uponor PP Stormwater System 10 x de (max. 2.0 m) 30 x de (max. 3.0 m)
Uponor Pre-Insulated Sewer System 10 x de (max. 2.0 m) 30 x de (max. 3.0m)
Uponor PVC Pressure Pipe System 12 x de (max. 3.0 m) 30 x de (max. 3.0 m)
Uponor PE Pressure Pipe System 10 x de (max. 1.6 m) 30 x de (max. 3.0 m)
ProFuse 10 x de (max. 1.6 m) 25 x de (max. 2.6 m)

Table 5.1.8

Only use brackets specially designed for Insulation requirement


use with plastic pipes. Loose brackets Interior building pipes
allow axial thermal movement of the Plastic pipes generate less condensation
pipe. Since fixed brackets lock the pipe than metal ones. In practice, pipes must
firmly into place, use fixed brackets on always be insulated wherever temperature
sockets and branch sections. Fastenings differences might cause condensation.
and brackets located beneath load- With respect to the insulation of pipe
bearing base floors must be made of lead-throughs, fire safety regulations take
acid-proof steel. precedence over moisture protection.

When hanging socket pipes, a fixed Special requirements for large-


bracket must be installed at the base diameter pipes, stormwater basins,
of each socket. Loose brackets must be inspection chambers and tanks
used between socket joints, to allow Groundwater conditions must be given
thermal movement. When supporting careful consideration in the installation
pressure pipe systems, the need for sup- of large pipes, stormwater basins and
port due to pressure loading must also inspection chambers. Plans must take ac-
be taken into account. count, for example, of hydrostatic uplift,
caused by groundwater, in chambers,
tanks and oil and petrol separators. These
factors are covered in more detail in the
various product sections.

58 Uponor Gravity Sewer Systems


Sewer System Flow Design

Gravity Sewer
Systems
When determining the pipe system’s di- As the chart for a partially filled pipe
mensions, for trouble-free operation it is shows, at this filling ratio the relative
important to ensure that the system has water level is
sufficient flow and self-cleaning capacity. h/di = 0.28
Using a case study, this introductory the relative flow velocity is
section describes the design principles v/vt = 0.76
of storm- and wastewater sewers. The and the relative hydraulic radius is
example given illustrates the design R/Rt = 0.65
method, while the relevant design charts
are presented in the appendix. In the above calculations, the pipe's
outside diameter has been used. When
Gravity sewer design example calculating self-cleaning capacity, how-
The correlation between hydraulic gradi- ever, the inside diameter of the pipe is
ent and flow rate in a full pipe, as well as used, as this gives a more realistic value.
the speed of water flow, can be deter- For example, the inside diameter of a
mined using the flow chart shown below. 250 Dupplex pipe is 216 mm.

From the Uponor Dupplex pipe chart, we Flow velocity


can see, for example, that v= 0.76 x 1.2 ≈ 0.91 m/s
a flow rate (Q) of 20 l/s and Water level
a hydraulic gradient (l) of 6 ‰ 0.28 x 216 ≈ 60.5 mm
h=
(6 mm/m) 0.65 x 216
require the use of a de 250 mm pipe. Hydraulic radius
R = 4 = 35.1 mm
The total capacity of the pipeline is
Qt = 30 l/s
and the flow velocity in a full pipe is
vt = 1.2 m/s
If the minimum flow rate is, for example,
5 l/s, then
Q/Qt = 5/30 = 0.17

Uponor Gravity Sewer Systems 59


The self-cleaning capacity of the pipe can In the above example, the friction stress is
Gravity Sewer

be determined by calculating the friction T = 1000 x 9.81 x 0.006 x 0.0351


Systems

stress using the formula = 2.07 N/m2


T=γxgxIxR
where According to research, a sewer pipeline
T = friction stress N/m2 can be regarded as self-cleaning if its
γ = density of water = 1000 kg/m3 friction stress exceeds 1.0 N/m2. In the
g = acceleration due to gravity above case study, the sewer is self-clean-
= 9.81m/s2 ing, guaranteeing trouble-free operation.
I = gradient m/m If the friction stress is below 1.0 N/m2,
R = hydraulic radius m the sewer gradient should be modified.

Figure 5.1.9

60 Uponor Gravity Sewer Systems


1,0

Gravity Sewer
Systems
0,9

0,8

0,7

0,6
1
Relative water level y/d

3
0,5 2

0,4

0,3

0,2

0,1

0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0 1,1 1,2 1,3

1: Relative flow rate Q/Qf


2: Relative flow velocity v/vf
3: Relative hydraulic radius R/Rf
Figure 5.1.10

Uponor Gravity Sewer Systems 61


Gravity Sewer Installation –
Gravity Sewer

General Instructions and Supervision


Systems

Account must be taken of the specific sions can form beneath the pipe during
conditions at the installation site, and trench filling, and during compaction of
of the installation process, in the project the backfill above the pipe. To prevent
design, installation works and timing collapse or subsidence, pipe trenches in
of installation. To ensure that, when in or near roads and paved areas must be
service, the pipes perform to their full ca- built and backfilled correctly. In certain
pacity, trench excavation, pipe placement cases, trenches in cohesive soils may be
and backfilling must be carried out with left without sloping. The trench width
extreme care and precision. Studies show must allow a space of 0.4 m between the
that careful installation is the single most outermost pipe and the trench wall.
important factor in achieving a good end
result. Ultimately, the developer will de- B. Bedding
cide which installation instructions should The pipes are installed on a bedding
be followed. layer, to provide even support and bring
them to grade. A 15 cm deep bed is
Uponor's instructions for sewer installa- normally sufficient.
tion are presented below.
If natural aggregate is used for the bed-
A. Trench construction ding, the maximum grain size is determined
The trench bottom must be made firm by the pipe's outside diameter. The maxi-
and even throughout, particularly in mum stone size for pipes with an outside
unstable soils where uneven depres- diameter of more than 600 mm is 60 mm.

Backfill
As-dug material.
No >ø30 cm stones
within 1m of
the pipe.

Initial backfill, compacted.


Depth above pipe crown
normally ≥30 cm.
Haunching
up to pipe centerline,
thoroughly compacted.
Bedding, approx. 15 cm of initial backfill material
or subsoil compliant with construction specs.
Level, stoneless foundation.
Width min. pipe diameter + 40 cm.

Figure 5.1.11

62 Uponor Gravity Sewer Systems


The maximum stone size for all pipes with Compaction is carried out in 0.2 m deep

Gravity Sewer
an outside diameter of under 200 mm is layers (compacted depth). It is continued

Systems
20 mm. until the pipe crown is covered by at
least a 0.30 metre layer or, for small pipes
If crushed aggregate is used for bedding, (de > 160 mm), at least a 0.15 m deep
the maximum grain size is 16 mm for all layer. The same material requirements ap-
pipe sizes over 110 mm. ply to initial backfill as to bedding.

The bedding material used must not be D. Final backfill


frozen. In traffic loading areas, the final backfill
material must be compactable. In non-
If the native soil meets the above require- traffic areas 'as-dug' material (both
ments, no additional bedding is required. non-cohesive and cohesive) can generally
Depressions must be made in the bed- be used. Cohesive soils typically cause
ding as necessary, to accommodate the greater deformation than non-cohesive
pipe sockets. ones. The presence of stones in the
initial backfill can cause point loading,
C. Initial backfill and thus pipe deformation. If the as-dug
The function of initial backfill is to give material meets the above criteria and is
the pipe sufficient support on all sides compactable, it can be used as backfill.
and to prevent point loading. In the initial Installation quality must nevertheless
backfill zone, the distance between the be maintained in every respect. Uponor
pipe and the edge of the trench must products are designed to withstand point
be at least 0.4 m, to enable the use of loading deflection of a higher level than
the appropriate compaction equipment. the standardmaximum tolerances.

Compactor type Weight t Optimum No. of NB!


layer thickness compactions*
Vibratory rollers, < 5 ≤ 0,40 3-6 Not suitable for highly
manual 5-8 ≤ 0,60 3-6 cohesive soils
> 8 ≤ 0,80 3-6
Vibratory rollers – 6-8 ≤ 0,60 4-8
self-driven 8-10 ≤ 0,80 4-8
> 10 ≤ 1,00 4-8
Rubber wheel < 20 ≤ 0,30 8-12 Tyre pressure for sandy
rollers > 20 ≤ 0,50 8-12 soils 300 kPa, gravelly
soils 600 kPa
Smooth-wheel approx. 10 ≤ 0,20 5-8 Used mainly for load-
rollers bearing layer compaction
and finishing
Sheepsfoot rollers < 10 ≤ 0,30 6-12 Used for compaction
> 10 ≤ 0,50 3-6 of highly cohesive soils
Plate compactors ≥ 0,05 0,10-0,15 3-6 Normally used only on
≥ 0,10 0,10-0,20 3-6 non-cohesive soils
≥ 0,40 0,15-0,40 3-6
*If the layer depths are reduced, fewer compactions are necessary. The compaction speed is chosen
according to the compactor manufacturer’s recommendation. Source KT 02.
Table 5.1.12. Use of mechanical compactors

Uponor Gravity Sewer Systems 63


Installation control and monitoring Freeze protection and thermal
Gravity Sewer

In order to avoid pipe deformation, qual- insulation


Systems

ity control monitoring is essential with The purpose of freeze protection and/or
regard to sufficient soil load-bearing thermal insulation is to prevent the water
capacity, bedding depth, gradient, initial in pipes and chambers from freezing, and
backfill and proper compaction. Quality thereby causing pipe system damage,
control of gravity sewer installation is during periods of ground frost. Water
carried out by monitoring ± deviations freezing can cause blockages and damage
from elevation and alignment limits, and pipes and chambers.
through the approval and monitoring of
tightness testing. In addition, flushing The depth of installation of pipelines
and camera inspections are increasingly depends, for example, on
used in post-installation inspection. • the frost susceptibility of the soil
• the groundwater level
Gravity sewer tightness testing • the degree of pipe heat loss
Water tightness testing is carried out at • the locality (extent of freezing)
sites where air tightness cannot be tested
due to the groundwater level. These tests Pipe system freezing can be prevented
are not aimed at testing material or joint by installing thermal insulation and/or
strengths. freeze protection, such as ground frost
insulation boards and/or lightweight
In a water tightness test, the closed net- aggregate, or by using pre-insulated
work is filled with water and low pressure systems such as Uponor’s pre-insulated
is applied. The tightness is determined sewer system.
based on the volume of water at the
inspection end of the network. Air tight- In locations where the ground does not
ness testing follows the same principle as freeze, such as in rock, wrap-around
water tightness, but using air instead of thermal insulation is installed around
water. The network's tightness is deter- the pipes. In frost-susceptible ground,
mined based on the pressure loss over a freeze protection is installed on the upper
set time period. Pressure test values and part of the pipes. This also prevents
rejection and approval limits are specified the ground underneath the pipes from
in detail in the above standard. freezing. In both cases, heating cables
can be installed for additional protection.
Records are made of the tightness tests.
These include, for example, the developer
and/or contractor, test conditions, test
equipment, pipe gradient, test pressures,
test duration, the date and the signatures
of all parties.

64 Uponor Gravity Sewer Systems


The planning and design of freeze

Gravity Sewer
protection is influenced by the following

Systems
key factors:
• thermal properties of the oil or rock
• quantity and temperature of water in
the pipe
• minimum allowable temperature of
the conveyed fluid
• local climatic conditions
• installation depth.

Figure 5.1.13. Correlation between cold content (maximum cold content per 50 years, in hours) and
average ground frost penetration depth in different soil strata and different conditions.

Uponor Gravity Sewer Systems 65


66

You might also like