Professional Documents
Culture Documents
Table of Contents
1 Project and Process ............................................................................................. 2
1.1 Description of Works............................................................................................... 2
1.2 Requirements ........................................................................................................... 3
1.2.1 Design .............................................................................................................................. 3
1.2.2 Site Visit ........................................................................................................................... 3
1.2.3 Site Access ...................................................................................................................... 3
1.2.4 Equipment Installation & Disruption to Pool Operation............................................. 3
1.2.5 Commissioning, testing, handover and documentation............................................ 4
2 General Requirements ......................................................................................... 4
2.1 Standard of Materials and Workmanship ............................................................. 4
2.2 Performance-based specification .......................................................................... 4
2.3 Materials.................................................................................................................... 5
2.4 Supply and Metering ............................................................................................... 5
2.5 Circuit Protection ..................................................................................................... 5
2.6 Cutting, Fixing, Drilling and Making Good ........................................................... 5
2.7 Wiring Methods ........................................................................................................ 6
2.8 Fastening and Fastening Materials ....................................................................... 6
2.9 Reticulation............................................................................................................... 6
2.10 Warranty and Free Service ..................................................................................... 7
3 Technical Requirements ...................................................................................... 7
3.1 Performance Requirements.................................................................................... 7
3.1.1 Pool Specs....................................................................................................................... 7
3.1.2 Plant Location ................................................................................................................. 8
3.1.3 Heating Requirements ................................................................................................... 9
3.1.4 Heating Capacity Requirements .................................................................................. 9
3.2 Control and Configuration ...................................................................................... 9
3.3 Equipotential Bonding ............................................................................................ 9
3.4 Standards Compliance .......................................................................................... 10
3.5 Schedule A –Heat Pump Proposal Outline ......................................................... 10
Specific System Features: ................................................................................................ 11
3.6 Methodology ........................................................................................................... 12
3.6.1 Proposed Installation Schedule .................................................................................. 12
3.6.2 Partial Installation ......................................................................................................... 12
3.6.3 Construction Schedule................................................................................................. 12
The Birrong Leisure and Aquatic Centre (BLAC) is open seven days per
week throughout the year.
The 50m outdoor pool is currently heated by 2 x Hunt Gas Boilers and this
system is nearing the end of its life and a replacement is required that will
achieve the target operational temperature through the year, will provide
notable energy efficiency by minimizing consumption and delivering
ongoing value over its operational lifetime.
The contractor will supply, install, integrate and commission the heat pumps
for the outdoor pool and do so in a manner that does not impact the service
provision. It is expected that the new system will be installed and ready for
commissioning on the same day the existing system is taken off line.
1.2.1 Design
The final detailed specification, electrical and control design must follow
industry best practice, and meet the performance specifications outlined in
this document.
The contractor will review and document existing plant, and supporting
infrastructure, including circulation pumps, plumbing connection and
electrical infrastructure.
The contractor will be responsible for ensuring any remaining plant room
pipework is flushed and cleaned of debris before connecting any heat
pump equipment to the system.
This project must be completed without disruption to normal pool operation. This
includes disruption caused by construction works in general and to outdoor pool
heating during replacement.
A testing schedule for heating and hot water supply, in line with
manufacturer documentation, will be provided by the contractor for on-site
commissioning in writing and via a sign off process for the heat pump
system.
The contractor shall carry out commissioning and final acceptance tests
as required by manufacturer’s guidelines. Final acceptance tests shall
conform with AS/NZS 3000 and AS/NZS 3017 standards.
2 General Requirements
2.3 Materials
Note that the new heat pump installation must be monitored by a suitable
electrical sub-meter for purposed of monitoring performance.
Nuts, bolts, screws, washers, etc. used as terminals shall be brass. All
fasteners are to be corrosion resistant.
2.9 Reticulation
The cost of all labour and materials expended in complying with the above
shall be borne by the Contractor.
3 Technical Requirements
To heat the pool (as specified in 4.1.1) to the target temperature (26°C , or
within no greater than 1°C below) through standard Sydney climatic
conditions (excluding 1 in 10 year weather events), during opening hours.
Length 50m
Width 21m
Total surface area 1050m2 (plus balance tank)
Average depth 1.3m
Balance tank volume Approx. 50,000 Litres
Balance tank area 3.0m x 4m x 4m (approx.)
Balance tank location Underground (50m Plant)
Normal Opening hours November to March
Mon - Friday: 5am-7pm
Sat & Sun: 6am-6pm
April to October
Mon - Friday: 5am-7pm
Sat & Sun: 6am-5pm
Backwash Volume Approx. 50,000L
Backwash frequency Once every 28 days in winter
(design months)
Once every 14 days in
summer
Filter type Atlas UFF – Perlite Media
Figure 1: Aerial view of site
Heat pumps are to be installed at the existing outdoor pool heating plant
location, outside the plant room to the north east of the pool.
Figure 2: Aerial zoom of pool pump room and compound area for new heating system location
3.1.3 Heating Requirements
Specifically, if a single unit within the heating plant is off line, at least 2/3 of
the heating capacity shall be available to operate unaffected and
independently controlled.
Preference will be given for control systems with flexibility and functionality
that improves performance and energy-consumption, for example, the
capacity to specify heating levels for two different daily time intervals.
This includes all metal pumps, valves, strainers, heat pumps, pipe work
and other fixed metallic parts or fittings, which are not part of the electrical
equipment but are more than 100 mm in any one direction).
3.4 Standards Compliance
All relevant design, supply and installation Australian Standards must be
adhered to, including but not limited to:
Heat Capacity
(at 25°C ambient air temperature)
COP
(at 25°C ambient air temperature)
Variation of COP with temperature (per °C)
Assumed inlet water temperature at rated
Heat Capacity and COP
Refrigerant Type
Maximum outlet water temperature
Components
Compressor type (scroll, axial)
Heat exchanger metal composition (eg
304/316 s/s, cupronickel, titanium)
Heat exchanger type
Flow Rate
Defrost type
Size per unit (LxWxH)
Noise Level
VSD
Maintenance requirements
Major Maintenance
Plant Frequency
Compressor
Heat Exchanger/Coil
Condenser fan
Electrical Supply:
Warranty:
Warranty type
Duration
Heat pump design and functionality differs significantly – list any other specific
design advantages of your offering, or attach product documentation.
3.6 Methodology