Professional Documents
Culture Documents
Session 24, 25
Dr Abdelaziz Berrado
EGR2302-Engineering Economics 1
Al Akhawayn University
Topics to Be Covered in Today’s Lecture
EGR2302-Engineering Economics 3
Al Akhawayn University
8.1 Ranking Inconsistency
EGR2302-Engineering Economics 4
Al Akhawayn University
8.1 An Example – Shows Ranking
Inconsistency Problem
EGR2302-Engineering Economics 5
Al Akhawayn University
8.1 Two Projects; A and B
•A $120
0 1 2 3 4 5
$100
$201.14
•B
0 1 2 3 4 5
$100
EGR2302-Engineering Economics 6
Al Akhawayn University
8.1 Example Problem
EGR2302-Engineering Economics 7
Al Akhawayn University
8.1 Look at A and assume Reinvestment
forward to t = 5
• Reinvest the $120 out to t = 5
$120
0 1 2 3 4 5
$100
EGR2302-Engineering Economics 8
Al Akhawayn University
8.1 Look at A and assume Reinvestment
forward to t = 5
F5 = ?
• Find F5 for Alt. A
$120
0 1 2 3 4 5
$100
•F5 = 120(F/P,10%,4)=$175.69
EGR2302-Engineering Economics 9
Al Akhawayn University
8.1 ROR of A given reinvestment
• -100 +120(F/P,10%,4)(P/F,i*A,5) = 0
•Solving for i*A
•(P/F, i*A,5) = 0.569
• i*A/reinvestment @10% = 0.1193
•i*A/c=10% = 11.93%
EGR2302-Engineering Economics 10
Al Akhawayn University
8.1 Now Compare A to B
• Compare revised A with reinvestment at 10% to B
•i*A/C=10% = 11.93%
•i*B = 15% as before
•ROR Rankings:
•B is superior to A (15% > 11.93%)
EGR2302-Engineering Economics 11
Al Akhawayn University
8.1 Ranking Inconsistency…
• Occurs between ROR and PW because
•Both methods have different reinvestment
rate assumptions
•Two different cash flows may not generate
funds at the same rate
EGR2302-Engineering Economics 12
Al Akhawayn University
Section 8.2: ROR for Mutually
Exclusive Projects
•Given Two or more alternatives
•Rank the investments based upon their initial
time t = 0 investment requirements
•Summarize the investments in a tabular format
EGR2302-Engineering Economics 13
Al Akhawayn University
8.2 Tabular Format
t Alt. A Alt. B B-A
0 $ $
1 $ $
2 $ $
… … …
Find the ROR of this
N $
investment $ is
which
(B – A)
EGR2302-Engineering Economics 14
Al Akhawayn University
8.2 Ranking Rules
• Given two or more Mutually Exclusive
investments
•Select the first investment to be the one with the
lowest time t = 0 investment amount.
•The next investment is to be the one with the
largest investment at time t = 0
EGR2302-Engineering Economics 15
Al Akhawayn University
8.2 Example
• Two Investments: A and B
• A costs $30,000 at time t = 0
• B costs $50,000 at time t = 0
•MARR = 10%
•Life is 4 years
EGR2302-Engineering Economics 16
Al Akhawayn University
8.2 Example: A and B
• For this problem, A
is superior to B based
on PW and on ROR!
•A is ranked first;
•B is ranked second
•Both alternatives have
a PW > 0 and have i*’s
> MARR.
•Both are feasible
alternatives initially.
EGR2302-Engineering Economics 17
Al Akhawayn University
8.2 Form the Difference (B – A)
• For mutually exclusive alternatives…
•One should focus on the differences between the
alternatives
•“Differences” are illustrated best by forming
what is called the incremental investment (B-A)
EGR2302-Engineering Economics 18
Al Akhawayn University
8.2 Incremental Investment
A B (B-A)
Find the
ROR of this
investment
Lowest Next
The
First Highest first
Cost Cost = Incremental
investment
investment investment
EGR2302-Engineering Economics 19
Al Akhawayn University
8.2 Incremental Investment
B-A
EGR2302-Engineering Economics 20
Al Akhawayn University
8.2 The logic….
EGR2302-Engineering Economics 22
Al Akhawayn University
8.2 Explaining….continued
A B (B-A)
EGR2302-Engineering Economics 24
Al Akhawayn University
8.2 Is it worth it?
• Now the question is….
•Is it worth spending an additional $20,000 to
move from investment A to investment B?
•Answer: Compute the ROR or PW of the
incremental investment to see!
EGR2302-Engineering Economics 25
Al Akhawayn University
8.2 Analysis
• For this problem, NPV(10%) < 0
• and, no ROR could be found!
EGR2302-Engineering Economics 26
Al Akhawayn University
8.2 Another Example
•Cash Flows are shown on the next slide
• Two alternatives
•Semiautomatic machine vs.
•Automatic machine
•Assume a 6 year life for analysis
EGR2302-Engineering Economics 27
Al Akhawayn University
8.2 Example
Year SemiAuto Auto (B-A)
A B
0 -$40,000 -$90,000 -$50,000
EGR2302-Engineering Economics 28
Al Akhawayn University
8.2 Analysis
• Computed PW @
18% shows that B
has the lowest PW
cost and would be
preferred to A
EGR2302-Engineering Economics 29
Al Akhawayn University
8.2 Incremental
(B-A)
Cash Flow
•Question?
0 -$50,000 •Is it worth spending an
additional $50,000 in the
1 15,000
automatic machine in order to
2 15,000 receive the incremental savings
shown to the left?
3 50,000
•Compute the ROR of the
4 15,000 incremental Cash Flow
5 15,000
6 21,000
EGR2302-Engineering Economics 30
Al Akhawayn University
8.2 Incremental ROR = 35.95%
EGR2302-Engineering Economics 31
Al Akhawayn University
8.2: NPV Plot of A and B
• A is equivalent to B @ Incremental ROR rate of
35.95%
NPV PLOT-INC. C.F.
0.00
00
10
20
30
40
50
60
70
80
90
00
10
20
30
40
50
60
70
80
90
00
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
1.
1.
1.
1.
1.
1.
1.
1.
1.
1.
2.
-100000.00
-200000.00
-300000.00
NPV(i%)
-400000.00
-500000.00
-600000.00
-700000.00
-800000.00
Disc. Rates
EGR2302-Engineering Economics 32
Al Akhawayn University
8.2: i* (B-A) = 35.95%
• The incremental i*(B-A) is greater than the firm’s
discount rate of 18%
EGR2302-Engineering Economics 33
Al Akhawayn University
Section 8.3 Interpretations of ROR
• The i*incremental is the ROR of the additional or
incremental investment required to move from
one project to the next most costly project
EGR2302-Engineering Economics 34
Al Akhawayn University
8.3 Multiple Alternatives
• If Cost-Revenue Problem…
•Calculate the computed i*’s for each alternative
in the set
•Discard those alternatives whose i* value is less
than the MARR – they would lose anyway!
EGR2302-Engineering Economics 35
Al Akhawayn University
8.3 Independent Projects
• If dealing with independent projects, one
does not compute incremental investments
among the candidate projects
•Rule: Accept all projects whose ROR > MARR
and stay within any budget limitations
EGR2302-Engineering Economics 36
Al Akhawayn University
8.3 The i* (B-A) value
• Given two mutually exclusive alternatives,
A and B.
EGR2302-Engineering Economics 37
Al Akhawayn University
8.4 ROR Using PW: Incremental
and Breakeven– Mutually Exclusive Case
• Selection between multiple mutually
exclusive alternatives by the IROR method.
•If unequal lives – either establish a
common project life or,
•Apply the LCM of life approach found in
chapter 5
EGR2302-Engineering Economics 38
Al Akhawayn University
8.4 PW Approach – Mutually
Exclusive Case
EGR2302-Engineering Economics 39
Al Akhawayn University
8.4 PW Approach – Mutually
Exclusive Case
• Compute the incremental cash flow (B-A)
• Given the MARR find the PW of (B-A)
investment
• If PW(MARR) of (B-A) is >0; accept the
increment – go with the higher investment
cost alternative.
•Else, reject the increment and go with the
lower investment cost option
EGR2302-Engineering Economics 40
Al Akhawayn University
8.4 ROR Case – Unique i* (B-A)
• Compose the incremental Cash Flow
•Examine that cash flow for sign changes and
apply the Norstrom test (from Chapter 7)
•If a unique i* (B-A) is indicated – solve for it
and compare it to the MARR
•If i* (B-A) > MARR, accept the increment else
reject
EGR2302-Engineering Economics 41
Al Akhawayn University
8.4 Example 8.3 Bell/GTE
•10 year project (merger)
•New equipment is required
•Two vendors
•MARR = 15%
•Which vendor should be selected
•Cost or Service Problem
EGR2302-Engineering Economics 42
Al Akhawayn University
8.4 Setup A vs.PW(15%)
B shows
that A has the
lowest PW Cost and
should win!
EGR2302-Engineering Economics 43
Al Akhawayn University
8.4 PW analysis
• We could stop because the PW(15%) has
signaled that A is the winner!
•Lowest PW cost
•Proceed with a ROR analysis BUT….
•ROR must be performed on the incremental
investment
EGR2302-Engineering Economics 44
Al Akhawayn University
8.4 Incremental Cash Flow Fig. 8-2
EGR2302-Engineering Economics 45
Al Akhawayn University
8.4 Inc. Cash Flow Results
i* (B-A) is less
Inc. PV(15%)
and is than the
negative. MARR of
Thus, reject 15%.
the increment Reject
and go with A! increment
and go with
A!
EGR2302-Engineering Economics 46
Al Akhawayn University
8.4 So-called Breakeven ROR
• Recall, the incremental i*(B-A) is the interest rate
at which the two alternatives are economically
equivalent.
•This special interest rate is called:
•Breakeven Interest Rate
•Fisherian Intersection Rate
EGR2302-Engineering Economics 47
Al Akhawayn University
8.4 Breakeven Rate Illustrated
• For Example 8.3 the NPV Plot is:
NPV PLOT-INC. C.F.
0.00
0
0
-5000.00
0
0
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
1.
1.
1.
1.
1.
1.
1.
1.
1.
1.
2.
-10000.00
-15000.00
-20000.00
NPV(i%)
-40000.00
-45000.00
-50000.00
Disc. Rates
EGR2302-Engineering Economics 48
Al Akhawayn University
8.4 Conclusions i* (B-A) = 12.65%
• For MARR < 12.65% extra investment is
justified. Go with B
•For MARR > 12.65%, the extra investment is not
justified: Go with A
•If MARR = 12.65%, both options are
economically equivalent.
Recall: MARR = 15%
EGR2302-Engineering Economics 49
Al Akhawayn University
8.5 ROR Evaluation Using Annual
Worth based relation
• ROR approach requires comparison over an
equal-service life
•When the lives are equal or unequal (Must use
LCM), set up the AW relationship for the cash
flows of each alternative
•Then solve 0 = AWB – AWA for the i* value
EGR2302-Engineering Economics 50
Al Akhawayn University
8.5 ROR Using Annual Worth
• See Example 8.5
•Manual approach
•It is best to avoid this approach and stay with
either the PW or ROR over the total life of the
project or the LCM life
EGR2302-Engineering Economics 51
Al Akhawayn University
8.6 Incremental ROR Analysis of Multiple,
Mutually Exclusive Alternatives: Criteria
EGR2302-Engineering Economics 52
Al Akhawayn University
8.6 Comparing Alternatives
EGR2302-Engineering Economics 53
Al Akhawayn University
8.6 Ranking Rules - Ordering
1. Order the alternatives from smallest to largest
initial investment
2. Compute the cash flows for each alternative
(assume or create equal lives)
3. If the alternatives are revenue-cost
alternatives do the following…
EGR2302-Engineering Economics 54
Al Akhawayn University
8.6 Revenue-Cost Problems
4. Compute the i* value for all alternatives in
the considered set.
•If any alternative has an i* < MARR drop it from
further consideration
•The candidate set will be those alternatives with
computed i* values > MARR.
•Call this the FEASIBLE set
EGR2302-Engineering Economics 55
Al Akhawayn University
8.6 Revenue-Cost - Approach
• Calculate i* for the first alternative
•The first alternative is called the DEFENDER
•The second (next higher investment cost)
alternative is called the CHALLENGER
•Compute the incremental cash flow as
•(Challenger – Defender)
EGR2302-Engineering Economics 56
Al Akhawayn University
8.6 Revenue-Cost
4. Compute i*Challenger – Defender
•If i*Challenger – Defender > MARR drop the defender
and the challenger wins the current round.
5. If i* Challenger – Defender < MARR, drop the
challenger and the defender moves on to the next
comparison round
EGR2302-Engineering Economics 57
Al Akhawayn University
8.6 Revenue-Cost
• At each round, a winner is determined
•Either be the current Defender or the current
challenger
•The winner of a given round moves to the next
round and becomes the current DEFENDER and is
compared to the next challenger
EGR2302-Engineering Economics 58
Al Akhawayn University
8.6 Revenue-Cost
6. This process continues until there are no
more challengers remaining.
•The alternative that remains after all alternatives
have been evaluated is the final winner.
EGR2302-Engineering Economics 59
Al Akhawayn University
8.6 Potential Problems
• See Example 8.6 for the potential problems that
can occur using ROR
•Pitfalls often exist when one uses the ROR
approach for the analysis of alternatives
EGR2302-Engineering Economics 60
Al Akhawayn University
8.6 Cost Problems
• Remember
•Cost problems do not have computed ROR’s
since there are more cost amounts than revenue
amounts (salvage values may exist)
•Thus there are no feasible i*’s for each
alternative
EGR2302-Engineering Economics 61
Al Akhawayn University
8.6 Cost Problems - Rules
• Rank the alternatives according to their
investment requirements (low to high)
•For the first round compare:
•Challenger – Defender Cash Flow
•Compute i*Challenger – Defender
EGR2302-Engineering Economics 62
Al Akhawayn University
8.6 Cost Problems
• The current winner now becomes the defender
for the next round.
•Compare the current defender to the next
challenger and compute i* Challenger – Defender
•The winner becomes the current champion and
moves to the next round as the defender
•Repeat until all alternatives have been
compared.
EGR2302-Engineering Economics 63
Al Akhawayn University
Chapter 8 Summary
•PW and AW methods are preferred methods for
evaluating alternatives
•ROR can be used but care must be taken
•If ROR, must perform an incremental analysis
•Two at a time (paired comparison) is required
EGR2302-Engineering Economics 64
Al Akhawayn University
Assignments and Announcements
EGR2302-Engineering Economics 65
Al Akhawayn University