Project: 18-1154/ Hog's Back

2 Week Schedule
Prepared by: Joel Van Beek

Month & Date: November 26 27 28 29 30 1 2 3 4 5 6 7

Item M T W T F S S M T W T F
1 Finish Mobilizing site x
2 Key In silt fence (or place peastone if ground is still frozen) x x
3 remove brush from bank where cofferdam is being installed x
4 Install fast fence gates and silt fence from staging area to cofferdam x
5 install fast fence gates to allow for pedestrian traffic x
6 install phase 1 turbidity curtian x
7 excavate topsoil x
8 install mud matt/ gravel access road to top of cofferdam x
9 install video camera x x
10 screen stockpiled rock x x x x x x
11 Start install of cofferdam (based on approvel Nov. 28th) x
12 Continue install phase 1 cofferdam rock fill x x x
13 add phase 2 turbidity curtian x
14 Continue install phase 1 cofferdam rock fill x x
15 add phase 3 turbidity curtian x
16 continue install phase 1 cofferdam rock fill x x
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Deliverables
1 Latest Sheetpile delivery x
2 ODS Marine (Dec 10th)
3 Latest Liner delivery x
4 Rig Welder (Dec 10)