You are on page 1of 1

BRONTE CONSTRUCTION

PRE-PAVE CHECKLIST
This checklist should be performed by the Foreman and the Project Coordinator, a copy of this form must be emailed to the
construction manager and superintendent the day before the schedule paving operations
Project Number & Name Date
Element Mix Number
Total Asphalt Ordered (t) [2.2 - 2.4 t/m3] Spacing (min)
Contract Drawings Reviewed? ☐ Y ☐ N Dwg. Number(s):
Contract Specifications Reviewed? ☐ Y ☐ N Spec Number(s):

☐ OPSS.MUNI ☐ 310 OPSS.PROV ☐ 310 OPSS ☐ OPSS 1003


Applicable Specifications Reviewed?
☐ OPSS 1101 ☐ OPSS 1103 ☐ OPSS 1150 ☐ OPSS 1151
Milled Surface
Existing asphalt milled to correct Dim? ☐ Y ☐ N ☐ N/A Cracks/Holes repaired? ☐ Y ☐ N ☐ N/A
Existing asphalt milled to correct Elev? ☐ Y ☐ N ☐ N/A Elev. Layout Complete?
Lap Joints have Straight Clean Vertical Cuts, 40 mm deep? ☐ Y ☐ N ☐ N/A
Tack Coat
Tack Coat on site? ☐ Y ☐ N Product Name
Quantity of Tack Coat On Site Tack Coat Yield?
Tack Coat Applicator on site? ☐ Y ☐ N Applicator tested? ☐ Y ☐ N
Granular Base
Elevations/Alignment Verified? ☐ Y ☐ N Cross-Fall Check w/ Straight-Edge? ☐ Y ☐ N
Straight Edge is 3 m metal edge? ☐ Y ☐ N Granular Dry? ☐ Y ☐ N
Roadbed not Frozen? ☐ Y ☐ N Free of Standing Water? ☐ Y ☐ N
Compaction Test Completed ☐ Y ☐ N Compaction Result
Temperature
Surface Course Min Air Temp (celcius) Base Layer Min Air Temp
Compaction

Compaction Equipment meets weight and size requirements of Specifications? ☐ Y ☐ N

Ensure that sub-layers and surface layer have reached min 50OC prior to allowing traffic? ☐ Y ☐ N

Laser Level on Site to Confirm Alignment and Elevations at various points? ☐ Y ☐ N

3 m Straight-Edge on Site to Verify Cross-Fall and Smoothness ☐ Y ☐ N

Line Painting

Line Painting Immediately Required? ☐ Y ☐ N Layout Sketched Out? ☐ Y ☐ N

Health and Safety

Personnel wearing appropriate PPE? ☐ Y ☐ N Hazards Identified? ☐ Y ☐ N

Form 1000 & WSIB from Sub? ☐ Y ☐ N Guardrails In Place? ☐ Y ☐ N


Accountable and Responsible Staff
Proj. Coord Name: Foreman Name: Super Name:

Proj. Coordinator Sig: Foreman Sig: Super Sig:

Page 1 of 1

You might also like