Project Manager
Welding group
Lifting group
Piping group
Mechan.group
Steel group
Line group
Test group
Elec.group
M
Total 18 persons
2. Construction equipment
Management.
3.2.1 Set-up
a. Invesigate working field;
b. Auditing construction drawing, take attend the technique hands overh and construction
drawing audited;
c. Comply the construction plan、schem etc.
d. Comply the manpower plan、construction equipment plan and the quality assurance plan.
e. Enhancing a profession training for the personnel, carrying on a quality education and raising
a whole member quality consciousness;
f. Regarding the various construction crafts, techniques all should run before of construction
project and construction measure;
g. Regarding the the engineering design, construction crux, construction counterplan and
technique measure, standard know completely;
h. Construction equipment, water despense and electricity all have already arranged.
3.2.2 General Provision
a.The construction place should carry on unifying programme.The preservation of equipments
should carry on "the water turbo-generator install, transport, preservation condition"
performance.The equipment store field should be consider the loading ability;
b. To choose the assembly method according with the site condition and the main part should
particularly consider the technical measurement for installation;
c. the draft parts which be used for the installation have to meet diagram paper provision,
certificate required for the main material of point part, such as have no certificate or have doubt
to the quality should be checked, meet to request rear quasi- usage;
d. The main welding line should be finished by the welder passed the SD263-88 provision
examination. The welding craftwork should be conform to the standard DL-5017-93. Earthing
line should fixed the welding part.
e. Check the combination surface with ruler, the burr、clearance accord with the requirement of
the standard GB8564-2003 item 2.0.6.
f. Clean the equipment, regarding to the finish machining clean the grease with soft tool.check
the tolerance of the main part of the equipment.
g. Check the slot of the part and oil resistance of the oil system. Connector of the seal not biger
than 0.1mm.
h. Check all the screw with the driver before installation, fix the bolt、nut and the pin should be
fixed with the design or welding.
i. Setting certain number of assembly axes in fastness and nakedness. Difference should be
controlled under ±0.5mm.
3.2.3 Survey Instruments
The special installation tool and survey instruments should be ready for the work:
a. Steel ruler precision 1/10000;
b. J2 theodolite;
c. S3 water level
d. Knife ruler length 150ram and 300mm;
e. Survey ruler with magnetism seat.
Tubular Seat
Runner
Generator Shaft
Oil Feeder
Preparatory work;
Rail installation;concreting
Fram assembly
No-load running
f
F
C
S L1 L2
Fig.1
b.king post levels curving f≤L/2000, but does not surpass 20mm most greatly, this value is
from the leaving lap approximately 100mm of the web plate.
c . On king post lap horizontal deflection b≤B/200. this value may survey from the
reinforcement plate before no building rail.
d . King post web plate vertical oblique b≤H /500 this value surveyed from the long
reinforcement plate.
e.Crane frame diagonal line ∣D1-D2∣≤5mm.
f . The king post host web plate wave inspected by the 1m flat scale, in leaves in lap H/3
region not to be bigger than 0.7δ,Other regions are not bigger than 1.0δ.
g . A leg in the span direction verticality h1≤H1/2000, its inclined direction is mutually
symmetrical. With the alternative means can guarantee the headstock gear span, this item may
not take examination.
h.The bogie rail installation should satisfy the following request:
(1)When the gauge is smaller than or is equal to 2.5m, does not surpass 2mm; When the
gauge is bigger than 2.5m, does not surpass 3mm;
(2)The relative difference of the bogie span T1, T2 does not surpass 2mm when the gauge is
smaller than or is equal to 2.5m;
( 3 ) The bogie track height difference in identical lateral section, when gauge
T≤2.5m,C≤5mm;
(4)Bogie track middle line and orbital beam web plate middle line position deviation: axle
box beam δ≤12mm, d≤6mm,δ≥12mm when d≤δ/2. To single plate-web girder and girder truss
d≤δ/2;
( 5 ) The bogie orbit center straight dimension is not bigger than 3mm (only permits to
platform side raised tune);
(6)The bogie track should be with the king post flange plate close fitting, when the partial
gap is bigger than 0.5mm and the length surpasses 200mm,Should add the tie plate;
(7)The bogie rail joint should satisfy the following request:
①The rail joint place height misses C ≤1mm;
②The rail joint place dislocation g≤1mm;
③The rail joint place gap dose not bigger than 2mm;
(8)The bogie track is curving in the lateral part, is not bigger than 1mm willfully in the 2m
scope;
(9)The movement mechanism installation should satisfy the following request:
①When the crane span is smaller than or was equal to 10 meters, its span deviation is not
bigger than 3 mm, also the both sides span relative difference is not bigger than 3mm; When the
span is bigger than 10 meters, its span deviation is not bigger than ±5mm, also the both sides
span relative difference is not bigger than 5mm;
②Wheel horizontal deflection P ≤L/1000, L is the survey length, also any pair of wheel oblique
direction should be opposite on the identical axial line.
5.5.7 Electric Equipment Installation
a.Equipment inspection
( 1 ) The power distribution and the control board appearance should make the detailed
inspection, should conform to the state technical standard. The equipment has the data plate and
the product technology document is complete;
(2)The cabinet outward appearance integrity, does not have the damage, does not have the
distortion, the non-corrosion phenomenon, is not obviously affected with damp, the equipment
structural style and the protection rank should conform to the standard requirement;
(3)The insulation material is good, the electrical connection should be reliable, the wire
mark should be clear.
b.The cabinet and resistor installation
(1)The cabinet should carry on the installation according to the blueprint order of rank,
fixes with 4 M12mm galvanized screws in the foundation channel steel, the allowance difference
verticality: smaller than 1.5mm/m ; Levelness: The neighboring two cabinet crown is smaller
than 2mm, falls in is smaller than 5mm; Undulation: The neighboring two cabinet crown is
smaller than 1mm, falls in is smaller than 5mm; Between the cabinet the slit is smaller than 2mm.
The cabinet body and the cabinet body, the cabinet body and the side back plate apply the
galvanized screw connection;
(2)The outdoors type switchboard should install correctly reliable, and has the rainproof ;
(3)The resistance box vertical folds installs should not surpass 4 box, surpasses 4 box to be
supposed to adopt the support to be fixed.
c.Trolley line, the support, insulator installation:
( 1 ) The trolley line support installation should conform to the relevant requirement, the
support installation should straight reliable, and in identical horizontal plane;
( 2 ) The trolley line installtion should be straight, the trolley line center and crane track
actual middle line maintenance parallel;
(3)The flexible cable sling and the free suspension trolley line installation: should conform
to the following requirement: The mechanical strength of the terminal attachment system and the
tightening device should conform to the requirement, the terminal tightening device adjustment
remainder should conform to the relevant specification requirement; Relax deviation between the
trolley line is not bigger than 20mm; Between the trolley line and the end instrument insulation
should be reliable;
(4)The flexible cable installtion should conform to the following requirement: adopt the
sectional steel for the flexible cable chute, the section should install straight, the chute should
straight smooth, the mechanical strength conform to the requirement. The suspension unit moves
along the chute should be nimble, not have the beat, does not have the jamming; The flexible
cable moves length compared to the crane is away from long 15% to 20%, install the traction
rope, and its length should shorter than the move length of the flexible cable.
(5)To spread the electric compound grease in the bus duct rabbet, when the engine driver
move, the electric conduction block glide steady, the contact good, does not have the jamming,
the beat, braves the spark phenomenon.
d.The electric cable, the electric wire laying and distributing
(1)Besides the light current system, should use 500V and above rated voltage copper core
stranded wire or the electric cable, and the section does not smaller than 1.5mm2;
(2)The electric wire or the electric cable should be installed in the steel pipe, the trunking or
the guard shield; The steel pipe, the trunking should fix reliably; The orifice should have
protection wrap, the trunking exit be supposed to have the protective measures;
(3)The electric cable, the electric wire should arrange neatly, not suitable overlapping, the
intensity and the light current cable separates the placing suitably, the electric cable both sides
should have the electric cable sign;
(4)When electric cable fixed placing, its bevelling radius should be bigger than the electric
cable outer diameter 5 times, when the electric cable moves the placing, its bevelling radius
should be bigger than the outer diameter 8 times;
(5)The electric cable, the electric wire match the line to be supposed to arrange neatly, both
sides of the wire should compression-join the corresponding binding clamp reliably, and should
have the obvious wiring serial number.
(6)Electrical device testing and electrical looping simulation testing.
①The hoist crane isolator, the air switch, AC contactor and so on installation to be supposed to
conform to the standard requirement;
② The power switch should be placed appooaches the crane on the ground, and its terminal
can not be connected other electric consumer.
③The hoist crane should be equipped the power switch, and its terminal can not be connected
other electric consumer.
④The isolating switch should be equipped on the crane, and the switch should have obvious
effective disconnecting distance when it is opening, the breaker or the fuse should be equipped
on the short circuit protection purpose on the power supply looping.
⑤ Inspect the reliability of the limit switch、the rammer switch、the console switch and the
operating button;
⑥ Inspect the accuracy of the electric looping , and its insulation resistance value is not lower
than 0.5MΩ;
⑦ To check the reliability and the accuracy of the electric looping by the functional simulation
test.
e.Earthing
(1) The electrical equipment outer covering, the conduit and the voltage step down to
secondary circuit side should be reliable connected with the steel structure;
(2) The steel structure should adopt null line or earthing protection according to the LV system
earthing specifications, adopts the reliable single item short circuit protection or the leakage
protective device separately;
(3) Each track of the crane should set two reliable earths, the electrical cross-over should make
in the joint between the track end; the earth resistance should satisfy the design request, and not
lower than 4Ω;
(4) When cab be connected by the bolts with the hoist crane , carries on the electrical cross-
over. The cross-over position cannot be short in two, and the multi-core wire those sectional area
cannot be smaller than 16mm2.
f.Illumination equipment installation
(1) The special-purpose null line or the insulating transformer will be set in the illuminates
looping, illuminates power should not be failure after the crane power shut down.
(2)Tthe safety transformer or the isolating transformer installation should be reliable, the
insulation is good;
(3) The cab and the corridor have the appropriate illumination when the crane is working;
(4) The portable lamp device voltage should not be higher than 36V.
5.5.8 Trial rRun
a.Inspection before trial run
(1) inspect all machine parts, connecting parts and each kind of protective device and the
lubrication system, the oiling result should conform to the requirement; then eliminates all
sundries both sides of rack;
(2) inspect steel wire end fixed should be reliable, in the reel, the direction of the block pulley
is correct;
(3) inspect the electric cable reel, central electric conduction installation, skid wire,
transformer, as well as various electrical wiring、earthing correct;
(4) check the rotation and speed of the travel mechanism motor which are synchronization or
not;
(5) starting the various brake wheel by hand rolling 360 degree no jamming phenomenon.
b. Noload test run
Lifting mechanism travel the range three times and check the electric and mechnical parts as
following:
(1) motor running smooth as well as the three phase current;
(2) electric equipment no abnormal heat as well as the controller contactor;
(3) limit switch, protective device and interlocking device should be in good working condition;
(4) the limit plate of the wheel cannot be touched the rack when bogie and the crane working;
(5) electric device no jamming、running smooth and no serious open fire when bogie and the
crane working;
(6) all mechanical parts should not have the impact sound and other unusual sounds as they
running;
(7) the brake shoe should leave the brake pulley and don’t have any friction during it operation;
(8) all bearings and the gear should have good lubrication, and those temperature should not
surpass 65C;
(9) the noise can not bigger than 85dB(A) in the cab by window closed.
c. static load test
The static load test is to check the load capacity of the various parts of the headstock gear and
steel structure.
Lifts the rated load (increase to rated load gradually), carry out the shuttle operation. The
performance should achieve the design request, removes the load to stop the bogie at the end of
the main beam and get the reference point. Then lifts the 1.25times of the rated load 100 to
200mm above the ground maintaining not less than 10mins. Then removes the load, inspects the
equipment whether it has the permanent deformation. Repeat those three times and the crane
frame should not have any permanent deformation. Drives the bogie to the end, the actual camber
value and the curls upwards value not to be smaller than: The cross 0.7 L /1000, the cantalever
end 0.7 L1 (or L2) /350; then drive the bogie to stop in the cross or the cantilever end, lift the
rated load and inspect the main beam deflection value (and on curls upwards value by actual
camber value to calculate) was not bigger than: the cross L /700 ;the cantilever end L1(orL2)
/350.
Any part of the crane do not have broken, joint loosen or damage after the testing.
d. Dynamic load test
Lift 1.1 times of fixed load test. Start two mechanisms simultaneously according to the design
request, repeat such action: starting, operation, shut down, clockwise, reverse maintaining 1h at
least. Various mechanism should act keenly, work steady reliable, various limit switch, the
security interlocking device should act correctly reliable, various spare parts should not have
damage phenomena, various attachment points do not have any loosen.
5.5.9 Acceptance
a. Check and inspection should be carried by the installation team according with the blue
drawing and the following terms; after inspection the qualified side can be carried on the
approval process; then it can be brought into operation.
b. The following technical documentations should be hand over :
(1) installation as-built drawing;
(2) design amendment davice;
(3) the setting-out record and test record of the installation dimension; the static and dynamic
load test;
(4) the welding seam inspection report and record;
(5) the major deflection treatment record;
(6) the all documentations from the equipment manufacturer.
Hand over of the finishing documentations Testing & acceptance of the equipment
1. the preparatory work
(1) Verify the construction drawing、construction regulations、standard and technical document;
a. The chief engineer is responsible for getting the professional engineers to verify the
construction drawing, records of the verification and judgment shall be well kept;
Prepara the construction equipment and main material procurement plan in accorandance with
the material and equipment sheet;
Get staff studying the safety regulations、installation technical specification、the relevant drawing
and technical paper, technical coordination and judgement should be done by the professional
engineer;
Prepare the installation method statement and technical measurement for the key equipment and
the installation process;
Be aware of the construction requirement and the special installation craftworks noted on the
drawing.
Prepare the installation progress schedule
Prepare the electric equipment installation planning programe on the basis of the M/E installation
schedule, and the annual 、 quarter and month plan would be prepared upon the site
progress.During preparation of the schedule,we should comprehensively understand each kind of
electric equipment installation quantities as well as civil engineering progress and so on, upon
which the installation progress would be arranged in single item or unit works to be finished on
time.
The general requirements of progress schedule preparation:
The electric embedded works excuted together with the civil engineering and the finishing works
to avoid missing any items;
b. the primary work which will be influnced the construction time limit will be given the woking
face priority to reduce the working fastigium, to insure the instllation can be carried
continuously;
c. regarding the cross-working surface the effective measure should be taken to avoid the
different working face disturbing each other and note the safety working;
d. the debugging and commissioning time should be taken in account in the comprehensive
progress;
e. take any effective measures to avoid the natural influence during construction;
f. the construction progress should be excuted to insure the safety and quality;
g. combined working with civil engineering and finishing works should be taken into account
comprehensively;
h. check the condition of the equipment and main material arrived so as to draft the auxiliary
material procurement plan.
2. working face checking
According to the design drawing and installation documentations, the working face can be
classified into two kinds:the embedment face of foundation and embedded parts, the equipment
installation face; the hydraulic structure holes、equipment foundation and installation face shall
be checked whether they meet the design requirement or installaiton condition by the
construction technician and supervision engineer.The installaiton level and location will be
surveyed by water level and tape and marked with red paint, if any unconformity found written
proposal will be submmited to the site supervision engineer.
3. foundation and embedment
Before embedding of the foundation and embedment parts , technical clarification will be done
by the engineer in charge and the working group on the basis of design drawing 、 installation
documentation、design amendment notificaiton and supervision notification, the principle of no
impeded the progress schedule, the requirement of the relevant regulations and specifications,
setting out the embedment location applied by the theodolite 、 water level and tape after that
carrying on the embedment process and the record will be well kept.
4. acceptance of the embeded parts
After the embedment works finished and passed the three kinds of checks, it can be turned over
to pouring concrete when supervision engineer justify it qualified and sign the paper.
5. Equipment foundation installation
The electric equipment's foundation instllation mainly means the installation of the foundation
rack of the main transformer and the section beam of the electric board foundation, installaiton
method see clause 3.
6. equipment and apparatus acceptance & testing
The equipment and apparatus arrived at site will be checked by the technician、housekeeper、the
supervision engineer and the representative of the client according to the requirements of the
design、bill of the order、packing list、instruction book and the relevant regulation specifications,
after that it can be stored and kept in the warehouse as the ISO9001 standard.Any equipment and
apparatus need to be tested should be carried out the kind of testing according to the state
standard and the relevant requirements by the qualified tester.Any disqualified equipment and
apparatus found written proposal promptly will be submmited to the site supervision engineer
and the client.
7. Equipment installation
Equipment will be installed on the time schedule in good quality according to the design
requirement and the state standard regulations and specifications.
8. inspection and testing
Each of the equipment installed should be carried out the three kind of checks according to the
requirements and the relevant state standard and regulations, the qualified equipment again
would be carried out the relevant kind of tests and the stimulation testing according to the
regulations and specificaiton by the professional qualified tester.
9. trouble-shooting test
The installed equipment can be turned into the commissioning test after it was signed and
qualified by the supervision engineer 、 design department 、 the client and the commissioning
committee's approval.
10. Handing over the documentations
In the purpose of operate and manage the unit, all the documentations will be handed over to the
client in one month after the trail run test.
5.6.3 10KV Electric Equipment Installation
Installation procedure of the 10KV electric equipment of the power house, top of dam and the
ship lock.
Preparation work
LV ciubcle installation
HV board installation
control board and
Busbar installation
installation
installation
Dry type transformer
Diesel generator
Cable check & test Sub item simulation Entire interlock test Trial run
test
1.Preparation work, embedded foundation and equipment acceptance & storge
(1) preparation work
a. to know and understand the construction drawing 、regulations、specification and technical
paper;
(a) to examine the construction drawing and collect the items which need to be clarified by the
design department;
(b) examine and check the main materials sheet to draft the procurement plan;
(c) all the staff should learn and understand the safety operation regulations, installation technical
regulations;
(d) to draft the major equipment installation scheme and technical measurement;
(e) note the installation requirement on the construction drawing and the special installation
craftwork as well;
b. draft the installation graph
set down the electric equipment installation time schedule according to the M/E installation
overall planning; and the monthly、quarter and annual installation construction planning will be
draft upon the exact progress on site;
The general requirements of progress schedule preparation:
(a) the electric embedded works excuted together with the civil engineering and the finishing
works to avoid missing any items;
(b) the primary work which will be influnced the construction time limit will be given the
working face priority to reduce the working fastigium, to insure the installation can be carried out
continuously;
(c) to avoid the different working face disturbing each other, and insure safety working;
(d) the testing run and the commissioning time should be taken into account in the
comprehensive progress;
(e) take any effective measures to avoid influence from naturae during the construction;
(f) the construction progress should be carried on under the safety and quality;
(g) civil construction、fitment or relative engineering and work should be considered sufficiently..
(h) verify equipments and materials. Make a list of assitant materials.
(2) foundation and parts embedded
On the basis of the design drawing, the relvant installation documentation and the revised design
paper; after the technique understanding, use theodolite, lever and curve ruler to set out and
position the reference point upon the E/M installation regulation and specifications. All the
technique and installation data should be recorded and filed after embedment work.
(3) equipment inspection, acceptance and storage
After the equipment arrived at the site, which will be inspected by the client, supervision
engineer and the keeper of the construction company upon the design equipment list, shipping
list etc. the equipment, which have been checked and conformed with the design requirement and
the relevant regulation & specification, will be stored according to the ISO9002 management
system.
2. cable rack, cable tray installation
The cable tray mostly installed along the wall or under the floor, also it should bear stress and
weight, ensure it is reliable and have good-looking.Therefore the product can be used after the
quality examination by the third part qualified organization, its structure should satisfy the
intensity, the rigidity and the stable request, its model, the specification,the material quality
should conform to the design requirement.To avoid the different working face disturbing each
other during the installation, and ensure safety working;a flexible joint will be applied to install
each of the 20m of the cable tray on the line installation. The installation procedure: fasten the
connecting plate with the bolt at the side of the tray; and the leave the other side of the nut
loosely.
The installation requirements:
1) the installtion of the cable holder and the cable tray should be arranged on the one level and
vertical;
2) the installation of the cable holder and the cable tray should have the same grade of the slope
with the working face, the cable tray should have proper eathing and the connectiong of the tray
should be protected by the flxible wire;
3) the cable holder, the cable tray should be leveled off and reliable, the arrangement is neat,
even, the height should be controlled on one level, the allowable deviation ≤ 5mm;
4) the cable holder keeps off to the ditch horizontally, the floor 、the ditch sole distance should
conform to the design requirement;
5) the fabrication and installation of the cable holder should be conformed to the design
requirement;
6) the welding seam of the cable holder and cable tray should be brushed the anti-corrosive
varnish and the paint, and the paint level have to be completed;
7) each of the cable holder should have proper earthing, the flexible wire should be applied to
install as the earthing conductor at the joint of the cable holder;
3. HV/LV cubice, control board, power distribution box and the control board installation
1) HV/LV cubice, control board, power distribution box and the control board installation
Installation
filtation Vacuum oiling Test run
Pipeline wiring
Lamps and
lanterns setting
Lightening switch
test
Check and
handling over
2. technical requirement
(1) tube arrangement
Twisted wire tube is arranged according to relative standards. Nozzle and channel should be
protected.
(2) nema wiring:
a. least section of insulated wire is 1mm2 (copper core)
b. No tie-in, wring. Well insulate.
e. the surface distance between naked current-carrying part (380V) and non-insulating part
≥20m.
f. connect firmly and rightly. Draw out insulating tubes on the board
g. load distribution should be in requirement, phase insulating resistance≥0.5MΩ
(5) lighting instrument installtion
a. fittings should not be damaged. Wire should meet fixed standards
b. requirements for installation of lights、laterns、switches and jacks
Install evenly, firmly and correctly. Phase and wire are cut off by switches. Jacks of AC, DC or
different voltage on the same site should be obviously varied from each other..
c. wire of mental halid light should be connected by connecting column. Power source should not
close to its surface.
d. lights, laterns, triggers, current limiter should be matched to use.
e. base of floodlight should be fixed firm. Light axes direction meets practical requirement. Pivot
should be pinned tightly
f. illuminative light should be specially signed
5.6.6 The Earthing System
The earthing system installation mainly means the earthing of the station service transformer、the
electrical motor machine etc.
transformer neutral point and outer case grounding
The low-pressure side zero line, outer case grounding and resistance value of the transformer
should comply with the design requirements. The connection with the grounding line is by
galvanized flat steel and the steel hole on the equipment side should be fastened with earth stud
while welding will be adopted on the earth trunck line side with the welding length of twice flat
steel (also 3 ridge welded at least)
(2) electric machine shell grounding
The connection with the grounding line is by galvanized flat steel and the steel hole on the
equipment side should be fastened with earth stud while welding will be adopted on the earth
trunck line side with the welding length of twice flat steel (also 3 ridge welded at least)
(3) electric appliance metal outer case grounding
a. AC and neutral points non-grounding :the electric equipments metal outer case should be
connected with the grounding apparatus while the electric appliance and lighting facilities metal
case with the bottom seat.(see the grounding drawings )
b. the metal shell and non-sheathing shell,1-2 shield core thread of the metal metallic sheath
,steel pipe layed and cable bracket of the power cable and controlling cable should be
grounded .The grounding thread of the cable head through zero-phase current transformer should
be grounded through the mutual inductor ;the cable head metallic shell and cable metal skin in
front of the grounding point should be insulated from earth.
c. the metal truss equipped with the electric apparatus grounding
The grounding thread connection is doen by welding without any crack .The pipe grounding may
adopt ground clip and thread clip to connect.The grounding thread connected to electric
apparatus should use galvanized stud and the grounding thread connected with DC current
electric apparatus use metal structure .
(4) grounding for semi-equipment installation
The grounding part of the electric apparatus should be connected with the grounding trunk line
from the grounding line singular .The connection with several grounding parts on the grounding
line will not be permitted.
2. electric equipment grounding
The electric apparatus such as logic ground ,power ground ,security ground and signal ground
should comply with the design regulation and the requirements as bellows:
(1) the consolidation of grounding busbar should insulated with board and boxes.
(2) the large and medium computer should adopt the copper core insulator with conformed
section.
(3) grounding network or grounding resistance value should comply with design requirements..
3. Lightning rod(line,band)production and grounding
(1) lightning rod production
Before producing lightning rod, we may be familiar with the drawing, be sure that all the
operation is to accord with the draft, the materials up to grade, welding up to requirements and
pay attention to the lightning rod concentricity and measurement at random during putting
together and welding.
(2) the connection between the lightning rod and down lead adopt welding connection. The
fastness of the down lead and grounding device adopt galvanized production. When the stud non-
galvanized is used ,antisepticise measure should be adopted.
(3) Set up cut-off clip equipped with protection in the place 1.5-1.8mm away from each down
lead as the lightning measure on the architecture adopt many pieces of down lead..The down lead
should be layed along with the outer wall and grounding by a minimal path.
(4) Check the appearance to be sure that the appearance is normal and the basic layout is to pass
the check and acceptance method before lightning rod installation. The lightning rod and
grounding device installation adopt the construction procedure from up to down. The
concentrated grounding device is installed firstly, down lead secondly.
(5) The lightning rod installation is on the basis of the drawing and control strictly the instllation
gravity.
5.6.7 Communication System Equipment Installation
A. communication apparatus installation working range of the power station
1. program controlling dispatch machine, power wave carrier, wiring equipments and power
source apparatus.
2. power wave carrier joint equipment
3. communication cable ,branch box and phone,etc.
B. Equipment check and acceptance
1. The communication equipment ,apparatus and auxiliaries of the project check and acceptance
should comply with the contract technical conditions and standard requirements with record.
Deal with the equipment with defections before installation.
(2) The construction materials and devices purchased should be checked and be with the quality
testment. Substitutes should be permitted to use by the supervising engineer party.
C. installation requirements
1. All the concealed project should be checked according to the design drawing ahead of pouring
concrete. If there is something missed and incorrect ,we may report to the client and cooperate
with them to deal with.Take the effective measures to make sure the on-site condition clean and
to install under the fixed temperature ,humidity and dustness.
2. The communication system connection and test should be done on the basis of the design and
all the wiring cables ,consumer cables ,high frequency cables ,power cables and grounding cables
used for the communication system should be the complete base cable without junction.
3. Set up the distribution frame and cross-connecting box together for the dispatching machine
telephone switch board or other communication equipments equipped. The route should be
confirmed on the basis of principle mentioned as bellows and the special layout requirement for
different line layout ways: choose the obvious bound ,and keep the wiring area bound tidy: the
consumer of the wiring area are concentrated to distribute lines; the consumer in a same
dispatching machine telephone system should be assigned into a same wiring area ;the
partitioning of the wiring area should base on the cross-connecting box and power cable capacity
and in the convenience of the future wiring adjustment.
4. The line route will be confirmed generally according to the principle mentioned below and the
route layout special requirements:
(1) The line route should be short and straight, safe and stable for convenience of construction
and maintenance .
(2) keep the main cable route and wiring cable route in a same step in order for pulling up and
dispatching .
(3) Try to avoid from the cable destroyable part and decrease internal cross of other obstacles
such as other pipes.
5. The power cable position put in the pipe hole should keep uniform from front to back .the
usage order of the pipe hole is from down to up, from side to middle. The lower two sides holes
is suitable to use for main power cable and mid-continual power cable. Each tube hole should put
one power cable.
5.6.8 Electric Device Test
1. debug work regulations
(1) the technical quality of the debug staffs
a. debug leading official
(a) possess university diploma or more professional theoretical level and three years or more
practical debug experiences.
(b) be familiar with and grasp the power station electric device and computer supervising and
controlling system working principle ,debug method and requirements.
(c) Apply expertly with the power station electric device and computer supervising and
controlling system debug mode and the country standard and field standard quoted inside the
regulations
(d) be responsible for compiling the hydraulic station electric device and computer supervising
and controlling system debug brief and test measurements.
(e) be familiar and grasp all the apparatus ,meter used in debug and debug equipment theory,
functions and usage.
(f) arrange and guide debug staff to do debug work.
(g) solve the common technical problems occurred in debug independently 、 verify and collect
the debug record and conclusion.
b. debug personnel
(a) possess the college diploma or equaled or more professional theoretical level and one year or
more practical working experiences .
(b) be familiar with the power station electric device and computer supervising and controlling
system working principle ,debug method and requirements
(c) know about the power station electric device and computer supervising and controlling
system debug regulation and country standard and field standard .
(d) use correctly the apparatus ,meter and debug equipments in debug.
(e) examine ,calculate and fill in parameters and data correctly inside the debug project.
(2) debug meter and apparatus
a. the debug ,apparatus meter in the construction unit and the specification ,quantity ,variety and
measure accuracy of the equipment and tools should satisfy the different type power station
electric device and computer supervising and controlling system debug needs.
b. all the apparatus and meter of the debug should pass the third class or more by the examination
of the electric meter unit measure till grade.
(3) debug personnel technical training and test technical measure in test.
a. Before debug the debug manager should arrange the staff to study the theory with practice
such as the design drawing ,production specification ,debug method and meter, apparatus usage
way and operation and so on .The production factory and design unit should do the technical
coordination before power station debug for the same model device of the first suit.
b. the debug of power station electric device and computer supervising and controlling system
should be done after the basic completion and through three-check conformity. The three-check
policy and quality management should be implemented during the whole debug process.
c. compile the commissioning prescript and experiment measure on the basis of regulation and
standard which list the test items and confirm test steps and ways .Confirm the position of the
supervising point in the test or examined hole number and actual measure allowance deviation
,the special apparatus ,meter specification in the test.
d. Do the debug initial report and debug test report according to the relative clauses offered in the
power station electric device and computer supervising and controlling system regulations.
(4) regulations and standards
electric device installation engineering electric equipment handing over test standards
large-medium style hydroelectric static rectification excitation system and device test regulations
DL496-92 turbine electro-hydraulic adjustable system and device adjustable test regulations
GB14285-93 relaying protection and safety automatic device technical regulations
static relaying protection and safety automatic device general technical situation
water conservancy ministry relaying protection and power net safety automatic device check
clauses
GB/T15145-94 microcomputer line protection device general technical conditions
DL483-92 static reclosing device technical conditions
DL/T526-93 stand-by electric power automatic input device technical conditions
DL479-92 static distance protection device technical conditions
DL/T528-93 static power station reverse power protection device technical conditions
DL/T 529-93 static power station dense protection device technical conditions
SD281-88 static power station rotor grounding protection device technical conditions
SD282-88 static power station stator grounding protection device technical conditions
SD276-88 static retio differential protection device technical conditions
SD283-88 static voltage relay technical conditions
SD 284-88 static current relaying technical conditions
SD 285-88 static time relay technical conditions
GB 3453 data communication basic controlling regulations
GB3454 data terminal (DTE) and data circuit terminal equipment (interface definition among
DCE)
IEEE802.3 net technical standards
GB23128 operating system standards
DL476 power system real time data communication practical layer agreement
JB/T5234 industrial controlling computer system acceptance outline
DL/T 5081-1997 hydroelectric automatic design regulations
the related GB,IEC,IEEE,ISO,ANSI,DIN,JH,JIE standards
2. electric device commissioning
(1) generator
a .measure stator winding insulation resistance and absorb ratio
b. measure stator winding direct current resistance
c. stator winding direct current pressure test and leakage current measurement
d. stator winding AC pressure test
e. measure stator winding insulation resistance
f. measure rator winding DC resistance
g. stator winding AC pressure test
h. measure power station excitation back circuit and insulation resistance connected with it
(unincluding stator rator insulation resistance)
i. electric machine excitation back circuit and AC pressure test of the jointed equipments(not
including power station rator parts)
j. stator iron core test
k. measure the insulation bearing and rator inlet bracket insulation resistance of the generator
l. measure the insulation resistance of the embedded thermodetector and examine temperature
deviation
m. measure de-excitation resistance ,DC resistance of the synchronism resistor
n. measure rator winding AC resistance and reaction and power loss
o. measure and record triphase short circuit characteristics curve
p. measure and record idle-load characteristics curve
q. measure the de-excitation time constant of the generator stator opening circuit
r. measure the residual pressure of the generator automatic de-excitation device disparting brake.
s. measure phase sequence
t. measure axis voltage
(2) power transformer
a. a measure winding and insulation resistance connected with sleeve
b. b check all tap transformation ratio
c. c check the transformer tri-phase tie line and single-phase transformer lead-out wire polarity
d. measure winding group and insulation resistance ,absorbed ratio and polarization index
e. tgδ measure winding group and medium loss angle tangent value tgδ
f. measure winding and DC leakage current connected with sleeve
g. the AC pressure test of the winding connected with sleeve(under the supervision of the
transformer production factory test engineers ,do induction pressure test
h. winding connected sleeve partial discharge test
i. measure each fastener of the iron core insulation and sleeve insulation resistance against outer
case from iron core grounding .
j. nsulation oil test
k. lashing switching off test under rated voltage
l. check phase
m. check noises
n. controlling protection equipment test
o. controlling protection equipment running test
p. cooling device check test
(3) SF6 breaker
a. a measure insulation pulling lever insulation resistance
b. measure phase conductance loop resistance
c. AC pressure test
d. measure breaker cutting and closing switch time
e. measure breaker switching off or on speed
f. measure breaker switching off or on coil insulation resistance and DC resistance
g. breaker operating apparatus test
h. measure sulphur hexafluoride gassy content
i. seal test
j. gas density relay ,pressure meter and pressure action valve examination
(4) mutual inductor
a. measure winding insulation resistance
b. the winding connected sleeve tube against the outer case AC pressure test
c. tgδ c measure 35KV and more mutual inductor once winding connected sleeve medium loss
angle tangent tgδ.
d. d measure voltage inductor once winding DC resistance
e. measure 1000V or more voltage inductor idle load current and excitation characteristics
f. measure current inductor excitation characteristics curve
g. check inductor tri-phase tie line grouping and single phase inductor leading out polarity
h. check inductor change ratio
i. measure iron core clipping bolt insulation resistance
j. partial discharge test
(5) lightning arrester
a. measure insulation resistance
b. measure conductance or leakage current and check combination component non-line
coefficient
c. measure metal oxide arrester continual current
d measure metal oxide arrester power frequency reference voltage or DC reference voltage
e. measure FS type valve arrester power frequency discharge voltage
f. check discharge counter action condition and seat insulation resistance
(6) generator excitation system and device test
a. excitation transformer test
b. series transformer test
c. excitation converter test
d. magnetic field breaker and excitation switch test
e. heavy duty rectifier test
f. pulse transformer test
g. non-line resistance test
h. silicon controlling cross-over machine test
i. excitation system parts insulation examination and dielectric test
j. automatic excitation regulator basic units ,auxiliary unit test
k. automatic excitation regulator overall static characteristic test
l. excitation system operation ,protection ,supervision ,signal and interface backward loop test
m. excitation ,pressure decreasing and reversible de-excitation characteristics test
n. measure automatic excitation regulator each adjustable channel voltage range and fixed
voltage changing speed
o.with the automatic excitation regulator generator voltage frequency characteristics
p. automatic/manual and two sets alternative test of automatic regulated channel
q. manual controlling unit regulation test
r. 10% stepped respond test under generator idle load condition
s. rectification power chamber cooling system examination
t. noises test
u. even stream and even pressure examination of the excitation system power unit
v. generator with automatic excitation regulator voltage differential ration examination
w. generator reactive load adjust and reflection load test
x. generator de-excitation test under idle and rated work condition
y. each auxiliary function unit and protection ,examination unit rectifying and action correctness
test
z. excitation system 72 hours continual running under the rated work condition
(7) speed governing system and device test
appearance check
meters and relay check and acceptance
electric machine connecting line check
pressure signalyzer and oil signal rectification
oil pressure device automatic running simulation test
power supply check test
frequency measurement tache test
amplifier test
transient feed-back loop test
electric regulator test
speed regulation device electric-hydraulic test of the rotation indicative check microcomputer
each part component initial adjust under the manual condition before fill in oil
each part of component adjustment test under manual condition of low oil pressure
each part of component precise adjustment test under the rated oil pressure manual condition
each part of component adjustment test under the automatic condition
each part of component of blade controlling adjustment test
displacement transducer adjustment test
the adjustment test of the relay switching on or off and urgency stopping magnetic valve
frequency and power given loop test
electric-hydraulic speed regulation device static characteristics test and rotation speed dead area
examination
liquid speed regulation device active characteristics test
relay examination under the static time
operating loop check and simulation action test
the electric regulation device leakage capacity and oil consumed quantity examination
abnormal function check test
electric liquid regulation device anti-interference ability test
hand movement logging on test
gear plate speed examine device characteristics test
the rotation speed swinging value examination under hand movement of the idle load condition
automatic switching off or on test
electric liquid regulation system anti-interference test
load reflection test
accident low oil pressure closed blade test
72 hours continual running test with load
(10) relay protection and automatic device test
appearance check of device
current, voltage introducer and back loop check
the relative device and loop check equipped inside the breaker and isolation switching on or off
gearing
the relative operating signal equipment and loop check
the machinery part of the relay and auxiliary equipment .
the relative loop insulation check and pressure test
electric function of the relay and auxiliary equipment
interaction and rectified value rectification test
conditions provided with in the complete group test .
5.6.9 computer supervisory control system installation and debug
5.6.9.1 supervisory control system installation
1. The supervisory control system of the power station includes 7 area units,2 sets of main engine
and operator workstation ,1 set of engineer station and emulation training workstation ,one set of
factory terminal and two sets of telecommunication servicer ,one set of print service and two
prints and control desks and so on.
2. All the system is a gradation distributing opening system, the quadruplet arrangement of the
machine unit LCU is beside powerhouse .The switch station LCU and public LCU arrangement
is inside the central controlling chamber of the auxiliary room.The main machine and operating
station ,engineer station and imitation training station and telecommunicating servicer
arrangements in the computer room of the auxiliary room.The factory director terminal
arrangement is in his own office.
5.6.9.2 supervising system debug
1.the functions of hydroelectric station computer supervising system
The central controlling chamber computer setting and operating station share the same or
isolated one ,double machine redundancy device, automatic change-over device and clock
synchronizing system .It is mainly responsible for generating electricity of power plant machine
sets controlling, auto voltage controlling (AVC),limit over and condition changing accent alarm ,
event order recording, integrated data processing ,trend record analysis ,event settlement
reminding and automatic settlement of sound ,light ,phone image alarm and so on. It also
includes making out invoice of the operating ticket , appearing ,editing and printing ,all kinds of
report forms calling up and timing printing ,communicating with present terrain_class LCU and
the functions of man machine interface.
The terrain-grade computer or hypogyny machine is responsible for machine sets sequential
control ;terrain data collection and arrangement; switching station ,public utility control, safety
supervision ,event sequential detection and transmission ;terrain operation and supervision ;quasi
synchronization of machine sets. The communication with the main chamber : transmit the data
collected by LUC to the main-controlling grade computer correctly, receive the controlling
demand from the main-controlling computer and echo the result to it.
The engineer station ,functions as protecting supervising system and expiring system software
and editing ,repairing application software ;train the working and manage staffs in the plant
;supervisory controlling system gateway with the outside functions etc.
2. computer supervisory controlling system debug
After the equipments installation and making other equipments which is not included in this
installation abundant safety precautions, adjust the computer supervisory controlling system then
due to the safety operating regulation strictly to ensure the debug may not influence other
equipments working and the safety of the staffs who are examining and installing .the debug
including:
(1) circuit examine
According to the computer supervisory controlling system drawings from the factory and
designing institute, check the inner and outer connections carefully .check till the interface
terminal of the computer supervisory controlling system as for checking the outer connection. Be
sure all kinds of sensors , transmitters and meter connection lines are correct and power source
circuit ,twice circuit insulation resistance, and earth resistance conform to the requirements.
(2) switching on apparatus
Switching on and starting item by item and step by step. Check the running condition ,network
configuration and internet applications. After starting , check and diagnose the working condition
of the running system and the complete system.
(3) test
the computer supervisory controlling system continually and completely and confirm the ///time
due to technic agreement requirements .Arrange the professionals to guard and pay attention to
the equipment temperature ,working condition and ///condition.
Or it will be done after other debugs of the system completion, which combines with the 72-hour
commissioning of the turbine .The time will be fixed according to the ordering technical
conditions of the computer supervisory controlling system and spot plan .
(4) the software application debug
Check the central chamber supervisory screen ,running report forms ,historical measuring point
definition ,event report forms ,operating keyboard definition ,voice alarm sentences ,operating
ticket functions data-base definition, AGC, AVC controls parameter and boundary condition,
outer communicate data,
(5) input/output (1/0)joint debug and check
Debug the input and output joint end correspondingly on the basis of schematic of the back
circuit for each LCU :
Input /output (DI/DO)check: kick the simulation actual transporting signal of the supervisory
controlling system joint terminal to be sure that the local LCU can receive the signal; if the
system demand ,each of output amount should have the reliable signal outlet ,the corresponding
joint should have correct signal jump or action to relay.The signal definition ,signal name and
signal address should be correct and also with the event order and time scaling.
The simulation amount input check and debug: import the corresponding signal on the basis of
the needs ,choose the different points from the smallest to the largest range to examine to see
whether the calculation correct or not and the measure deviation of the system should accord
with the regulation and skill requirements .
The simulation export check and debug: the simulation amount export of the power station is to
provide for governor and excitation device controlling adjust without the simulation amount
import control fixed .So the simulation amount export check examination of the supervisory
controlling system is done according to the system device from the export demand of the system
and adopt the corresponding examine apparatus such as oscilloscope on the basis of signal form .
Pulsed quantity import check and debug : import the corresponding signal ,check the received
condition and set the calculation formula on the basis of the kilowatt-hour meter technical
parameters .Examine to be sure the measure deviation should be with the regulation and technical
requirements .
(6) singular point linkage test
The workload and external factors involved are very large in the singular linkage test and debug
process ,so every point of the linkage test will be treated well and carefully .Examine each
apparatus action condition and feedback signal correctness from demand out of the operation
station of the power station center chamber linked with the local instruments .the qualitative
analysis from the original terminal import signal will be done for CT,PT and simulation amount
backcircuit .The linkage items are as bellows:
The unit controlling LCU :the unit auxiliary instrument control such as the lubricating oil
pump ,high voltage jack oil pump ,governor oil pump ,leakage pump ,generator cooling wind
machine ,generator mechanism brake ,electric valve ,generator switch ; all sorts of unit signals
such as current ,voltage ,frequency ,temperature ,lubrication oil flow amount and instrument
action position signals and set protection system.
The switch instrument controlling LCU unit: direct current system, factory power supply
system ,leakage drainage pump ,repairing water drainage pump ,compressor,trash rack rake
differential pressure and upper and lower beam water level system.
(7) corresponding device simulation test
Switching station instrument controlling LCU unit: all the brakers, isolation knives, earth knives ,
CT, PT signals and cable protection system inside of the switching station .
The center chamber fixed with simulation screen, examine the simulation screen meter indicator
and signal indicator in the singular point linkage test process.
The corresponding device is important in the supervisory controlling system and the
corresponding deviation will destroy the power station unimaginable .Use the protection measure
meter to export 100 V voltage simulation set PT voltage and governor to adjust the system
voltage to 100V simulation system PT voltage in the process of debug .With safety
measurements start-up the corresponding procedures to compare with the qualified
corresponding meter to be sure that the corresponding device should judge and measure system
side voltage ,set side voltage and catch the corresponding points correctly.
This test can also be done under the state of all the corresponding conditions available
(8) sequential control flow test
Step into the sequential control flow test after the singular linkage test. A complete flow test with
the local instruments will be done for each segment flow. Change the instruments flow
unsatisfied in time .
(9) The main flow of the set LCU is the set auto-braker earth knife, isolation knife linkage
operation procedures.
The main flow of the set is the set auto open /close sequential flow, running supervisory flow,
emergency stop flow, event stop flow .Use the signal generator simulation governor to transport
signals as the set is in quiet state in simulation test. The test projects are :stop to empty run, then
to electricify and net merging ,to run unload, then to stop, emergency stop procedures and finally
to event stop procedures.
The public instrument LCU: the pump automatic running, factory power supply standby self-
commissioning.
(10) other system telecommunication joint debug
The debug will be done according to the design with the communication contract negotiated at
the time of the design. The computer supervisory controlling system of the bulb turbinar power
station and the governor system and excitation system all adopt the telecommunication RS 232,
RS485 to communicate.
(2) the DN100mm steel pipe use flange to connect ,each of segment is 5—6m.
3. Confirm the pipe holder space
(1) erection of the pipes, 1-2 for each layer
(2) Erection as follows
Caliber size
15 20 25 32 40 50 65 80 100 150
(mm)
Caliber size
15 20 25 32 40 50 70 80 100 125 150
(mm)
Space (m) 2.5 3 3.5 4 4.5 5 6 6 6.5 7 8
installation
Position fixing
Hanger setting
testing
9.1 The professional healthy, safety, environmental & quality plan organization and the
object
9.1.1 Policy; Safety; Environmental; High quality; Innovation; Discipline
9.1.2 Object: All 100% pass in one time; 80% excellent; 85% client satisfaction
Management Representative:
The third part Mr.Liu Shaoyue
Supervision Dept.
刘少跃
Quality management dept.
Mr.Ye fuxing
Project manager
Welding group
Piping group
Lifting Group
Mechan.group
Steel group
Line group
Elec.group
Wel
M
2. Management procedure
(1) The quality record system
a. The project manager specified a person who take charge of collect; work up the quality record.
b. It is not allowed to use the ball-pen and the pencil write the quality record,any amendment
should write beside the primary one which will be redlined and be still visual able.
(2) Quality record management
a. The record should be kept and filed as the requirement of the “File and documentation
management of GYT”.
b. It is not allowed to use the ball-pen and the pencil write the quality record, any amendment
should write beside the primary one which will be redlined and be still visual able.
9.2.14 Service management
(1) The re-visit will be carried out by the project office; the technique division and the
construction division within 3 month or one year after the commercial running of the unites.
(2) The normal re-visit will be charged by the project office and the key one will be hold by the
company.
2. The re-visit system
(1) The re-visit will be carried out within 3 month or one year after the commercial running of
the unites. And collect the information of the installation quality from the client.
(2) Fill in the quality visit paper which will be recorded and filed in company.
(3) If any installation defection founded the primary project will assign people for treatment
which is free within one year after the commercial running of the unites.
9.3 Environment protection controls
9.3.1 Factor recognition
1. The expulsive water, air, noise and the liquid waste explosive from the work.
2. Environment influence from the raw material, the third-party supplier and the waste expulsive.
3. The foreseeable condition ( such as fire, explosion etc.) occurred during the construction.
4. Any pollution at site.
9.3.2 Environmental assessment
<The environment factor assessment detailed list>will be managed as the following
1. The mainly has: raw material, turnover material, energy, expendable goods, motor vehicle,
machine equipments and other.(if maintain, maintain etc.)
2. The environment influence factor mainly has: Air pollution, water pollution, the soil
pollution, noise, vibration, solid, discard, resources consume, poisonous and harmful chemicals
usage, ozone layer break, electromagnetism radiation, light hot radiation, smelly and other
factors.
3. In the detailed list the factor should be filled in a homologous product and exhausts thing,
wastes, energy.
9.3.3 The environment management rules
1. Obey the ordinance concerning environmental protection. The plant, forest out of the
construction movable boundary ruled in the contract, make an effort to maintain its original
shape. Don't use harmful material(anticipate such as the fuel, oil, chemicals, sour etc., and exceed
harmful air and dust of allowing the amount of, leave a residue...etc.) a pollution a land, river.
2. tidy up garbage in time, carry it to the appointed location to carry on burying or burn a
processing, in the workplace and the residence area should have enough temporary health
facilities, periodically cleaning up ; keeping environmental hygiene.
3.The prevention and request of the noise and the vibration: Will start construction the spot of fix
noise, vibrate a source opposite concentration decoration, increase to establish plank of separate,
blocking the noise, device; can not clamor loudly when residents' area neighborhood and
nighttime start construction, avoiding artificial noise.
4. the request prevented and cured to the water pollution: Construction waste water, living dirty
water carry on concentrated processing, reach mark rear row to put to go into appointed of be
subjected to a Na water body.
5. Carry on a point control to important environment factor holding of movement and activity, as
to it's medium may result in the homework that the important environment influences order, is
established it as environment control point by the item department.(press construction
organization inside design of <important environment factor and its influence general chart >
performance)
6. construction the spot of the warehouse be responsible for flammable to explode an
article(oxygen...etc.) to store to save easily with usage, performance company of <the dangerous
chemicals manage provision>;To construction process of dirty water, dust etc. the environment
influence a performance <construction the spot civilization construction management>.
7. supervise and control equipments and examine equipments to carry on a maintenance to
maintain for construction,see <construction the machine maintain management provision>.
8. the item department bring the equipments that the important environment influences to may to
adopt to correspond measure to carry on a management, if adopt to the noise, such as generator
and air compressor...etc. soundproof, absorb a sound etc. measure, keep construction field from
boundary noise is super to mark; (concrete performance <construction the spot civilization
construction management provision>)For leak, drop oil phenomenon the adoption lead oil slot,
oil bucket to give collections etc.
9. open the exhibition environment management work according to the related request strictly,
and work well to correspond a record.
9.3.4 Hygiene, environmental protection measure
1. establish temporary health facilities on the scene in the workplace, should periodically clean
up a processing also through the department concerned approval. Face to establish a place
constitution in a row, smooth catchments system, and reasonable organization drain. Drain ditch
to carve with the brick, the flowing water noodles uses the M5 cement sand syrup to put on
noodles. Draining the ditch crosses road to use to cover up a tube or adds a cover plank. Adopt to
cut water measure effectively in construction inside the building, prevent from to the construction
area outside the influence of the building space, facilities
The processing of dirty water with exhaust. Establish to precipitate pond and flush slot inside
place, attaining all living or other dirty water have to respectively after handling, square can
through drain a dike row into net or river of the municipal services drain pipe.
2. Keep the environmental hygiene of construction area and life area, live area to establish a
garbage pond, have to tidy up garbage in time, and carry it to appointed of the location carry on
burying a processing. The living garbage can fill to cover up, burn with the hygiene, fertilizer,
recover to make use of an est.’s method to carry on a garbage processing.
3. the solid discard can recover to make use of , should recover by oneself; The solid discard can't
recover to make use of, have to according to environmental protection of relevant the provision
handles by oneself perhaps entrust unit treatment of having the ability of corresponding, natural
intelligence. The solid discard facilities, place has to meet national relevant provision with
exhausting index sign. Should manage strictly to handling facilities, place and periodically
support; can not result in pollution. Forbid to sneak into dangerous discard life garbage or other
discards. Discarding the lead sour storage battery's waiting other dangerous discards should
recover exploitation. Don’t have a condition of take back, should deliver the dangerous discard
management had already corresponded natural intelligence unit to handle on behalf.
4. the workers' meal, drinking supply...etc. should meet a hygiene request
5. establish a homologous medical treatment health care organization, there are the drugs of
necessary medical treatment apparatus and appropriate amount fully. Make to defend a disease
cure work, open the exhibition medical treatment health publicity.
9.4 Safety, housekeeping management
9.4.1Safety, housekeeping management measurement
9.4.1.1 The safety target
(1) Eradicate completely to die trouble, industrial accident ≤ 10 ‰;
(2) Severely wounded control at lower of 1.8 ‰ , no poisoned and collapse to fall trouble
occurrence;
(3) Avoid the occurrence negative traffic accident of equal class and following responsibility;
(4) Press work to grow, the post provision issue labor protection equipment, hazing the post
of[with] influence to provide with each labor protection and healthily to the employee-The
protection equipment rate is 100%
Project manager
Deputy manager
Safety office
Professional engineer
Forman