You are on page 1of 3

Cathodic Protection

QC-195F
Storage Tank
CONTRACT# CLIENT / PROJECT SYSTEM

JOB# CWP

CLIENT REF:

Mark “N/A” where Not Applicable


Designation:
Location: Drawing and Rev :

CORROSOMETER TEMPERATURE TEMPORARY


ANODES REFERENCE CELL
PROBE PROBE ANODES
Type
Quantity

Inspected by
Item Checks Result
Initial Date
INSTALLATION
1 Ribbon anodes installed
2 Anodes header cable installed
3 Header cable to anode C-Tap connections
4 C-Tap connections mastic sealant applied
Header cable to anode C-Tap connections shrink sleeves
5
applied
6 Corrosometer probes installed
7 Temperature probes installed
8 Temporary magnesium ribbon anodes installed
Slotted CPVC monitoring pipe nylon rope & end caps
9
installed
10 CPVC monitoring pipe Nilex filter sock installed
11 Tank weld on tab installed
12 Tank negative lead connection installed
13 PVC conduit system for anodes installed to junction panel
PVC conduit system for corrosometer probes / temperature
14 probes / electrodes / temporary anodes installed to junction
panel
15 Tank center & perimeter identified
16 Teck cable installed between rectifier & junction panel
17 Ribbon anode spacing
18 Remove plastic bags from cells
19 As-Built complete
20

Revision 0 July 6, 2006 QC-195F R0 Cathodic Protection Storage Tank.doc Page 1 of 3


Cathodic Protection
QC-195F
Storage Tank
Mark “N/A” where Not Applicable

Designation:

LEAD WIRING TO JUNCTION PANEL


Inspected by
(or to protective chamber at edge of tank)
Check For Continuity /
Termination
Lead Wires Installed Color Nicks / Identification /
(tank end) Initial Date
Damage Tagging
Anode Lead Wires
Tank Negative Lead
Wires
Corrosometer Probes
Temperature Probes
Reference Cells
Temporary Anodes

Complete Associated Anode Junction Panel Record


Complete Associated Rectifier Panel Record

Inspected by
Checks Result
Initial Date
SOIL RESTIVITY TESTS
Test Equipment ID: Ω-cm

Sample #1 soil resitvity (ohm-cm) Ω-cm

Sample #2 soil resitvity (ohm-cm) Ω-cm

REFERENCE CELL TESTS (millivolts)


Before After Inspected by
Backfill Backfill
(mV) (mV) Initial Date
Test Equipment ID:
C1 lead to C2 lead
C2 lead to C3 lead

CORROSOMETER
Test Equipment ID:
Corrosometer P1 (Mag Connected)
Corrosometer P2 (Mag Connected)
Corrosometer P1 (Baseline Reading)
Corrosometer P2 (Baseline Reading)

INSPECTED BY CHEMCO CLIENT OTHER


NAME: NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE: SIGNATURE:

DATE: DATE: DATE: DATE:

Revision 0 July 6, 2006 QC-195F R0 Cathodic Protection Storage Tank.doc Page 2 of 3


Cathodic Protection
QC-195F
Storage Tank
Mark “N/A” where Not Applicable

Designation:

ANODE RESISTANCE TESTS (Power Feed Connections Ω Between Leads)

Test Equipment ID Before After Inspected by


Backfill Backfill
Loop # Ω Ω Initial Date
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω
Ω Ω

TANK TO GRID
Test Equipment ID:
Tank to grid circuit resistance Ω Ω

TEMPERATURE PROBE
Test Equipment ID:
Temperature Probe P1 (microvolts) µV µV

Temperature Probe P2 (microvolts) µV µV

COMMENTS:

INSPECTED BY CHEMCO CLIENT OTHER


NAME: NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE: SIGNATURE:

DATE: DATE: DATE: DATE:

Revision 0 July 6, 2006 QC-195F R0 Cathodic Protection Storage Tank.doc Page 3 of 3

You might also like