This document contains a cost breakdown for the actual prolongation costs of a construction project. It lists staff roles like project manager, engineer, and foreman along with site establishment and plant costs. For each item, it provides the quantity, rate per day, estimated overtime days, and calculated amount. The total net cost for prolonging the project for 300,000 days is over 145 million with a gross weekly cost of around 6.3 million.
This document contains a cost breakdown for the actual prolongation costs of a construction project. It lists staff roles like project manager, engineer, and foreman along with site establishment and plant costs. For each item, it provides the quantity, rate per day, estimated overtime days, and calculated amount. The total net cost for prolonging the project for 300,000 days is over 145 million with a gross weekly cost of around 6.3 million.
This document contains a cost breakdown for the actual prolongation costs of a construction project. It lists staff roles like project manager, engineer, and foreman along with site establishment and plant costs. For each item, it provides the quantity, rate per day, estimated overtime days, and calculated amount. The total net cost for prolonging the project for 300,000 days is over 145 million with a gross weekly cost of around 6.3 million.
RATE/ EOT DESCRIPTION NAME/ITEM QUANTITY UNIT AMOUNT REMARKS DAY DAYS
Project Manager name 1.000 Nr. 89.650 300.000 26,895.000
Project Engineer name 1.000 Nr. 41.250 300.000 12,375.000 QS / Cost Controller name 1.000 Nr. 30.250 300.000 9,075.000 QA / QC name 1.000 Nr. 41.250 300.000 12,375.000 Planner / Scheduler name 1.000 Nr. 22.000 300.000 6,600.000 Draftsman name 1.000 Nr. 19.250 300.000 5,775.000 Document Controller name 1.000 Nr. 12.375 300.000 3,712.500 HSE Co-Ordinator name 1.000 Nr. 17.875 300.000 5,362.500 Surveyor name 1.000 Nr. 15.125 300.000 4,537.500 Foreman name 1.000 Nr. 16.500 300.000 4,950.000 Store keeper name 2.000 Nr. 13.750 300.000 8,250.000 Site Estalbishment name 1.000 Nr. 32.279 300.000 9,683.600 Site Establishment name 1.000 Nr. 4.842 300.000 1,452.540 Site Establishment name 3.000 Nr. 3.530 300.000 3,177.000 Plant name 1.000 Nr. 75.000 300.000 22,500.000 Plant name 1.000 Nr. 16.667 300.000 5,000.100 Plant name 1.000 Nr. 14.000 300.000 4,200.000 Total Net Cost 145,920.74 Gross Weekly Cost 6,344.380 Prelims costs in DelayPeriod