ID Task Task Name Duration Start Finish

Mode 21 Jun '20 28 Jun '20 5 Jul '20 12 Jul '20 19 Jul '20
M T W T F S S M TW T F S S M TW T F S S M TW T F S S M TW
1 Bundle SKG K2400 assembly with FSR23 days Mon 22/6/20Mon 20/7/20
2 seal and spare parts arrive 0 days Mon 22/6/20Mon 22/6/20 22/6
3 rotor arrive 0 days Wed 24/6/20Wed 24/6/20 24/6
4 cleaning ,inspection & measurement 1 day Thu 25/6/20 Thu 25/6/20
5 laby ID 0.5 days Thu 25/6/20 Thu 25/6/20
6 rotor dimension 0.25 days Thu 25/6/20 Thu 25/6/20
7 bearing dimension 0.25 days Thu 25/6/20 Thu 25/6/20
8 axial floatation measurement 1 day Fri 26/6/20 Fri 26/6/20
9 install rotor 1 day Sat 27/6/20 Sat 27/6/20
10 install top and bottom half bundle 1 day Sat 27/6/20 Sat 27/6/20
11 install bundle head 1 day Sun 28/6/20 Sun 28/6/20
12 preparation of DGS assembly 2 days Sun 5/7/20 Mon 6/7/20
13 fabricate sheering 2 days Sun 5/7/20 Mon 6/7/20
14 grinding outbord plate thrust bearing
1 day Mon 6/7/20 Mon 6/7/20
15 repair inner seal laby 1 day Mon 6/7/20 Mon 6/7/20
16 install DGS 0.5 days Tue 7/7/20 Tue 7/7/20
17 install journal bearing 0.5 days Tue 7/7/20 Tue 7/7/20
18 install thrust disk and thrust bearing1 day Wed 8/7/20 Wed 8/7/20
19 vacuum pack 1 day Mon 13/7/20Mon 13/7/20
20 transport to port 1 day Tue 14/7/20 Tue 14/7/20
21 custom check and clearance 2 days Wed 15/7/20Thu 16/7/20
22 preparation for shipping vessel depart1 day Fri 17/7/20 Fri 17/7/20
23 vessel reach bintulu 0 days Mon 20/7/20Mon 20/7/20 20/7

Task Inactive Task Start-only


Split Inactive Milestone Finish-only

Project:Bundle SKG K2400 Milestone Inactive Summary Deadline


assembly with FSR Summary Manual Task Progress
Date: Mon 6/7/20
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary