Professional Documents
Culture Documents
Group 3
Written Report
Design Process
Preliminary Stage
Initial Planning, Investigation Phase
Preliminary Design Considerations
Data Requirements
Detail Design
Preliminary Stage
The preliminary stage includes:
Some of the factors that must be analyzed when considering the construction of a
wastewater collection system for example are:
Depending on the regulatory agency evaluating the design, either the sewers must be able
to carry the design flow while flowing full or at some given fraction of the full depth, or the
design flow must be some percentage of the full-pipe capacity (e.g., 75 percent of capacity
at design flow). The engineer must determine which is the better approach for a given case,
as the two requirements can produce different pipe sizes. Minimum slopes to prevent
sedimentation and minimum cover to prevent traffic impacts must also be considered.
Where local codes do not exist or do not address a specific issue, widely adopted standards,
should be consulted.
In addition to technical design criteria and the hydraulic loads, other pertinent
considerations include the following:
Costs – The planning, design, construction, operation, and maintenance costs should all
be considered in assessing the long-term sustainability of the project.
Schedule – The time between the initial planning and the operation of a sewer may be
as long as a decade and the project may need to be constructed in phases.
Operation and Maintenance – Gravity sewers are not maintenance free. They require
periodic inspections and cleaning, and some components may require repair or
replacement. An organization to operate the system must be in place.
Environment – Construction of the sewer results in both temporary disruption of and
long-term effects on the environment. Short-term effects include temporary lowering of
the groundwater table and release of sediments. Over its design life, the sewer system
will affect the performance of the wastewater treatment facility and the water quality of
the receiving water body.
Regulatory compliance – The sewer project must comply with all applicable laws and
regulations. The design criteria should be developed in consultation with the sewer
utility and the financing and regulatory agencies. Consensus on the design criteria before
the start of the design is essential.
Data Requirements
Additional physical data, beyond that necessary for hydraulic analysis, is required for the
design of new sewers. The following list of data requirements has been adapted from
American Society of Civil Engineers (1982):
The data may be obtained from a variety of sources. Maps, aerial photographs, construction
drawings, and ground surveys may be queried. Typically, no single data source is complete,
so one must identify inconsistencies and fill in gaps. Instrument surveys are the most
accurate method of obtaining high quality spatial data. Many vertical-elevation reference
and control points should be established systematically along the route.
Detail Design
Detail design is the finalisation of the design for the development, including all approvals,
consultation with residents, all details for how the system will operate, the location of the
infrastructure and provision of all details.
The accredited designer must include in the NPV assessment and estimates for the
operation and maintenance costs for the proposed system, which may take into
account site specific conditions. There is also an assessment if higher operation and
administration costs will result in implementing the proposed system over a typical
conventional gravity system.
References:
http://www.hunterwater.com.au/Building-and-Development/Drawings-Plans-
Specifications/Water--Sewer-Design-Manuals/WSDM6.pdf
http://civilengineerspk.com/design-of-sewer-system/