PROJECT:
PROPOSED G-ONLY OFFICE, G+M WORKERS FACILITY, G-ONLY
SHED, OPENSHED & OPEN WASH AREA ON PLOT NO. 5337865
@ SAIH SHUAIB 4, DUBAI
Signature:
LOYAL BUILDING CONTRACTING LLC
METHOD STATEMENT, ITP & RISK ASSESSMENT
Next Review
SL NO DESCRIPTION Approved by
Date
5/8/2020
1 MOBILIZATION Mr. Mathew
5/8/2020
Mr. Mathew
2 EXCAVATION
5/8/2020
Mr. Mathew
3 PCC AND FOUNDATIONS
5/8/2020
Mr. Mathew
4 CONCRETE WORKS
5/8/2020
Mr. Mathew
5 BACK FILLING
5/8/2020
Mr. Mathew
6 ERECTION OF STEEL STRUCTURE
5/8/2020
Mr. Mathew
7 BLOCK WORKS
5/8/2020
Mr. Mathew
8 PLASTERING WORKS
5/8/2020
Mr. Mathew
9 ELECTRICAL WORKS
5/8/2020
Mr. Mathew
10 GYPSUM WALL/ CEILING WORKS
5/8/2020
Mr. Mathew
11 PLUMBING WORKS
5/8/2020
Mr. Mathew
12 PAINTING WORKS
5/8/2020
Mr. Mathew
13 DEMOLITION WORKS
5/8/2020
Mr. Mathew
14 EQUIPMENT/ VEHICLE ON SITE
LOYAL BUILDING CONTRACTING LLC
MOBILIZATION – METHOD STATEMENT, ITP & RISK ASSESSMENT
Mobilization
Mobilization works shall be carried out immediately up on receiving the letter of Intent / Order to commence.
Control
Risk
Contractor
Premises of Consultant Review point - Representative of indicated party to review
R
Inspection / Site Approval submitted documents, result of test etc..
Work Area
Coordinates
Acceptance
Criteria Contractor Consultant Owner
Activity Description of (Controlling
Drawing N" of reference
NO Inspection & Test Activity Procedure, Specific
Specifications, Contractor CEC Quality Punchlist
MOBILIZATION Standars etc..) H W R H W R H W R Signature Signature Report Item N"
1 COMPLETION
Control
Risk
Task/Job/Operation: MOBILIZATION Project: PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC- REV-0
WORKERS FACILITY, G-ONLY SHED, OPENSHED & 026
Main Contractor: LOYAL BUILDING CONTRACTING LLC. OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Risk Assessor:
Client: SILVERLINE CONSTRUCTION & MACHINERY SHUAIB 4, DUBAI Mr. JAMES NEEL(SO)
RENTALS LLC
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Excavator, Shovel, Skid Steer Loader Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
(Bobcat) goggles, gloves
might be Harm/
Consequences
Risk level Risk
Control E/I/R
Risks / Who
compliance
Job steps/
/Potential
Remarks
Activities
Hazards
Legal L S R
Sl no
Fencing work 1)Slip, falls 1) instruct to walk slowly and carefully (do
Workers 3 2 L
2 Yes 3 5 H R not run)
2)injury to
Control
Risk
Hazard identified
might be Harm/
Consequences
Risk level Risk
Control E/I/R
Risks / Who
compliance
Job steps/
/Potential
Remarks
Activities
Hazards
Legal
L S R
Sl no
Control
Risk
Hazard identified
might be Harm/
Consequences
Risk level Risk
Control E/I/R
Risks / Who
compliance
Job steps/
/Potential
Remarks
Activities
Hazards
Legal
L S R
Sl no
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Excavation
Loyal Engineer shall ensure that prior to commencing work the position of services obstructing the work area are
established, marked, agreed, and recorded. The position if cables shall be provided by carefully hand digging.
For excavations deeper than 1.2 meters, a ladder will be provided, and kept close to the workplace in the excavation should
an emergency arise.
Adequate warning signs i.e. “Deep excavation “, Excavated area- Keep back” etc will be provided.
If the depth of vertical cut exceeds 1.5m Shoring will be provided to avoid cave in.
Adequate measures like bulk timbering to be provide to avoid vehicle over running into the excavation.
Where a vehicle is being used to tip material in to an excavation, it will be kept at a safe distance away from the edge to
prevent possible collapse.
After completing sub structure works, all remain excavated area will be backfilled properly.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
All the area will be leveled properly as per the site condition.
INSPECTION & TEST PLAN (ITP)
Main Identfication Information
Document Revision Status Type of Inspection
System Subsystem
Plan Rev / Date 00M 01M 02M 03M H
Project Phase Hold point - Representative of indicated party to attened (Mandatory)
(Manufacturing / Contractor
Construction Witness point - Representative of indicated party to be notified. If not
Construction / Issuing W
attending at specified time, inspection may proceed.
Commossioning)
Contractor Premises of
Consultant Review point - Representative of indicated party to review submitted
Inspection / Site Work R
Approval documents, result of test etc..
Area Coordinates
Control
Risk
Task/Job/Operation: EXCAVATION Project: : PROPOSED G-ONLY OFFICE, G+M WORKERS Ref No: RA- REV-00
LBC-001
FACILITY, G-ONLY SHED, OPENSHED & OPEN WASH AREA
Main Contractor: LOYAL BUILDING CONTRACTING LLC. ON PLOT NO. 5337865 @ SAIH SHUAIB 4, DUBAI Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHINERY LLC Mr. JAMES NEEL (SO)
Date : 5/10/2019 Date Next Review: 5/04/2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator, Shovel, Skid Steer Loader (Bobcat)
goggles, gloves
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Unauthorized Work area to be visually inspected for any
personnel on site hazard, adjacent activity or unusual
condition by the supervisor
use of damaged Pre-Task briefing to be conducted daily to
equipments brief the workforce on the tasks and
hazards during safety Induction/tool box
Inadequate PPEs Employee & Public
talks
1 Preparatory Works and Others 1 3 L
No 3 3 M R Supervisor to check adherence to PPE
hazards not accessing Supervisor to arrange the placement of
identified
tools, materials and equipment to avoid
personnel not slips, trips and falls
conducted safety Banksman to guide the movement of
induction delivery vehicles and control operatives
Site superintendent to inspect the work
inadequate area prior to the task for adequate access,
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
supervision and excavation sloping and shoring where
Inadequate trainings required in adherence to the Permit to
Work
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Supervision Vehicle movement to be at 6mts from the
edge.
Unsafe Access/ Egress Trespassing to be prohibited during
excavation.
Safe Access and egress Should be Provided
All Underground supply should be
monitored with competent person
Electrical Cable detector should be used for
monitored Electrical power supply
Excavation Permit should be issued from
Project Incharge
COC 1 Should be needed for Excavation
works in JAFZA Areas
Safe Vehicle Distance should be provided
Check the underground utilities from the as
built utilities drawing else check
Trial trenches shall be hand excavated to
ensure absence of underground services or
cables
Electrocution,
Cable detector shall be used to ascertain
Flooding, Gas
Expose all existing Damage to the presence of live cables if any below ground 1 5 L
4 poisoning, Yes 3 5 H R
services by hand underground utilities All visual services above ground effected
Explosion, strain,
due to excavation works shall be supported
sprain
before start of excavation
Exposed cables and pipe protected
To ensure proper use of PPE during entire
work
All personnel to be attended HSE Induction
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
training from safety department. Before
entering in to the site.
Work permits should be taken from utility
authorities (if required).
Unknown services encountered during
excavation shall be reported to Safety
Incharge/PM/Client representatives
EHS Approved Third party certificate,
Operator license & registration card
available for heavy equipment’s like JCB,
Showel &Cranes etc. as per the EHS
requirements.
People not to work inside of excavation
when heavy equipment is in operation.
Fall of Men or Excavation area to be cordoned off and
Machine Improper warning signs shall be displayed
access & Egress noise Equipment toppling Fitness of machinery to be checked in every
5 Serious injuries, 1
collapse of trebch Yes 3 4 H R shift. Outriggers to be on solid ground for 4 L
fatality, ear problem
wall due to heavy preventive measures.
vibration Excavated sand must be stacked away at
least two meter away from barricading
Proper shoring / sloping /step cutting and
hard barricading to be provide where the
excavation deep more than 1.5 m
Proper access shall be provide at required
location
To ensure proper use of PPE during entire
work
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Tool box talks to be given before
commencing the activity
Ear protection to be provided monitor to
operative use
Maintain distance from other Machinery/
Equipment’s.
Post signal man/banks man, if required.
Movement of plant Contact with other Equipment damage, 1
6 No 3 5 M R Excavation area to be cordoned off and 5 L
and equipment equipment personal injury
warning signs shall be displayed
Proper access shall be provide at required
location
Safe accesses & egress to the work area to
be provided at all times.
Personal injury, 2 3
7 Access/ egress Trip, slip, fall No 3 3 M R Signage should be provided. L
fracture
Access not to be blocked with any
materials.
Adequate signage to be placed all around.
Trip, slip, fall, Dust Provide edge protection barricade all
Barricading around Personal injury, around the area with railing, net & toe
8 generation during 1 3
the excavated area fatality No 3 3 M R L
excavation board.
Dust suppression by sprinkling water and
dust mask for dusty area
Environmental noise Heat stroke plant Certified and good condition plants to
& dust, oil spillage exhaust burns Employee, Public reduce vibration and smoke.
9 2 3
land contamination dehydration. Earpain and Others Yes 4 3 H R In case of any oil spillage inform to M
air, water pollution, or deafness environmental department/remove the
Health & Hygiene respiration Problem contaminated soil dispose as per
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Hazards by dust, eye sight instruction of authority
Avoid Over fill oil and other lubricant
Provide suitable ear protection for use In
noisy area.
Dust suppression by sprinkling water and
dust mask for dusty area.
All operatives briefed on the benefits of
good hygiene (about eating and washing)
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Control
Risk
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Inspection for the grids and levels shall be confirmed from the consultant and concerned authority prior to
Pouring of concrete.
Shuttering box shall be fixed according to the grid line and levels marked. Concreting shall be done as per the
mix design and specification.
After cu ring for three days one coat of cold bitumen / polythene shall be placed prior to commencement of steel
reinforcement and shuttering for the foundations.
Steel reinforcement shall be fabricated according to bar bending schedule and placed as per the approved
drawings accordingly shuttering works for the same shall be proceed. After checking from the concerned
authorities concrete shall be poured as per design mix and Specification.
Control
Risk
3 CURING INSPECTION
Control
Risk
Task/Job/Operation: RCC & PCC Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-006 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL (SO)
Client: SILVERLINE CONSTRUCTION MACHINERY LLC
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Skid Steer Loader (Bobcat), Telescopic Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Handler, Shovel, Concrete Pump, Vibrator, Scaffolds goggles, gloves
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Control
Hazard
Harm/
Risk level
Sl no
Legal
E/I/R
Mitigation action to be taken/ Hazard/Risk
s Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Control
Hazard
Harm/
Risk level
Sl no
Legal
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Control
Hazard
Harm/
Risk level
Sl no
Legal
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Control
Hazard
Harm/
Risk level
Sl no
Legal
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Control
Hazard
Harm/
Risk level
Sl no
Legal
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
All concrete works shall be carried out by an approved ready mix plant and as per suggested mix design.
All formwork of concrete work shall be made with 18mm marine ply wood and as per the given sizes in the
drawing.
Steel reinforcement will be cut and bent as per the required diameter and shape and it will be fixed with
interconnect.
Proper cover space. Shop drawings and bar bending schedule shall be prepared and to be approved by the
consultant.
Sampling and testing of concrete shall be done in accordance with the specified code of practice.
All the concrete shall be vibrated properly and finished nicely and it will be cured by application of concrete
curing compound.
Temperature controlled concrete shall be used. Max. Temperature of concrete not to exceed 32 degree C.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Contractor Premises of
Consultant Review point - Representative of indicated party to review submitted documents, result
Inspection / Site Work Area R
Approval of test etc..
Coordinates
Consultant Owner
Acceptance Criteria Contractor
Description of Inspection & Test
Activity NO Drawing N" of reference (Controlling Procedure, Specific
Activity
Specifications, Standars Contractor Quality Report Punchlist Item
etc..) H W R H W R H W R Signature CEC Signature Code (If any) N"
2 SLUMP TEST
3 CUBE TEST
4 CURING INSPECTION
5 SCOFFOLDING CHECK
Control
Risk
Task/Job/Operation: SHUTTERING & DE SHUTTERING Project: : PROPOSED G-ONLY OFFICE, G+M WORKERS Ref No: RA-LBC- REV-0
WORKS 004
FACILITY, G-ONLY SHED, OPENSHED & OPEN WASH
Main Contractor: LOYAL BUILDING CONTRACTING LLC. AREA ON PLOT NO. 5337865 @ SAIH SHUAIB 4, DUBAI Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHINERY LLC Mr. JAMES NEEL (SO)
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Shovel, bobcat , Scaffolds, crane, Power Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
tools, tools goggles, gloves
Risk
compliance
Rating/ Residual
Remarks
Control
Job Risks / Who might
Legal
Risk Risk
E/I/R
Sl Hazard identified Mitigation action to be taken/ Hazard/Risk
steps/ be Harm/ level
no /Potential Hazards Control Method
Activities Consequences
L S R
L S R
Chance of Fall down Minor & Major Access and egress should be clear of
( Persons& injuries obstruction
Workers worn all PPEs for Shuttering & de
materials) on Damage materials
shuttering works
Shuttering footing shuttering, Time Loss Proper / adequate Tool box Meeting & H S E
and De
1 Column shuttering Money Loss induction Training Conducted 2 3 L
shuttering No 3 3 H R
works Removed penetrated nails from planks
& tie beam Life Loss
Adequate Scaffolds should be provided
shuttering Adequate Housekeeping at site
Failure of material Material Stocked Properly
Well Supervision
on persons
Control
Risk
Risk
compliance
Rating/ Residual
Remarks
Control
Job Risks / Who might
Legal
Risk Risk
E/I/R
Sl Hazard identified Mitigation action to be taken/ Hazard/Risk
steps/ be Harm/ level
no /Potential Hazards Control Method
Activities Consequences
L S R
L S R
Control
Risk
1. All waste materials will removed daily from the wok area and transferred to the designated waste skip
2. All Hazardous waste shall be immediately removed as per UAE regulation and dispatched slip maintained.
Risk Assessment Methodology
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
Control
Risk
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Backfilling
Backfilling materials shall be approved from the concerned authority prior to commence. Levels shall be marked
for the required level of backfill. Backfilling shall be done in layers not more than 30 cm for each layer and
compacted Field density tests shall be done for every 2nd layer of the fill and same shall be continued till the
Control
Risk
Contractor Premises of
Consultant Review point - Representative of indicated party to review submitted documents, result
Inspection / Site Work Area R
Approval of test etc..
Coordinates
2
COMPACTION TEST
Control
Risk
Task/Job/Operation: BACKFILLING Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-002 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHINERY LLC OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL (SO)
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Excavator, Shovel, Skid Steer Loader Recommended PPE: Hard Hat, Safety shoes, overalls, gloves, safety harness, dust
(Bobcat), plate compactor mask, goggles
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Risk
Consequence
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
sSl no
Harm/
Legal
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
The contractor reserves the right to adopt the methods used according to the site needs and conditions and if
required this method statement will be revised and re-submitted for review and approval (if any)
PURPOSE;
The purpose of this Method Statement is to outline the sequences of work and methods used in the erection of
Pre-Engineered steel structure.
SCOPE;
This Method Statement is applicable for the erection work of the steel structure only.
Written approval must be obtained prior to start of erection work building area wise/location wise.
The following shall be checked and provided before the arrival of the steel to the job site.
Control
Risk
Correct foundation positions with respect to the building lines and bench marks
The anchor bolts positions have been checked after the concrete has been poured
All steel materials shall be carefully checked and unloaded by use of heavy duty fork-lift or by crane. Care shall be
exercised when handling materials to avoid damages
At time of unloading materials shall be checked against the bill of materials or packing list. Any shortage must be
reported to concern department immediately
Materials should be laid out to avoid double handling. Lay-out will depend on size of building and site
conditions, Timber blocks shall be used between bundles or members for ease of handling
STORAGE;
Each place of steel should be marked and identified as per drawing before sending to site
SHEETS STORAGE
Control
Risk
The bundles of sheets shall be elevated above the ground with one end higher than the other to allow water
drainage. There shall be air circulation spaces between the bundles and the whole stack should be covered using
a tarpaulin in times of rain or high humidity
This practice when followed helps protect the sheets if keep in prolonged storage
Polythene sheets shall not be used to cover bundles of sheets as polythene causes condensation
ERECTION;
Prior to beginning the erection of any steel structure, the contractor shall develop a detailed steel erection plan,
includes, risk assessment, temporary supports, and erection equipment used and the sequence of erecting of
these structures, and the plan shall be submitted to the consultant engineer for approval
A steel erection contractor shall not start steel erection unless ensuring that concrete has attained and has
sufficient strength to support the loads imposed during steel erection, and obtains approval of the consultant
engineer according to the project specifications
The contractor shall provide his employees with all necessary personal protective equipment and shall ensure
their effective use
The weather forecast shall be checked for favorable weather conditions before commencing erection. Start of
erection shall be rescheduled if weather conditions are unsettled or strong winds imminent
Ensure all cranes and lifting tackles are thoroughly tested and approved
Third party as per national regulations and certificates available at site
Control
Risk
Ensure that all operators are licensed trained and competent as per national regulation
If possible visibility of the lost and rigger and operator is not feasible proper communication facilities must be
provided
All lifting operations must be controlled by component person who will take over all responsibilities and possess
a method attainment for the work activities
Tool box talks to be conducted on daily basis before the commencement of job
Ensure a safe working platform with proper hand rail and intermediate rail
Control
Risk
Ensure all elevated working areas have proper hand barriers/hand rail all around and install intermediate rails
where employees need to carry out then works in a crouching position
Ensure employees use proper fall arrest system such as full body harness and hood the harness to a proper
anchorage point wherever fixing hand rails is not practicable
Train employees on work height safely and the use of fall arrest system
All mobile man lifts scissor lift must be equipped with necessary warning and alarm system supervisors
(revolving beacon light/reverse alarms)
Don’t lift any erection Steel materials, MEWP must be only used for lifting working personals.
Control
Risk
The columns for the braced bay base plate shall be set, base plates shall be shimmed and anchor bolts & nuts
shall be tightened sufficiently to prevent columns from rocking
The rafter members shall be assembled on wooden block on ground , the bolts in the rafter splices shall be
installed to be proper tension
The rafters shall be raised in to position between the columns, the beam shall be held in position with hoisting
equipment while required bolts are installed through the column splice plate, the bolts shall be tightened to snug
fit
The rafter shall be tied with cables extending lengthwise of the building, the bracing shall be located in the center
near the ridge, quarter of the purlin in between are installed for permanent bracing, the temporary bracing
between the erected beams shall be released, the remaining roof purling at every purling location shall be placed
Before proceeding further, the first bay shall be made plumb and square, temporary braces shall be used to pull
the columns into plumb, all anchor bolts eave strut bolts and columns to beam bolts shall be fully tightened
Mezzanine column beam joist are erected now after completion of building erection
Adequate temporary bracing and support to be provided during erection wherever necessary in vertical or
horizontal
Control
Risk
Erection work should be carried out in a safe manner under proper experienced personals
All works shall be carried out by selected, experienced skilled workers and utmost safety precautions to be
maintained
Lifting hooks, points by paints should be properly wrapped or protected to avoid any damages to member or
finishes
After the completion of the erection all connections shall be checked to ensure that all blots & nuts have been
installed and that all high strength bolts & nuts are tensioned to correct requirements
SHEETING;
Use a chalk line for accurate drilling and screwing. This gives better appearance and less risk of leakage due to
mis drilling
At the end of each working day clean the roof with a soft brush, sweep off old drill bits, pop reverts, sward from
drill or cutting. These items can cause rusting if they are not removed
When walking on the roof, do not stand on high ribs; stand only on the low ribs, preferably over the purlin line.
Standing on the high ribs can cause severe damage which could lead to possible leakage. Not that stitch crews
are required at side laps on roof sheets
Do not walk on sky lights sheets if any, mark out the sheeting along the length of the building, this will give the
correct overlaps and avoid creep
Control
Risk
Mark the notch as per cover width as an aid to keeping the correct sheet coverage, take note of the starting
dimensions’ shown on the erection drawing, proceed with roof fixing from valley from valley gutter to ridge.
Direction of erection shall be as per drawing.
Final Check
After completing all trims and accessories a final inspection of the building should be made
All bolts and place and high strength bolts tightened to correct tension
Check that roof and gutter are clear or debris and ferrous metals
Control
Risk
Control
Risk
Task/Job/Operation: STRUCTURAL STEEL ERECTION Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-010 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED Risk Assessor:
& OPEN WASH AREA ON PLOT NO. 5337865 @ Mr. JAMES NEEL(SO)
Client: SILVERLINE CONSTRUCTION MACHINERY LLC
SAIH SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Equipment Required: Shovel, Crane, bobcat , Scaffolds
goggles, gloves
Consequence Risk
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Control
Risk
Hazard
Harm/
Legal
Sl no
Risk level
E/I/R
Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
Control
Risk
platforms.
Ladders do not make safe
working platforms - they should only
really be used as a means o f access
(i.e. to get to a platforms roof etc.)
Except for very short work, such as
taking samples. Ensure that ladders are
in good condition and of sound
construct.
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Control
Risk
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Block works
2. All the block work below ground level will be solid block work made with SR cement.
3. All the block work shall be properly grouted, leveled and plumped.
4. All solid and hollow cement blocks shall be procured from an approved automatic factory. 6 courses of block
work will be carried out in one day. Mortar for block work shall be as per the given specifications.
5. Mortar shall be mixed in a mixer machine (one bag of cement and sand shall be weighed in wooden box for one
mix load).
6. All completed superstructure walls shall be kept clean and cured for a minimum 3 days. Wherever block work
flush with structural members, all such joints shall be covered with wire – mesh as approved by the Engineer.
7. Care shall be taken while shifting blocks to avoid breaking of corners.
8. Blocks shall be kept on plywood or polythene sheet to avoid contact with soil.
Control
Risk
Contractor Premises of Consultant Review point - Representative of indicated party to review submitted
Inspection / Site Work R
Approval documents, result of test etc..
Area Coordinates Acceptance Criteria
(Controlling
Owner
Description of Inspection & Procedure, Contractor Consultant Specific
Activity NO Drawing N" of reference
Test Activity Specifications, Contractor CEC Quality Punchlist
Standars etc..) H W R H W R H W R Signature Signature Report Item N"
MATERIALS AS PER
1
SUBMITTAL APPROVAL
2 LAYOUT MARKING
3 CHECK MORTAR MIX
4 CHECK FOR OPENINGS
5 CURING INSPECTION
Control
Risk
Task/Job/Operation: BLOCK WORKS Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-007 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHINERY LLC OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL (SO)
SHUAIB 4, DUBAI.
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Shovel, Telescopic handler, bobcat , Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Scaffolds, Block Cutting Machine, Power tools goggles, gloves
Risk
compliance
Job steps/
Conseque
/Potential
identified
Remarks
might be
Residual
Activities
Hazards
Control
Hazard
Risks /
Rating/
Harm/
Sl no
Legal
nces
E/I/R
Who
Control
Risk
Risk
compliance
Job steps/
Conseque
/Potential
identified
Remarks
might be
Residual
Activities
Hazards
Control
Hazard
Risks /
Rating/
Harm/
Sl no
Legal
nces
E/I/R
Who
Mitigation action to be taken/ Risk
Risk level Hazard/Risk Control Method
L S R L S R
Scaffold must be erected,
dismantled or altered by
competent person, safety harness
Installation of Improper manual must be worn, guard rails & toe
scaffolding for handling, boards are required to all working
miscellaneous lack of proper Death & Fractures due
platforms & provide fall
block works & training and skills for to fall from scaffolds,
2 protection(Full body harness) 1 4 L
working at Scaffolding works & back pain due to body Yes 4 4 H R
Proper training for scaffold
fall hazards while injury, serious injury
height:: working
working on
suspended platform Tool box talk on proper manual
& scaffolding handling, erecting of scaffolding
& working on scaffolding
Adequate House keeping
Well supervision
Proper training for rigging works &
Improper manual
procedures.
handling, lack of Death, Serious body
proper training and Tool box talk on proper manual
Delivery using injury, Serious injury
skills for standard handling, Using of vehicles/
boom loader & due to accidental
3 rigging procedures. Yes 4 4 H R Equipment’s 1 4 L
cranes: contact with
Accidental contact Always secure blocks while on
with the delivery machinery
delivery on upper levels using
trailer & cranes, cranes & provide nylon net
collapse
secured & fix to avoid collapse of
Control
Risk
Risk
compliance
Job steps/
Conseque
/Potential
identified
Remarks
might be
Residual
Activities
Hazards
Control
Hazard
Risks /
Rating/
Harm/
Sl no
Legal
nces
E/I/R
Who
Mitigation action to be taken/ Risk
Risk level Hazard/Risk Control Method
L S R L S R
blocks
Maintain always good
housekeeping
Proper supervision
Adequate signal man with
rd
approved by 3 party certificate
for vehicle and operator
All vehicles / equipment’s must be
equipped with all safety materials
(reverse alarm, warning light,
license, vehicle certificate &
rd
Approved 3 party certificates….)
Installation of Improper manual
blocks at handling, lack of
designed areas proper training and Proper Training for block works
using wooden skills for concrete Adequate Supervision
block works. falling Serious body injury Tool box talk on proper manual
platforms &
4 hazards while handling 2 5 M
scaffolds for No 4 5 H R
miscellaneous installation of Maintain always good
block works: scaffolding and housekeeping.
working at wooden Use appropriate PPE.
frames while
installation of
Control
Risk
Risk
compliance
Job steps/
Conseque
/Potential
identified
Remarks
might be
Residual
Activities
Hazards
Control
Hazard
Risks /
Rating/
Harm/
Sl no
Legal
nces
E/I/R
Who
Mitigation action to be taken/ Risk
Risk level Hazard/Risk Control Method
L S R L S R
concrete blocks
Control
Risk
Risk
compliance
Job steps/
Conseque
/Potential
identified
Remarks
might be
Residual
Activities
Hazards
Control
Hazard
Risks /
Rating/
Harm/
Sl no
Legal
nces
E/I/R
Who
Mitigation action to be taken/ Risk
Risk level Hazard/Risk Control Method
L S R L S R
Adequate housekeeping must be
maintained
Adequate supervision
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Control
Risk
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Plastering Works
Sand used will be washed and screened and as per approved material.
Leveling pads shall be fixed to the required thickness. Spray dash with bonding agent shall be done for the
plaster areas and cured for 2 days before doing the Plaster. Plaster thickness shall be as per the given
specifications.
Plaster accessories like GI corner-beads, plaster stops, metal lathe etc. shall be provided wherever necessary and
as per specification.
All finishing works shall be carried out as per specification to the satisfaction of the consultants. Approval for all
finishing materials shall be taken prior to starting the respective work.
Control
Risk
Control
Risk
Task/Job/Operation: PLASTERING Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-008 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED Risk Assessor:
& OPEN WASH AREA ON PLOT NO. 5337865 @ Mr. JAMES NEEL(SO)
Client: SILVERLINE CONSTRUCTION MACHINERY LLC
SAIH SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Shovel, Telescopic handler, bobcat , Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Scaffolds goggles, gloves
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Well supervision
Proper supervision
All vehicles / equipment’s to be
installed with all safety materials
(reverse alarm, warning light, license,
rd
vehicle certificate & ADM Approved 3
party certificates….)
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
when
reversing.
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
might be Harm/
Consequences
Risks / Who
Risk level Risk
compliance
Job steps/
/Potential
identified
Remarks
Activities
Hazards
Control
Hazard
Sl no
Legal
E/I/R
Mitigation action to be taken/ L S R
Hazard/Risk Control Method
L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Lockout/tag out is the specific practices and procedures to safeguard employees from the unexpected energization or
startup of machinery and equipment, or the release of hazardous energy during service or maintenance activities
Disconnects the machinery or equipment from its energy source(s) before performing service or maintenance.
The authorized employee(s) either lock or tag the energy-isolating device(s) to prevent the release of hazardous
energy and take steps to verify that the energy has been isolated effectively.
Materials
All the materials used for the installation shall be as per the consultant’s/client’s approval.
Any material delivered at site should be inspected and approved by the consultant before installing them.
Pre installation
Ensure all drawings and electrical method statement is approved and available to the installation team.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Prior to the installation of cables in any area, cable ladders or any containment system must be inspected and
approved. Ensure that the factory test reports for continuity of the cables is provided and reviewed to ensure the
fault free installation.
Check that ladders/trays are free from any sharp edges and have sufficient space for installing the cables.
Ensure that ladders/trays are provided with purpose made bends to accommodate the minimum bending radius
of the cable. This is to ensure that cable is not given undue stress.
PVC sleeves shall be installed for all cables passing through brick, block or concrete or similar structures in case
there is need for future withdrawal.
Collect and keep ready at site materials such as cable pulling sleeves, tools, rollers and tackles etc.
Preparation
Cables and wires shall be installed in accordance with the approved shop drawings and properly coordinated with
MAIN CONTRACTOR site engineer/construction manager for exact locations and levels.
Proper marking / selection of location on site to be done prior to commencement of electrical installation works.
Complete a mock-up installation before main works and get its approval.
Wire pulling
Control
Risk
Make sure that all conduits and boxes in both ends are free from damages and blockages etc. and installation is
approved.
Blockage shall be checked by inserting the draw wire and checking that it reaches to the other end without any
disturbance.
Once the conduit is not blocked the wires shall be pulled using the draw wires while ensuring no damage occurs
while pulling.
Pulling compound or lubricant shall be used for pulling the wires where required.
Use soap-based pulling compound for short runs i.e. less than 20 meters for semi conductive insulated wires.
Use wax based pulling compound for the runs greater than 20 meters for semi conductive insulated wires.
While pulling the wires care should be taken to not insert the pull tension greater than the manufacturer allowed
limits.
Cable should be free of any static load i.e. to be places side by side parallel on the cable tray or ladders. Any kind of
dead weight on the cable shall be avoided. At all times the cable schedule & section drawings for the relevant area
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
will be referred to ensure proper location of cable on the required ladder and to ensure compliance with project
specifications.
A pulling compound / lubricant shall be used where necessary as per site conditions i.e. in slabs and underground
conduits etc., the lubricant should not deteriorate the cable insulation. The cables shall be secured to the
containment system using approved cable ties for horizontal runs and cable cleats for vertical runs. All control cables
will be installed at a minimum distance of 100mm from power cables unless otherwise agreed with consultant as per
site conditions.
Earth (green/yellow) cables shall also be pulled along the power cables. At all-time of pulling, mark both power and
earth cables for pairing them on both sides of connection i.e. at sending and receiving ends. Before termination
complete length and route of the cable shall be inspected by QA/QC engineer, after which a WIR shall be raised for
consultant approval. Cable shall be caped and sealed on both ends after installation until termination is done.
Termination shall be done by using the approved termination materials that include glands, lugs and other
accessories part of termination kit, by using proper crimping tools. Matching color gland sheaths shall be provided.
All termination shall be provided with tight fitting covering sleeves.
Set the Meggar meter to 1000 volts DC for cables and 500 volts DC for wires. Take reading between phase, phase
and neutral, phase and earth neutral and earth. Note that resistance reading must not exceed 2 mega-ohms
Control
Risk
(MΩ). Check and record the resistance readings as per specification on the approved insulation resistance test
forms.
Cables Identifications
Install the tags / labels as per project specifications and as per approved material submittals.
Cables shall be identified at feeders i.e. the sending and receiving ends (outgoing cables in SMDB’s and final
DB’s) about 50mm below the gland.
Identification labels shall be provided at all positions where cable changes direction and each side of the wall or
floor slab and where cables are in multiple runs.
Cores of cables connecting control gear, thermostats, valves etc will also be identified and shall be fitted with
identification sleeves bearing the same marking as the terminals of the apparatus to which these are connected.
For cables at feeders, identification will be done as per specification and approved materials.
Ensure a safe working platform with proper hand rail and intermediate rail
Ensure all elevated working areas have proper hand barriers/hand rail all around and install intermediate rails
where employees need to carry out then works in a crouching position
Ensure employees use proper fall arrest system such as full body harness and hood the harness to a proper
anchorage point wherever fixing hand rails is not practicable
Control
Risk
Train employees on work height safely and the use of fall arrest system
All mobile man lifts scissor lift must be equipped with necessary warning and alarm system supervisors
(revolving beacon light/reverse alarms)
Don’t lift any erection Steel materials, MEWP must be only used for lifting working personals.
Control
Risk
Contractor Premises of
Consultant Review point - Representative of indicated party to review submitted documents, result of
Inspection / Site Work Area R
Approval test etc..
Coordinates
Control
Risk
Task/Job/Operation: ELECTRICAL WORKS Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-023 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL(SO)
Client:SILVERLINE CONSTRUCTION AND MACHINERY.
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Equipment Required:
goggles, gloves
Risk
might be Harm/
Consequences
Residual
Control E/I/R
Risks / Who
Rating/
compliance
Job steps/
/Potential
Risk
identified
Remarks
Activities
Hazards
Hazard
Risk level
Legal
Sl no
Control
Risk
working platforms.
All personnel working at site to
be informed about the testing
and commissioning of electrical
line/machineries by circulars and Tool
Box Meeting.
1. Identify Hazards
Control
Risk
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Control
Risk
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Ordered materials is delivered to the site and received by the site foreman.
The site foreman will check the materials as per the delivery note and will verify against approved material submittal and
Make sure that all materials are free from damages and defects:
subcontractor for MEP coordination and serviced drawing to ensure clear demarcation of MEP services.
Mark the level of ceiling on the walls with the help of chalk line powder as per the levels indicated in the shop drawings.
Fix the L angle/ Shadow line stopping Angle on the marks with the help of Hammer screws. The W Wall angle should be
Control
Risk
Cut the “L-Angle for the vertical suspension” 100mm more than the suspension length. Snip one flange of “Suspension” at
100mm from one end and bend it to form a L. Secure the bend part by screwing the overlapping metals with drill point M4.2
wafer head screw. Drill the upper slab with suitable drill @ specified center’s along the line of the main channel offset by
After suspending the Hanger, fix the main channels (1200mm max centers) to the rigid hanger with the help of wafer head
screw. When Main channel are spliced, the ends shall be overlapped not less than 300mm and securely fastened with wafer
head screws.
Fix the furring channels at a spacing of 600mm at right angles to the main channels. The main channels are connected to
the furring channel with the help of wafer head screws/ preformed clips.
members.
After completion of fixing of gypsum boards, the joints have to be sealed as per the following procedure:
Control
Risk
1. Apply readily available joint compound evenly and fully over the gypsum board joint duly filling the voids
2. Centre the joint/fiber tape reinforcement between the board joints and press it down into the fresh joint
compound.
3. When the tape is embedded, apply a skim coat of joint compound immediately after embedding.
4. After first coat is dry, sand slightly and apply thin finishing coat of topping compound to joints.
5. After the second coat is dry, sand the surface lightly to achieve the flat smooth surface.
Control
Risk
Contractor Premises of
Consultant Review point - Representative of indicated party to review submitted documents, result
Inspection / Site Work Area R
Approval of test etc..
Coordinates
Control
Risk
Task/Job/Operation: GYPSUM WORK Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-030 REV-00
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHUNERY LLC OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Shovel, bobcat , Scaffolds, crane, Power Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
tools, tools goggles, gloves
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Base supports
Scaffolding tag system should be
maintained
Adequate Life line (Wire ropes only – min
8mm to 12mm) should be provided
Safety harness with lanyard should be used
properly and anchored at rigid point
Scaffold supervisor should be Checked
Periodically
Safety harness should be use above 1.8 mtr
height
Only Scaffold erectors should be erect
scaffolding
Use PPEs Properly –mainly Safety Harness,
Helmet, Hand gloves, Goggles, etc…
Well Safety Training & Tool box meetings
Adequate Full platform provided
Injury to the personals Should be tight Tires of all mobile
Erection
of Falling down when Loss of Life scaffolding
Mobile Working on Mobile Damage to the Should be provided adequate Guardrails
5 3 5 H R 1 5 L
Tower/ Scaffolding(Workers materials and Toe boards
Mobile &Materials) Scratches any part of Provide adequate outriggers
Scaffolds body Safe access-egress should be provided
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
equipment in a area
of hydrocarbon gas
in the combustible
range, coming in to
contact with an
ignition source and
leading to an
explosion or fire.
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
Risk
compliance
Job Residual
Remarks
Rating/
Control
Risks / Who might
Legal
Risk
E/I/R
Sl steps/ Hazard identified Risk level Mitigation action to be taken/
be Harm/
no Activit- /Potential Hazards Hazard/Risk Control Method
Consequences L S R
ies L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Plumbing Works
Trench Preparation for the underground pipes
The contractor shall carry out the excavation for the trench depending on the pipe diameter, type of ground and depth of
lying.
Bedding for pipes shall be constructed by spreading and compacting approved bedding material over the whole width of the
pipe trench.
After pipes have been laid, additional material shall, if required be placed and compacted equally on each side of the pipe.
Where pipes are required to be bedded directly on the trench bottom. Final excavated surface shall be trimmed and levelled
Control
Risk
Anchor bolts/ raw bolts are fixed and threaded rod of suitable length is fixed
Straight pipes, cleaned from the inside, with fittings are inserted and properly clamped
Pipeline thus erected are plugged from both ends at the end of the day work
Mark the drainage pipe route with the lime powder for excavation of trench as per the approved drawings.
Check the trench bottom level with levelling instrument to match the invert level of the pipe line as per the approved
drawings.
Provide concrete base with required gradient for a firm base for pipe installation.
Install the pipe between the manholes as per the specification and approved drawings.
Control
Risk
Make sure that the maximum distance between manholes should be only 25 to 30mtrs.
Make proper supports after the installation and checking of the level.
After checking the level of the installed pipes arrange for testing.
Control
Risk
Control
Risk
Task/Job/Operation: PLUMBING WORKS Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-016 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL (SO)
Client: SILVERLINE CONSTRUCTION MACHINERY LLC
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Equipment Required: MEWPs, Telescopic handler, Bobcat
goggles, gloves
Risk
Legal compliance
Hazard identified
Residual
might be Harm/
Consequences
Rating/
Control E/I/R
Risks / Who
Risk
Job steps/
/Potential
Remarks
Risk level
Activities
Hazards
Sl no
Drilling of
block walls for Wear gloves, Wear safety glasses
pipe inlet/outlet
Flying fragments, eye injury Suitable Mask and Goggles shall be
Application of used
1 Plumbing Respiratory deices No 3 4 H R 1 4 L
works solvent
Trained personnel should be used
Injury to the personnel for works.
Water line
damage due to
improper
Control
Risk
connection/high
pressure
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Control
Risk
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Surface Preparation
All necessary surface preparation shall be carried out prior to primer coat.
Work shall have a smooth finish and adequately cured prior to painting.
Paint Preparation
The paint materials delivered to site shall be checked and confirmed to comply with the approved system/samples.
The materials must be stored in a well-ventilated place protected from direct sunlight.
Protection of adjoining surfaces not to be painted shall be done by providing polythene sheets and masking tapes.
Control
Risk
Painting subcontractor must not commence any work until each stage of painting procedures have been checked by Loyal’s
supervisor or Consultant.
Control
Risk
Task/Job/Operation: PAINTING Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-09 REV-0
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
Client: SILVERLINE CONSTRUCTION MACHINERY LLC OPEN WASH AREA ON PLOT NO. 5337865 @ Mr. JAMES NEEL(SO)
SAIH SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Equipment Required: Plastering machine, Power tools, tools
goggles, gloves
Risk
Consequence
Control E/I/R
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Hazard
Harm/
Sl no
Legal
Risk level Mitigation action to be taken/ Hazard/Risk
s Control Method L S R
L S R
Control
Risk
Risk
Consequence
Control E/I/R
Residual
Risks / Who
compliance
Job steps/
Rating/
/Potential
identified
Remarks
might be
Activities
Hazards
Risk
Hazard
Harm/
Sl no
Legal
Risk level Mitigation action to be taken/ Hazard/Risk
s
Control Method L S R
L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Demolition works
The scope of works involved in the demolition of the existing structures is as follows:
a) Obtain NOC’s from Etisalat, DEWA, and Drainage or any required NOC’s from the authorities.
d) Disconnection of services
Control
Risk
k) Demolition of flooring
l) Demolition of foundations
METHODOLOGY
All the requirements of Local and Statutory Authorities regarding notification of demolition works shall be complied.
Control
Risk
Before starting the demolishing work, all the available drawings and documents will be studied and carry out a through survey and
examination of the building, structure or service to be demolished.
All the details with record drawings will be provided to client, showing the level, size, position and contents of any abandoned
services, foundations, underground chambers, wells, underground tanks or any other work discovered during the demolition.
Any building, structure or services to be retained at site and any adjoining property or services liable to be affected by demolition
shall be examined before demolishing and any existing crack or other evidence of damage shall be noted.
d) . Disconnection of Services:
Obtain necessary NOCs from the respective authority prior to start the work.
Control
Risk
Before starting demolition, the contractor shall arrange with the client and Statutory Authorities, if applicable for the locating
and marking of the position of all known services affected by the work and for the proper disconnection of their mains supplies
and cables.
Any electrical cabling will be removed for recycling prior to soft stripping and the demolition of the structure.
No cable-stripping work will commence until the electrical supplies to the site have been irreversibly isolated either to the main
distribution board by the local electricity supply company or from the main distribution board by a suitably qualified electrician.
Hand tools will be used by the demolishing operatives to cut all the exposed electrical cables and which are easily extracted, but
which are not exposed.
MEWPS will be used to remove the cables in the trays or the wire present above the floor level.
The removal of cable insulation and armor is to be undertaken using a machine
All waste generated by the cable-stripping is to be disposed of appropriately.
8. Soft Stripping:
Control
Risk
An internal soft strip of the buildings will be carried out by demolition operatives to remove as much of the waste materials from
the building ahead of the demolition works.
Materials that are to be removed by the internal soft strip can include doors, door frames, fixed and non-fixed furniture, carpets
and floor coverings and other materials which obstruct the construction of asbestos removal enclosures.
Operatives will strip out all doors, frames, and windows, timber of any description, toilets, pipe work, electrical items and any
debris.
Any clean, unpainted constructional timber will be segregated from the general waste. Where this material is free of nails,
screws, hinges etc. it will be segregated for recycling and any materials deemed as not suitable for recycling will be removed
from site.
Where possible the materials will be loaded by hand method into skips and removed from the site. Where access for skips is not
available the materials will be segregated and stored within the building where they will be removed at a later stage.
Operatives will use Step ladder for stripping the fall ceiling tile and AC ducts.
Control
Risk
Ensure the step ladder is damage free and 3 point contact must 3-point contact (two hands and a foot, or two feet
and a hand) when climbing/ descending a ladder.
Ensure that the ladder has been placed on a stable and level surface that is not slippery.
All the waste generated during the removal of fall ceiling tile is to be disposed of appropriately.
Control
Risk
First roof sheet panel to be removed from the ridge area of end wall. Removing the ridge panel first and progress
toward the rear side.
Follow the pattern line by line towards the other side end wall.
Ensure that the MEWP is certified and all the operators are 3rd party certified.
All the equipment involved in the demolishing activity will be inspected and all the personal shall be inducted and
trained before they commence the work on site.
All the removed screw should be secured properly and stored
The entire removed panel to be packed in a bundle, not exceeding 8 panels.
More caution to be considered while addressing the skylight panels.
The old panel bundle to be offloaded to ground with mobile crane as the work progress.
Stack the bundle properly in the ground and clear at the earliest.
Remove the edge protection with the help of MEWP.
Control
Risk
First wall cladding panel to be removed from the ridge area of the end wall, removing the ridge wall panel first and
progressing towards the rear side.
Follow the same pattern till removing the last wall panel.
The entire removed wall panel should be secured properly and stored.
All the removed panels to be attacked in a bundle not exceeding 8 panels.
More caution to be taken during the shifting of the damaged wall panel.
The entire waste panel must be removed from the site.
3. The building to be demolished on site is of steel framed type structure, clad in corrugated single ply steel sheeting.
Control
Risk
4. All workers and staff will be given induction training and job specific instructions by the site in charge.
5. Workers will be provided with PPE’s such as reflective jackets, safety belt, shoes, masks, goggles, full body harness etc.
6. Prior to dismantling the block, all the fittings along the wall such as Windows, doors, duct etc. to be removed.
7. The masonry walls and RCC slabs of the building will be dismantled thereafter using Excavators fitted with bucket and
breakers.
8. Care to be taken that, while the block wall dismantling area should be isolated and no person should trespass.
8. Ensure the excavator is certified and the operator is 3rd party certified.
Control
Risk
The office area consists of the roof panel and a mezzanine floor consisting of hollow core slab.
After the removal of the roof panel, proceed with the removal of secondary members and the hollow core slab bay by bay.
Start from any one side of the office; consider one sequence frame consists of 4 columns.
First remove the roof flange brace, sag rods and purling in this bay by soft stripping.
Procced to remove the hollow core slab. Make 4 to 6 holes of 4” dia (depending on the panel size) in the hollow core, lift each
panel with the help of chain and crane arrangement.
Once the secondary members and slab is removed, remove the steel beams and then steel column.
Repeat this pattern for the entire bay.
The removed slab to be stacked properly and removed periodically.
The removed steel member to be stacked properly and barricade should be provided.
3rd party certified rigger should give signal to the crane.
Experienced team will be appointed for the execution of the work.
No person should stand below the suspended load or below the lifting area.
Removal of bolts to be carried out by spanners and power tool such as tighter.
Now that roof sheet and wall sheet is removed, proceed with the dismantling of steel structure.
Start with the end wall and proceed bay by bay pattern.
In the first bay, remove the roof flange brace, cross bracing, sag rods and then purling by soft stripping.
Once secondary members are removed, proceed with the primary members.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Mobile crane of 25 ton to be used for all the primary members dismantling.
Remove the end wall rafters, section by section depending up on the size of the rafter.
Remove the wall purlin bay by bay and remove the particular end wall column.
For the remaining main frame, remove secondary members, followed by dismantling of rafters section by section depending on
the size. Review the wall purling along the eave side and remove the column along the eave side.
Repeat this pattern towards the other end wall.
Prior to the removal of the floor slab the area must be isolated and warning signboards must be displayed.
Once the steel structure is removed, the floor slab shall be demolished from any side.
The demolition of flooring will be done using excavators fitted with breakers and buckets. The tie beams will be demolished
along with the flooring. The debris will be removed intermittently.
All the worker and the operator involved in the activity must be induced and RA must be communicated to the work force.
The debris that is generated during the activity will be stacked properly and removed appropriately.
Once the floor is demolished excavation will be done to demolish the foundations. The foundations are exposed and will be
demolished using breakers. The reinforcement bars will be cut and separated. The concrete debris etc. will be carted away to
approved dump yard using dump trucks.
Control
Risk
The reinforcement bars will be cut and removed using gas cutters. The demolition will be done up to the floor level. The debris
will be removed using dump trucks at regular intervals.
After clearing the debris, the foundation pits etc. will be backfilled and the area will be levelled properly.
Control
Risk
Contractor
Premises of
Consultant Review point - Representative of indicated party to review
Inspection / Site R
Approval submitted documents, result of test etc..
Work Area
Coordinates
Consultant Owner
Contractor
Acceptance
Criteria Specific
Activity Description of Inspection Drawing N" of
(Controlling Quality
NO & Test Activity reference Contractor CEC Punchlist
Procedure, Report
Signature Signature Item N"
Specifications, Code (If
Standars etc..) H W R H W R H W R any)
SAFETY MEASURES
1 TAKEN BEFORE
DEMOLITION WORK
2
Control
Risk
Task/Job/Operation: DEMOLITION Project: : PROPOSED G-OLY OFFICE, G+M WORKERS Ref No: RA- REV-00
FACILITY, G-ONLY SHED, OPENSHED & OPEN WASH AREA LBC-001
Main Contractor: LOYAL BUILDING CONTRACTING LLC. ON PLOT NO. 5337865 @ SAIH SHUAIB 4, DUBAI Risk Assessor:
Client: SILVERLINE CONSTRUCTION AND MACHINERY RENTAL LLC Mr. JAMES NEEL (SO)
Consultant: DESIGN HOUSE ENGINEERING
Date : 05-02-2020 Date Next Review: 05-08-2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator
goggles, gloves
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
The whole working area must be properly
Accident to other
Isolation of the Major/Minor injury isolated from other unauthorized
people who is not
1 due to unprotected personnel. Watch person to be provided 1 3 L
area involved in the No 3 3 M R
demolition area. to aware other people of the ongoing
activity. activity.
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Tool box must be conducted and it must
be documented.
Supervisor must be available at site
during dismantling the electrical cables.
Waste debris raised during this process
must be removed immediately.
Hand gloves must be issued to workers
who are handling sharp edge object.
rd
3 party certified MEWP must be used.
rd
Ensure the operator has a valid 3 party
training card.
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Only competent person shall be
permitted to carry out the demolition
activity.
Full time supervisor to facilitate and look
over and monitor the whole operation.
Edge protection must be provided over
the roof sheet.
Edge protection post to be installed using
MEWP. Ensure that MEWP and operator
rd
is 3 party certified
Provide roof access and avoid using
MEWP for accessing roof.
Safety net will be provided beneath the
roof sheet to prevent the person falling
from height.
Removing of roof Fall from height. Injury to the Tool box talk must be conducted regarding the 1 5 L
5 sheet and wall Object falling from workers involved in Yes 3 5 H R hazard and risk associated with the removal of
cladding height, the activity. existing roof sheet.
Where tools or equipment are being
used adjacent to a roof edge and there is
a risk of falling of objects, in order to
prevent, the objects must be attached to
the safety lanyard.
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Make sure that the area is isolated
Keep the area clean such that no
machines or materials are stored in the
area
Major Injury to
Collapse of block wall Keep adequate signboards 2 4 M
7 Block Wall person, or property Yes 4 4 H R rd
on material or Person The Excavators and its operator to be 3
damage
party certified
Spray water periodically to avoid dust
pollution
Remove the concrete waste periodically
Tool box talks to be given before
commencing the activity
Suitable PPE like Safety shoe and safety
Physical injury and
8 Soft Stripping Minor Injury gloves to be worn by the workers. 1
hand injury to the Yes 3 4 H R 4 L
Ear protection to be provided for the
workers involved.
workers.
All debris to be segregated and stockpile
by plant ready for disposal.
1.Serious injury, Strictly comply with PTW system.
death due to person
being knocked by All the crane operators and riggers must
rd
crane part. have trakhees approved 3 party
Equipment
Use of crane for certificate. 1
9 2.unstable groung damage, personal No 3 5 M R 5 L
lifting. Ensure all safety and operational
causing machine to injury
instructions are followed as per the MS.
tip over and trap Only trakhees approved third party
operator or other riggers would be authorized to give signal.
workers. Work will not be permitted, if wind speed
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
3. high wing causing reaches 30 KM/HR
loss of control of laod
4.Unauthorized
person using crane.
5.load falling due to
improper securing
Competent supervisor must monitor the
working area to ensure that the proper
procedure of demolition is followed as
mentioned in MS
1.Trip, slip, fall Full body Harness must be worn by the
2.over exposed to worker, where there is a tendency of
vibration. All the workers falling from height.
Demolition of the 2 3
10 involved in the No 3 3 M R Suitable PPE like safety shoe and safety L
area. 3. Dust generated activity. gloves to be worn by workers.
during demolition. Dust mask to be provided for the workers
involved in the activity.
Worker handling hilti/ Jackhammers must
be given ample time to recover from the
impact of this equipment.
Control
Risk
Risk
/Potential
identified
complian
Consequ
Remarks
might be
Activities
Hazards
Residual
Control
Hazard
Risks /
steps/
Harm/
ences
Legal
Rating/
Sl no
E/I/R
Who
Mitigation action to be taken/ Hazard/Risk
Job
Risk
ce
Risk level Control Method
L S R L S R
Noise to be controlled and reduced to as
low as is reasonably practical through the
careful selection of plant and method of
demolition.
when noise is believed to be above 80
All the workers
Noise emitted during dBA (i.e. when you have to raise your 2 2 L
12 Noise Pollution involved in the No 3 3 M R
demolition work. voice to be heard two metre away).
activity.
Appropriate hearing protection to be
issued and worn.
Provide information, instruction and
supervision when and how to correctly
use hearing protection
Debris collection and disposal must be
supervised to avoid congestion of the
Accumulation of
Slip, trip and fall working area.
12 Housekeeping waste/ working area 2 3
hazard. Yes 4 3 H R Housekeeping shall be provided as the M
congestion work is on- going were accumulated
debris are to be removed to sustain a
workable area.
Control
Risk
5. Use of mobile phones during working hours is prohibited, except for emergency reporting only.
6. No eating, smoking and sleeping at the construction worksite. Use the facilities provided on site
7. Do not use defective PPE, tools, machinery, or equipment – get them replaced before you start your work
8. Report all near misses and accidents immediately to HSE In charge and your work leader
9. Work leaders are accountable for the behaviour of their operatives
10. Conduct a Tool Box Talk, Risk Assessment Review or issue safety instructions before the start of the day’s work.
11. Copy of this Risk Assessment available on site
Environmental
1. All waste materials will removed daily from the wok area and transferred to the designated waste skip
2. All Hazardous waste shall be immediately removed as per UAE regulation and dispatched slip maintained.
Risk Assessment Methodology
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk
Control
Risk
Equipment’s on site
General Tools
Control
Risk
1 CALIBRATION CERTIFICATE
CHECK
Control
Risk
Task/Job/Operation: VEHICLE AT SITE Project: : PROPOSED G-ONLY OFFICE, G+M Ref No: RA-LBC-029 REV-00
Main Contractor: LOYAL BUILDING CONTRACTING LLC. WORKERS FACILITY, G-ONLY SHED, OPENSHED & Risk Assessor:
OPEN WASH AREA ON PLOT NO. 5337865 @ SAIH Mr. JAMES NEEL(SO)
Client: SILVERLINE CONSTRUCTION MACHINERY LLC
SHUAIB 4, DUBAI
Date : 5/2/2020 Date Next Review: 5/8/2020 Approved By: Reviewed By:
Mr MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Equipment Required: Shovel, bobcat, crane, JCB, Boom Loader, Recommended PPE: Hard Hat, Safety shoes, Safety Harness, overalls, dust mask,
Trailer, Car, and Pickup. goggles, gloves
Risk
Residual
compliance
Hazard Rating/
Remarks
Risk
Control
Job Risks / Who might be Risk level
Legal
E/I/R
Sl identified Mitigation action to be taken/
steps/ Harm/
no /Potential Hazard/Risk Control Method L S R
Activities Consequences
Hazards L S R
Control
Risk
Risk
Residual
compliance
Hazard Rating/
Remarks
Risk
Control
Job Risks / Who might be Risk level
Legal
E/I/R
Sl identified Mitigation action to be taken/
steps/ Harm/
no /Potential Hazard/Risk Control Method L S R
Activities Consequences
Hazards L S R
Control
Risk
1. Identify Hazards
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
Control
Risk
4 16 12 8 4 6 Medium Risk
Severity
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
Control
Risk