Substitute 12 cy for sand quantity to be dumped and 95 cy/hr for truck loading rate.
12
Load time =
95
= 0.126 hr
Substitute 7 miles for distance transported and 30 mph for haul speed.
7
Haul time =
30
= 0.233 hr
Substitute 7 miles for distance transported and 40 mph for return speed.
7
Return time =
40
= 0.175 hr
Substitute 0.126 hr for Load time, 0.233 hr for haul time, 0.050 hr for dump time and
0.175 hr for return time.
T.C = 0.126 + 0.233+ 0.050 + 0.175
= 0.584 hr/trip
Therefore, the total cycle time for one trip is 0.584 hr/trip .
Substitute 0.584 hr/trip for T.C and 0.126 hr for Load time.
Trucks reqd = 1250 / 136
= 9.19 trucks
9 trucks Therefore, the number of trucks required is 9.