You are on page 1of 6

special Tunnelling

Underground Space & Tunnelling -


Challenges & Technology
The geological and geotechnical investigation program is required be adequately
accomplished in order to provide realistic information for economic and safe
design and construction of the underground structures, writes MM Madan,
former Executive Director, NHPC.

I
n India construction of tunnels in the form completed successfully in road & rail sector. 50km
of underground passages and water carrying long tunnels are very common today. For example,
conduits dates back to Mahabharata era. The 137 km long water supply tunnel was made in
famous lakshagriha escape route planned by 1945 in New York. Similarly, in Finland also 120
Pandavas was through secret tunnel under the km long tunnel has been made for water supply.
lakshagriha. Many more tunnels have been found In rail sector China and Finland have 123 km and
in the old forts and palaces which were used as 100 km long tunnel respectively. In road sector
secret escape routes. In British era many railroad the famous Gothard Base Tunnel of Switzerland is
tunnels were made. However, tunnelling for 151.84km long and has two single tunnels of about
hydro power took a lead and most of them were 57km length each.
constructed mostly in Himalayan terrain. The total road tunnels constructed in China
In the modern era, tunnelling and underground are more than 15285km (2017) and followed by
works constitute a major portion of development Japan which has more than 4026km (2012) of
MM Madan of rail tunnels, road tunnels, hydro power, mining, road tunnels and Norway 1338km (2017). India’s
Executive Director strategic oils reserves, water supply & sewerage, tunneling and underground segment has witnessed
(NHPC), CEO & coal mines, nuclear power projects and urban significant development in recent past. For
President (JSPL),
area metro rail network as well as strategic secret example, Metro rail network itself has executed
Director (Hydro) - GVK,
CEO (Hydro) - escape routes etc. about 500km of tunnels in India. Presently tunnels
LNJ Bhilwara Group Around the world tunneling has become a are being constructed at a pace of over 100 km
part of life. Many large and long tunnels have been per year.

62 | CONSTRUCTION TIMES | July 2020


special Tunnelling

PirPanjal
Railway Tunnel

India has also constructed longest 11.21 km Challenges


PirPanjal railway tunnel and 9.2 km long Chenani- It has been observed that tunneling projects in
Nashri and Rohtang 8.9km long road tunnels in India faces many challenges. The tunnels which
the fragile Himalayas besides 373 kms of are located in Himalayas are faced with complex
tunneling for Delhi Metro only in the country, geological conditions and then contractual
to name a few, completed and commissioned disputed override and the work gets affected.
recently. In the Indian context, as per available Even EPC contracts and turnkey contracts enter
data, the longest road and rail tunnels are mostly into unending disputes.
constructed in J&K, followed by Himachal. In execution of hydropower projects, it
In almost all hilly areas road and rail tunnels has been observed that, unforeseen geological
have been planned and execution is going on at conditions and associated geotechnical problems
fast pace. are major contributor to the cost and time
In addition, major road tunnel projects like overruns. Geological conditions alone cannot be
6.5 km long Z-Morh, 14.2 km long Zojilla, blamed for all the cost and time overruns. Most
having strategic importance, are in hand for of the time, the time and cost overrun are the
implementation. Sikkim is constructing rail tunnel of result of inadequate investigations, inadequate
about 42km length besides 25km long road tunnel geological data, inappropriate interpretation of
is also under construction. The longest power available data and incompetency in dealing with
tunnel for hydro project under construction is at the problems during execution and poor decision
Parbati-stage –II project having a length of 31.5 km making to deal with the issues once they have
besides to name a few; Kishangangatunnel (14km arisen. The basic problem faced in attempting to PirPanjal Railway
single face), Dulhasti tunnel (10.6km), Uri tunnel predict the prevailing geological and geotechnical Tunnel.
(10.5km), BSL project tunnel (13.12km), Nathpa
Jhakari (28km), Teesta St-3 (13.8km) & Teesta St-5
tunnel (17.2km) for hydro projects have been
completed successfully.
In spite of availability of the state-of-the-art
technology and equipment, the timely delivery
of such projects for creating underground
space has always been a matter of concern.
At present, many tunneling projects are under
construction in all the sectors. It is estimated
that in the future, the infrastructure development
will take place underground considering the
environment, scarcity of land, and for the purpose
of security. It has been planned to construct
about 6000km of road tunnel and 1000km of rail
tunnels in addition to hydro and strategic area
tunnels. However, in India there are no records
available for all the tunnels constructed in different
sectors.

July 2020 | CONSTRUCTION TIMES | 63


special Tunnelling

TBM at work

situations in the construction of surface structures disposition, dimensions, nature of material in the
and underground works is the inadequacy of the zone, its location with respect to a structure and
information obtained from the site investigations in the type of structure, etc.
squeezed investigation program.
The complex geological regions like the Underground Works
Himalayas pose major challenges for construction In tunneling and underground works, the complex
of hydroelectric projects. Projects located in geological setting has caused considerable stability
the region have faced many geological and geo- problems. The geological uncertainties for
hydrological issues while executing surface and underground openings are related to two major
subsurface works. The surface problems broadly factors: non-geological and geological.
include existence of inhomogeneous deep - The non-geological factors are connected
overburden in the river bed or buried valley, abrupt to the level of skill and expertise gained
change in bed rock profile, occurrences of fault by experience and the interpretation and
The objective zones / shear zones / fractured rock in the dam decision making skills during the planning and
of geological/ foundation and slope instability in the abutments as construction phases of tunneling projects. The
geotechnical well as rock fall /slide and failure of back slope of ability to evaluate and tackle the stability issues
investigations surface power house, etc. The major subsurface during planning and construction and the tools,
is to get problems in tunneling and underground works methods and technologies used in that process
the basic include issues such as squeezing ground conditions, have great significance, since erroneous
upheavals, tectonic stresses, popping, rock interpretation may result in considerable loss.
data for the bursting, high temperature gradient, heavy ingress - The geological factors are related to the
economic, safe of water during execution, existence of large shear geological complexity of the region. The
design and zones, flowing ground conditions, abrupt change complexity is represented mainly by four
construction in strata conditions, low cover zones or very high engineering geological characteristics that
of surface and cover/ overburden and emission of methane and have caused major stability problems during
underground other gases etc. tunnelling. These are: (a) weak rock mass
structures. quality (b) high degree of weathering and
Surface Structures fracturing (c) rock stresses and (d) groundwater
The occurrence of weak zones in the form of effect.
fault, shear zone etc. and buried channels is a It is a fact that the key to success or failure of
hazard in relevance to dam foundation and other any tunneling project is the quality of the rock mass
surface structures of a hydropower project. that the tunnel passes through and rock support
Their presence in the foundation of dams poses measures that are applied during tunnel excavation
problems of leakage creating uplift pressures, as well as the speed of providing supports so
settlement and sliding, etc. Thus the dam designers minimize the deformation of the freshly excavated
have to live with these adversities, analyzing and rock mass. In this respect, accurate evaluation,
treating them adequately to make the structure analysis and interpretation of the rock mass quality
safe beyond doubt. Treatment of these zones play significant roles. A major challenge therefore is
of weaknesses is mainly dependent on their to address the geological uncertainties so that cost

64 | CONSTRUCTION TIMES | July 2020


special Tunnelling

effectiveness and safer tunneling may be achieved. there will be very limited scope of deviation and
Inaccessibility to the investigation sites of tunnels the nature of work would not undergo major
and caverns, particularly in the Himalayan region changes during construction stage. The constraints
and other hilly areas, is the major hindrance in and uncertainties are well understood and suitable
carrying out geological / geotechnical investigations. provisions are made in design so that these are
Thick vegetation, rugged topography, river not met as surprises. The main requirement of a
crossing, obscured geological evidences along the DPR being bankable is the assurance of the project
tunnel alignments, etc., make the task of geological being constructed within the estimated cost and
/ geotechnical investigation more difficult. As the time schedule.
tunnels are very long, variations in rock types and The problems especially while executing
rock mass characteristics are imminent. Due to hydropower projects in complex Himalayan region
poor accessibility it is difficult to carry out detailed may be regarded as challenge and opportunity
explorations by drilling at the identified locations for generating new knowledge base and thereby The aim should
and these issues delays the investigation program. increasing self-reliance, particularly in tunneling be to obtain
While tunneling in complex and varied and underground works: The construction of
geological settings, prediction of rock mass quality, hydroelectric projects involving surface as well
as complete
analyzing stress induced problems, squeezing as tunnels and underground civil structures is a
information of
and prognostication of inflow and leakage have demanding task when these structures are located the subsurface
often been found difficult during the planning in rugged terrain under complex geological setup. geological
stage. Considerable discrepancies have been It is observed that execution of a number conditions
found between predicted and actual rock mass of hydroelectric projects in India have become to arrive at
conditions, resulting in significant cost and time hazardous, time consuming and costly affair on a techno-
overrun for many of the tunneling projects. Finding encountering adverse geological conditions. The
innovative solutions for quantifying geological key to accelerated implementation of hydropower
economic
uncertainties is a key factor for cost effective and project under such circumstance, therefore, lies in evaluation of
optimum tunneling through Himalayan rock mass. expeditiously managing these adverse occurrences. the project.
Prior knowledge of impending geological In the recent time, development of various
complexities is always helpful in giving pre-emptive advanced investigation techniques and instruments
engineering solutions. Hence, need for adequate aimed towards comprehensive site investigation
engineering geological investigations is necessity in have proved very helpful in minimizing the
order to minimize the risk of encountering unknown occurrence of geological surprises. Besides, there
or unanticipated adverse geological conditions. has been many fold improvement in construction
The geological and geotechnical investigation methodologies and construction equipment as
program, which is planned in four stages viz., Pre- well as modern construction chemicals, etc. that
feasibility stage(PFR), Feasibility stage(FR), Detailed are suitable for effectively tackling the adverse
Project Report (DPR) and Construction stage, is geological occurrences during surface and
required be adequately accomplished in order underground construction works and mitigating TBM at work in J&K's
to provide realistic information for economic and the detrimental issues, thereby boosting the level Kishaganga hydro
safe design and construction of the underground of confidence in project execution. project.
structures. The extent of work to be undertaken
at FR and DPR stages generally depend on the
complexity of geological conditions at project
sites. Sometimes the critical factors /problems are
missed in pre-construction phase and they only
come to light during construction stage, these lead
to extensive delays and cost overruns. Sometimes
these adverse geological conditions continue to
remain unsolved even during operation phase
making situation highly risky.
The experience of huge cost and time
overruns has resulted in the concept of ‘Bankable
DPR’ supported with adequate geological /
geotechnical investigations. DPR is expected
to provide a roadmap of the project so that the
project can be assessed techno-economically
and constructed with minimum time and cost
overruns. A bankable DPR is a document which
can give enough confidence to the lending agencies
that each component of the proposed project
has been adequately explored in such a way that

July 2020 | CONSTRUCTION TIMES | 65


special Tunnelling

Concluding Points
- Importance of investigation of the
geological conditions; how much to
investigate
- Risk sharing by developer vis a vis
contractor
- Adopting latest execution techniques
in difficult ground like ground freezing,
5 P method of excavation, DRESS
methodology, pre-grouting
- Adopting latest supporting techniques
- Adopting latest construction equipment
- latest construction chemicals
- Modifying designs as per the Himalayas
geology
- Adopting various latest methods of
ventilation in tunnels
- Shortage of skilled manpower and skill
Teesta Stage. Recommendations development at various stages
The construction of hydropower projects, - Respecting dispute resolution mechanism
particularly in Himalayan settings, requires - To avoid delays in struck projects,
thorough investigations of geological and quick decision making to be inculcated-
respective ministry to make strict rules-
geotechnical features. The objective of geological
approved panel of third party consisting
/geotechnical investigations is to get the basic data
of experienced engineers may be created
for the economic, safe design and construction of
- NATM to be implemented in right
surface and underground structures.
earnest based on Himalayan geology.
The aim should be to obtain as complete
- Future tunnels to be planned with
information of the subsurface geological conditions
using tunnel boring machines (TBMs)
to arrive at a techno-economic evaluation of the
depending on applicability in various
project.
regions.
Appropriate investigations during the initial
- Adoption of long term use of
planning stage may ultimately lead to a most
Instrumentation for monitoring stress and
economic design of the structures.
deformity after commissioning of projects
Geological mapping, subsurface exploration - Provisions of geological baseline report in
and rock mechanical (in-situ / lab) investigations are the bidding process
helpful in freezing the alignment of tunnels, sitting of
Appropriate underground structures and fixing of dam alignment
- Importance of geophysical investigations
by advance methods.
investigations etc to ensure stability and safety of dams and as well
during the as other surface and underground structures.
initial planning At times, situation might demand further Besides, the investigations would also to be
stage may investigations, therefore, time and quantum of site value addition for mechanized tunneling equipment
investigation should commensurate with the size like tunnel boring machine (TBM), to be used as an
ultimately and complexity of the project. alternative to the conventional drill-blast method
lead to a most The investigations are needed to be carried out (DBM).
economic in four stages: Pre-feasibility stage (PFR), Feasibility Each underground project is unique and
design of the stage (FR), Detailed Project Report (DPR) and vast uncertainty / risk exists in these projects.
structures. Construction stage. Results of each stage should The program of geological and geotechnical
be carefully reviewed and a conscious decision investigations should be framed to collect,
taken for the scope of work in the next stage. generate and analyze engineering geological and
The ultimate goal should be to determine, rock mechanics data for site characterization, in
with reasonable accuracy, the subsurface rock different stages of investigation and also to identify
mass condition both for surface and underground potential geo-hazards that may exist at project
works: sites.
During underground excavation rock mass The investigation program should effectively
behavior around the opening or tunnel/cavern cater to all stages of the sites evaluation process.
undergoes significant changes which results into Based on comprehensive investigations of the
deformation or displacement and it is important to various project components using advanced
understand how it will react to or behave during tools and techniques a Bankable DPR should
underground excavation. be prepared, deliberating possible problems

66 | CONSTRUCTION TIMES | July 2020


special Tunnelling

associated with various project components.


Investigations need not cease when construction
or execution has started.
Inadequate engineering geological investigation
can substantially increase the risk of encountering
unexpected adverse conditions that can seriously
delay or even stop construction with costly
consequences.
One of the difficult and intricate aspects of any
geological/geotechnical investigation is deciding
how much exploration to do. The amount of
exploration to be done on any given project site
should be determined by experience / budgetary
provision. It must also be known that how detailed
may be one exploration / investigation program for
surface and underground works in particular, it is Besides application of standard investigation
not that all problem areas can be duly predicted. techniques, possible solution lies in systematic
Hence, there is a possibility of encountering advance probing during construction: As the
adverse geological occurrences in the form of Himalayan geology in tunnels changes frequently,
geological uncertainties, during construction stage therefore, whatever amount of exploration is
which obviously involve physical and financial risks. done on ground cannot predict exactly the type
In view of the above, it should be a practice of strata that will be encountered. Therefore
to establish a base line of geological/geotechnical investigation ahead of tunnel face should become
data and prepare a ‘Geotechnical Baseline Report’ a part of excavation cycle in the form of probe
(GBR) for defining and allocating the risk and drilling and underground geophysical study, etc. in
associated cost, which may be shared with the order to get the geological foreknowledge of what
EPC contractor. In this way the executing agency lies ahead of tunnel face.
will have adequate resources and expertise in Preparedness at project site should always
handling such adverse conditions timely, as prompt be in the form of readiness in dealing with the
decision making by the implementing agency is the worst condition by keeping alternate equipment
essence of the matter. This risk sharing mechanism
Inadequate
and material at the work location. Continuous
also optimizes the cost as the contractor knows geological monitoring and inputs from expert
engineering
well in advance the risk and its sharing mechanism. committees important in facilitating the designer to geological
For efficient execution of the project, attention go in for mid-way correction in the designs, in investigation
is required to be given towards utilization of state- case essentially required. Prompt decision making can substantially
of-the-art investigation instruments & techniques. by the implementing agency is vital in managing increase the risk
With the recent technological advance, the practice adverse geological occurrences. of encountering
of investigation has undergone radical changes. For It is important to understand that in
comprehensive site investigation and successful
unexpected
hydroelectric project investigation, applications of
construction of surface and underground structures various techniques at sites for surface structures and
adverse
in complex geological situations and in dealing underground works would primarily be governed conditions
with the challenging issues, critical attention must by the necessity as well as the adequacy of that can
therefore be given towards prospective usage of information needed and selecting the appropriate seriously delay
advanced tools and techniques: tools and techniques according. or even stop
Adoption of suitable modern construction As each project is unique and the geological construction
equipment and methodologies would unravel issues are diverse, it is challenging task to
the geological complexities and adversities well execute in geologically complex conditions:
with costly
in advance: Now-a-days, with the availability of The geotechnical applications cannot be
consequences.
efficient construction techniques, equipment and generalized and implemented, as a routine, at
modern chemicals, etc. it has become possible sites for similar civil structures and it is prudent
to advantageously work through the adverse that utilization of state-of-the-art techniques
geological conditions. and instruments should in consideration of the
While other subsurface structures like surge relevance, applicability as well as the stage of
shafts, desilting chambers and powerhouse caverns the project development. Also, in the project
are constructed in limited spaces with lesser construction stage, during execution of surface
variations in ground conditions, the long tunnels and underground works, the efficiency of project
encounter frequently changing ground conditions execution can be greatly enhanced by the judicious
and face serious constraints in investigations due adoption of pragmatic approach, involving suitable
to inaccessibility and high superincumbent cover advanced methodologies and appropriate
that pose constraints in dependable estimations. construction equipment.

July 2020 | CONSTRUCTION TIMES | 67

You might also like