Professional Documents
Culture Documents
Key aspects of a DN4000 steel pipe jacking project in China: A case study of T
a water pipeline in the Shanghai Huangpu River
⁎
Jianfeng Wang , Kang Wang, Tao Zhang, Shuai Wang
Shanghai Road and Bridge (Group) Co., Ltd., Shanghai 200433, PR China
A R T I C L E I N F O A B S T R A C T
Keywords: Pipe Jacking is one of the most popular method to construct new pipelines below the ground surface in the area
Pipe jacking of oil & gas, water supply, sewage, communication and electricity pipelines, and pipe-roof projects. The common
DN4000 jacked pipes are concrete pipes, steel pipes, glass Fiber Reinforced plastic Mortar Pipes (FRMP), cast ductile iron
Bentonite slurry pipes and clay pipes. The key technologies involved includes but not limited to: selection of the jacking machine,
Trajectory
jacking force prediction and reduction, trajectory deviation control and corrosion protection. Moreover, the key
Corrosion
technologies may changes from one jacking project to another one, as the geological conditions and the size of
the jacking projects changes. These key aspects are crucial importance especially for the large diameter pipe
jacking, because out of control of theses aspects will remarkably increase of the failure risks. In this paper, these
key aspects were introduced and discussed based on the largest diameter steel pipe jacking project, called C3
pipe jacking project. This projects involved nine sections of a DN4000 mm and totally 5221 m jacking length in
soft soil strata. The largest single jacking length between two shafts is 970 m. An earth-pressure-balance pipe-
jacking machine (EPB) with a large spoke-type cutter face was employed to excavate the soil. A highly viscous
bentonite slurry mixed with polymer was used to reduce the friction resistance. Close control of the pipe welding
and use of corrosion protection technology has ensured the efficiency and quality of the project.
⁎
Corresponding author.
E-mail address: wjf7907@126.com (J. Wang).
https://doi.org/10.1016/j.tust.2017.12.012
Received 15 July 2017; Received in revised form 26 October 2017; Accepted 13 December 2017
Available online 19 December 2017
0886-7798/ © 2017 Published by Elsevier Ltd.
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
and Minfeng. The project starts from a shaft in the pump station of Jinze Zhongxin river and including obstacles such as high-voltage towers and
Reservoir, and terminates at the Minfeng water point. The water communication lines. The range of single jacking distances is between
transmission line is constructed using steel pipes with 4 m or 3.6 m 600 and 1000 m. Some wells, especially JB07 and JB08, are in a con-
inner diameter, and pipe jacked segments are connected using 70 fined aquifer, so sudden water ingress or other conditions were of
working shafts. As steel pipe has a good sealing performance, a high concern. Because of the long construction distance as well as the large
inner pressure capacity and little impact on the environment, it is diameter steel pipe, which lead to the lubrication mud difficult to
widely applied in urban drainage pipe construction (Chen, 2012). The surround the pipes entirely and the pipe-soil friction resistance in-
project is being used to transport 3.51 million cubic meters of water crease. Additionally, the large diameter steel pipes with high stiffness
every day (m3/d) through the 42 km transmission line. The success of are hard to adjust trajectory and need more stoppage time to welding.
this project will improve the ability to face a sudden water pollution So it is more difficult to control jacking force, trajectory and improve
incident, will enhance the safety of the raw water supply and promote jacking efficiency, etc. than in typical smaller diameter and shorter
the economic, social and environmental development of Shanghai. jacking distance projects. This paper focuses on those problems and
This paper focus on the C3 section of the project which runs from difficulties.
the JB03 shaft in Qingpu to the JB12 shaft in the Songjiang pump
station with a length of 5220.95 m, including 8 working shafts and 9 2.2. Geological conditions
jacking sections (Fig. 1, Table 1). The steel pipes used in the C3 section
are constructed with 4 m inner diameter and two different wall thick- The strata of the C3 section consist of artificial fill, silty soil, mucky
ness (40 mm and 38 mm). Such kind of large diameter and length steel soil, clay and sandy soil, as shown in Table 2 and Fig. 2. Fig. 2 shows the
pipe jacking project is firstly constructed in China with no construction strata condition of the JB06-JB07 jacking section which is noteworthy
precedent. because it has the longest jacking length and deepest depth of pipe. The
The C3 section crosses various types of terrain, including woodland, pipe jacking passes through mucky silty clay, silty clay and sandy soil at
fishponds, river channels and sluices. The geomorphic type along the
project line is a limnetic plain and slightly undulating. The surrounding Table 2
environment of the project is relatively complicated requiring jacking Summary of soil properties.
through areas containing multiple important watercourses and ports
such as Nandagang, Huanqiao port, Dongtang port, Qingsong port and Layer Soil Ps of CPT Density Cohesion Internal
(MPa) (kN/m3) (kPa) friction angle
(°)
Table 1
Information of all jacking periods of C3 section. ②1 Silty clay 0.70 18.5 19 20.5
②3 Silty clay 1.35 18.7 6 30.5
Jacking period Diameter-wall Pipe length Buried depth of pipe ③1 Mucky 0.41 17.6 13 18.0
thickness (mm) (m) center (m) silty clay
③1-inter Sandy silt 4.56 18.4 7 29.5
JB04~JB03 DN4000-38 253.05 −7.50 to −7.50 ③3 Clay 0.51 17.6 14 16.5
JB04~JB05 DN4000-38 289.06 −7.50 to −7.50 ⑥1-1 Silty clay 2.22 19.4 33 19.0
JB06~JB05 DN4000-38 763.30 −9.00 to −7.50 ⑥1-2 Silty clay 1.38 18.9 29 19.0
JB07~JB06 DN4000-40 969.94 −12.50 to −9.00 ⑥2-1 Sandy silt 3.41 18.7 5 31.0
JB08~JB07 DN4000-40 926.02 −12.50 to −12.50 ⑥2-2 Sandy silt 5.96 19.0 5 32.0
JB08~JB09 DN4000-40 637.61 −12.50 to −8.00 ⑥3 Silty 0.96 18.4 19 19.5
JB09~JB10 DN4000-38 247.60 −8.00 to −8.00 clayey soil
JB11~JB10 DN4000-38 689.30 −9.00 to −8.00 ⑥3-inter Sandy silt 3.18 18.5 26 31.0
JB11~JB12 DN4000-38 433.84 −9.00 to −9.00 ⑥4-1 Silty clay 2.22 19.6 40 19.5
Total 5220.95
CPT: Cone penetration test. Ps: specific penetration resistance.
324
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
the elevation between −7.5 and −12.5 m. The mucky silty clay has employed in this project was designed by the Shanghai Road Bridge
uneven soil quality and rheological thixotropy properties with a Group with the Yangzhou Guangxin Heavy Industrial Equipment Co.
thickness of 0.4–19.10 m. These engineering properties are poor for the Ltd fabricating and assembling the machine. The machine has following
pipe jacking, which will increase the risk of the project. The silty clay particular characteristics:
and the sandy silt are compatible with the pipe jacking with a thickness
of 0.6–8.00 m and 0.6–13.8 m, respectively. (1) The cutter face of the machine is of the spoke type. When jacking,
the earth pressure in the soil bin equals the earth pressure of the
excavating surface. It is different to that for a normal EPB for which
2.3. Hydrogeologic condition
there exists Δp between the earth pressure in the soil bin and the
excavating surface.
Underground water that is closely related to engineering construc-
(2) The soil cut by the machine is transported into a stirring tank by the
tion in Shanghai includes phreatic water, micro confined water and
screw conveyor. After they are mixed with water and stirred, it is
confined water in quaternary deposits. The phreatic water occurs in
transported to a surface precipitation tank through a pipe. After
shallow strata with a burial depth of 0.3–1.5 m. The micro confined
precipitating the solid material, the clear water goes to a recycling
water is found in silty soil and sandy soil which are located in the lower
tank for reuse. The sludge pipe and water delivery pipe both are
part of Holocene deposits, appearing in a discontinuous distribution
steel pipes with a diameter of 15 cm.
and partly connecting with the confined water. The burial depth of the
(3) This kind of machine has a wide application. The large spoke cutter
micro confined water is 3–11 m, and changes periodically with the
face cuts the soil mass in a full section, so that there will be only a
tides. The confined water is located in silty soil and sandy soil in the
very slight influence made on the surrounding area during jacking
upper Pleistocene deposits with a burial depth of 3–12 m. The water
and the surface settlement will be small after construction. It is
level of the confined water also changes periodically. The project is
especially applicable to a project that passes through river beds and
close to the Taimao river and Mao river where the river level varies
close to some important structures with high protection require-
with the tides. Because the shallow soil strata consist of clayey silt,
ments.
laminated clay soil, sandy silt and laminated sandy silt, which have
strong permeability, it is necessary to pay attention to the potential for
The main design parameters are listed in Table 3.
a hydraulic connection between the aquifer and the river.
325
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
Table 3
Design parameters of EPB jacking machine.
326
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
327
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
Table 7 silt. From Tables 5 and 7, it can be seen that the bentonite mud’s
The proportion and the technology parameters of the polymer bentonite mud. fluid loss is bigger than that for the polymer bentonite mud and the
⑥3 layer expansion coefficient is bigger than for the other soils, so
Proportion Bentonite Soda ash Polymer Water
materials when it absorbs water from the thixotropic mud, its volume will
350 kg 5 kg 1.2 kg 780 kg increase and grip the pipeline, making the jacking force larger. But
when the polymer bentonite mud is used, there is no such problem.
Technology parameters Funnel Water loss/ml Specific
(2) When the bentonite mud’s filtration rate is higher, it’s difficult to
viscosity gravity
0″ 10 1.4 form a slurry jacket outside the pipeline and hence the frequency of
grouting needs to be enhanced, leading to an increase in grouting
quantity. In contrast, there is no loss when using the polymer
4.3.3. Application comparison bentonite mud, so the grouting quantity is lower. The application
By analyzing the comparative applications of bentonite mud and contrast of dosage and frequency is shown in Table 8.
polymer bentonite mud, we draw the following conclusions: (3) By monitoring, and in reference to Fig. 4 showing the grouting hole
arrangement, we found that there is no slurry injected at the valves
(1) In the section JB06-JB05, the lower portion of the pipeline cross- of 1o 'clock and 11o 'clock, the slurry pressure is bigger at the 5 o
section is in ⑥3 layer, the upper part of the pipeline is in ⑥2-1 sandy 'clock and 7 o 'clock, causing the slurry flows to the bottom of pipe
328
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
329
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
Usually, the connection type for steel pipe jacking is an “F” type
socket joint or weld connection. The former is typically used in curved
pipe jacking and non-pressure pipe, while, the latter is used for straight
line jacking and pressure pipe. As both a straight line jacking and
pressure pipe, the welded joint connection was selected. The welding of
40 mm steel plate is difficult and it is critical that the weld joint should
keep the necessary strength and tightness. For the practical construc-
tion progress, the welding efficiency controls the speed of the whole
jacking procedure (Yang, 2012) and the long time required for the
welding means a pause in jacking and a remarkable increase of the
(b) Horizontal deflection jacking force. So, in order to make sure of the welding quality and di-
minish the welding time, a novel welding method and procedure were
Fig. 10. Laser deflection in JB06∼JB07 section. adopted, as shown in Fig. 11.
Firstly, the steel pipe barrel was divided into the upper semicircle
joints, the entire pipeline stiffness is very large and any small deviation and the lower semicircle. Then, the two sections of the pipe end were
of the steel pipe jacking axis generates a large bending moment and each grooved into a “V” shape with a 40° inclination angle. Considering
high stress in the steel tube. When the stress is too high, pipe failures the convenience of the welding operation, the upper groove is in the
can occur. The Yanqiao branch line and the Nanhui feeder were both outside of the pipe, and the lower groove is in the inside. The welders
exposed to pipe explosion accidents. could work inside or outside with a comfortable body position.
In this project, the guidance was carefully controlled using the Moreover, the groove was welded one layer by one layer, and totally,
eight layers were used for the complete weld. The widths of the welding
330
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
layers are 7–58 mm. Before the welding of the first layer, a ceramic
sheet was lain under the weld. Stages of the welding progress are shown
in Fig. 12.
Table 10 (1) A knife was used to score two parallel lines (at 10 mm interval) on
Ratio of anti-corrosion coatings.
the coating along the axis, and to score another two parallel lines
Temperature conditions Preservative: Curing agent with the same interval but obliquely crossing the former at a 30°
angle. It was required that the coating under the parallel lines
The normal temperature 3:1 should be absolutely separated. The knifepoint was placed at the
The high temperature 4.5:1
corner of the scored parallelogram, and pushed horizontally.
331
J. Wang et al. Tunnelling and Underground Space Technology 72 (2018) 323–332
Examining the damage of the coating, a flakiness fracture was not grouting amount mean that the overall cost difference is not large
allowed or else the coating should be recoated. If the coating was and hence was considered the preferred lubrication slurry for this
damaged as a plastic flow with only a small amount of powder project.
produced, the coating was deemed to match the requirements. (4) Through taking manual measurements combined with the laser
(2) The naked eye was used to inspect the outside of the coating. An guided detection, and making timely rectifications, the pipe jacking
acceptable product should be level, smooth, and with no sag. axis deviation was always kept within 15 cm.
(3) A coating thickness detector was used to check the upper, lower, (5) The “yuanyang groove form”, namely outside and inside pipe “V”s
left and right locations of the weld. An acceptable product should over the upper and lower 180° respectively of the pipe cir-
be no less than 0.6 mm in thickness. cumference was used to speed construction and make the welding
(4) An electric spark apparatus was used to test the coating on the weld of the pipe joints more convenient for this thick wall, large diameter
with 5 V/μm direct current. An acceptable product should exhibit steel pipe.
no electric spark.
References
7. Summary and conclusions
Cai, Z.Y., Dong, C.M., Wang, X.Y., Li, H.A., Yang, W.J., 2010. Case study on shield type
In this case study of a large-diameter steel pipe jacking project, selection Chaohe tunnel on central route of South-to-north Water Transfer Project.
Tunnel Constr. 30 (1), 91–96 (in Chinese).
analysis has been made of the construction related technical measures Chen, N., 2012. Mechanical characteristics of steel pipe-jacking with large diameter in
used on the project. The C3 section of the overall pipe project involved complex environment. MS dissertation. Shanghai Jiao Tong University (in Chinese).
the installation of a steel jacking pipe for water transmission with an Ding, W.Q., Yuan, S.L., Gao, X.Q., Xie, D.W., 2010. Research on construction disturbance
characteristics caused by super large diameter pipe jacking in electric power tunnel.
outside diameter of 4080 mm over a total distance of 5.2 km. In this Rock Soil Mech. 31 (9), 2901–2906 (in Chinese).
paper the selection of the appropriate machine excavation type and Gu, L.J., 2012. Construction risk and control of long-distance large-diameter steel pipe
cutter were described in conjunction with the assessed soil profiles jacking. Urban Roads Bridges & Flood Control. (06), 263–267+21 (in Chinese).
Huang, J.L., Feng, C.X., 2003. Development and application pipe jacking machine in
expected. Two sub-sections of the project were analyzed in more detail China. Trenchless Technol. 20 (4–5), 94–97 (in Chinese).
to study the measured relationships among various site and construc- Kunming Caohai of Dianchi lake pipe jacking project fills the technology gaps in China,
tion parameters. In addition, the measures to speed the steel pipe 2014. Tunnel Constr. (10), 966.
Liu, J.G., Guo, X.H., 2009. Study on the selection of super-large-diameter shield for an
welding and to enhance corrosion protection have been briefly de-
undersea tunnle. Mod. Tunnel. Technol. 46 (1), 51–56 (in Chinese).
scribed. Smith, T.M., Bousquet, G., Trembath, R.J., Wang, Y., 2001. Large Diameter Steel Pipe
From an analysis of the measured pipe jacking and lubrication Design in Liquefiable Soils. In: Pipelines 2001: Advances in Pipelines Engineering and
grouting data, the following conclusions are made: Construction, pp. 1–10.
Shen, X., Lu, M., Fernando, S., 2012. Automation system design and lab testing to facil-
itate tunnel boring machine guidance in construction of large-diameter drainage
(1) The soil conditions surrounding the pipe were shown to affect the tunnels. In: Construction Research Congress 2012: Construction Challenges in a Flat
friction resistance for both types of lubrication mud tested with the World, pp. 110–120.
Shirk, J.D., 2016. Large-Diameter Tunnel Challenges during the Integrated Pipeline (IPL)
largest increases noted for a swelling soil and using the bentonite Project. In: Pipelines 2016, pp. 904–912.
mud slurry. An increase in the lubrication grouting volumes was Trebicki, D.D., Webb, M.C., Smulders, P.A., 2002. Comparison of unstiffened and ring
seen to reduce the friction resistance. stiffened large diameter flexible steel pipe response to handling, transportation,
backfilling and traffic loads. In: Pipelines 2002: Beneath Our Feet: Challenges and
(2) Over comparable sections, the use of conventional lubrication mud Solutions, pp. 1–40.
for the jacking resulted in an average friction resistance of Yang, J.H., 2012. Large water supply pipe line construction key points and management.
1.16–1.62 kPa. When a polymer-mud combination was used, the MS dissertation. Zhejiang University of Technology (in Chinese).
Zhang, L., 2006. An improvement on resistance reduction technique by injection grouting
average friction resistance was from 0.72 to 0.93 kPa, and the lu- for steel pipe jacking in large diameter. Municipal Eng. Technol. 24 (2), 110–112 (in
brication effect is thus much better the conventional mud under Chinese).
these conditions. Zhong, X.Q., Zhou, Z.Q., Li, D.H., 2011. Key measures for large diameter steel pipe
jacking engineering in Xijiang water diversion project and their practical effects.
(3) The conventional mud fluid loss is larger than for the polymer-mud
Water Wastewater Eng. 37 (02), 93–96 (in Chinese).
fluid and the frequency of supplying slurry and the grouting volume Zhou, H.L., Wang, Q., Tao, X.Y., Geng, W.F., Xu, G.J., Li, M., Lu, D.Y., Li, G.P., Chen, G.,
also are larger; the polymer-mud because of its good performance 2014. EPC practice and innovation in Shanghai Hongqiao “Energy Heart” south and
characteristics showed little fluid loss and lower grouting volumes. north station construction connected by 4280mm large diameter steel pipe-Jacking.
Build. Constr. 10, 1182–1184 (in Chinese).
Although the polymer-mud cost is higher, the differences in
332