Professional Documents
Culture Documents
com
ScienceDirect
Underground Space 6 (2021) 101–125
http://www.keaipublishing.com/en/journals/underground-space/
Received 20 June 2019; received in revised form 8 August 2019; accepted 23 August 2019
Available online 27 November 2019
Abstract
Rectangular pipe jacking or box jacking has become more popular in municipal applications because of its better adaptability to
shallow overburdens and its higher structural section utilization than the conventional circular pipe jacking. This case study presents
a utility tunnel constructed by using rectangular box jacking in Suzhou, China. The utility tunnel, which has a cross section of 9.1 m
in width and 5.5 m in height, was jacked 233.6 m, which is the longest known single jacking length of a rectangular box jacking project
in China. The box jacking mainly passed through a silty sand layer with high groundwater levels with a minimum depth of cover of only
3.5 m underneath the Yuanhetang River. In this zone, the structures on the surface are sensitive to external disturbance, thus increasing
the challenges of construction. A series of measures were taken during the jacking process, and the project was successfully completed.
This paper provides an overview of this project and introduces key techniques in the construction of working shafts as well as in the
installation and retrieval of the box jacking machine. In addition, the use of lubrication to reduce friction resistance, navigation and
application of an anti-buoyancy slab under the Yuanhetang River, and analyses of soil deformation caused by box jacking are described.
Keywords: Utility tunnel; Rectangular box jacking; Lubrication and friction resistance reduction technology; Anti-buoyancy slab; Ground deformation
https://doi.org/10.1016/j.undsp.2019.08.003
2467-9674/Ó 2019 Tongji University. Publishing services by Elsevier B.V. on behalf of KeAi Communications Co. Ltd.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
102 X.L. Chen et al. / Underground Space 6 (2021) 101–125
determined the upper and lower bound of the jacking force and to provide reference for further rectangular box jack-
of a shallow rectangular box jacking project to ensure the ing projects.
stability of the excavation face by assuming two failure
mechanisms respectively for collapse failure and blow-out 2 Project description
failure. On the basis of a rectangular box jacking project
traversing two existing metro tunnels, Zhang et al. (2016) 2.1 Site overview
analyzed the ground surface settlement and the metro tun-
nel deformation during the construction by performing As stated earlier, the utility tunnel constructed by using
three-dimensional numerical simulation and on-site moni- rectangular box jacking has a cross section size of 9.1 m in
toring. Sun, Wu, Sun, Li, and Shao (2018) investigated width and 5.5 m in height, and a total length of 233.6 m;
the field performances and geo-environmental impacts by the average depth of cover is approximately 9 m. The con-
analyzing the field monitoring data in a case study of two struction site was located near the intersection of Cheng-
parallel tunnels constructed by using rectangular box jack- beidong Road and Qimen interchange in Suzhou, China.
ing. The above studies enable us to have a certain under- There were the Qimen interchange, gas stations, residential
standing of rectangular box jacking, including the control buildings, and commercial buildings along the alignment of
of construction parameters and its impact on the environ- the tunnel, as it passed beneath the Yuanhetang River
ment; however, they lack a summary of the key techniques when it was just a short distance from the receiving shaft.
of the rectangular box jacking construction. Owing to the The plan layout of the project is illustrated in Fig. 1. Fig-
lack of relevant specifications, the rectangular box jacking ure 2 depicts the relative position between the utility tunnel
project mainly refers to the construction experience of cir- and the pier foundation of the Qimen interchange. It can be
cular pipe jacking, which has many shortcomings and may seen that the horizontal distance between the utility tunnel
cause problems in the field. Therefore, development of and the pile cap is only 0.6 m, and the horizontal distance
specifications and presentation of key construction tech- from the utility tunnel to the nearest pile is only 1.1 m. The
niques of rectangular box jacking are needed. box jacking machine attitude, jacking speed, and jacking
The utility tunnel near Chengbeidong Road in Suzhou axis needed to be strictly controlled during the construc-
was constructed by using rectangular box jacking; its cross tion. When the tunnel crossed underneath the Yuanhetang
section has a width of 9.1 m and a height of 5.5 m. The tun- River, the distance from the riverbed to the tunnel vault
nel was jacked 233.6 m, which is the longest known rectan- was only 3.5 m, which could lead to the risk of leakage
gular box jacking project in China. It passed through of the box jacking machine and box joints. Moreover, there
complex strata with high groundwater with the possibility was a possibility of uneven settlement on the riverbanks
that the boxes may float or sink unevenly during crossing during the construction.
underneath the Yuanhetang River. In addition, surface
structures, which are sensitive to external disturbance, 2.2 Soil characteristics
increased the challenges of the construction. A series of
measures were taken to ensure the successful completion The geological section of the box jacking zone is
of the project with good results. This paper introduces depicted in Fig. 3. Through soil borings, various soils were
key techniques such as the construction of working shafts, discovered, including plain fill ①-5, clay ④, silty clay with
launch and reception of the box jacking machine, long- silt ⑤, silty sand with silt ⑥-1, silty sand ⑥-2, silty clay ⑦,
distance grouting and friction resistance reduction technol- clay ⑧, and silty clay with silt ⑨-1; miscellaneous fill ①-3
ogy, trajectory control and application of an anti-buoyancy was also found in some areas, and the riverbed of Yuan-
slab under the river, and deformation monitoring. The hetang was deposited with muck ①-1. The groundwater
objectives are to form a complete set of technical schemes level ranged from an elevation of 1.51–1.58 m; the water
Table 1
List of several rectangular box jacking projects in China.
Year Project Cross section (m m) Length of jacking (m) Box jacking machine
1999 Subway pedestrian passage (Shanghai) 3.8 3.8 62.25 Earth pressure balance
2004 Underpass beneath the road (Shanghai) 7.85 3.42 130 Earth pressure balance
2006 Subway pedestrian passage (Shanghai) 6.24 4.36 42.7 Earth pressure balance
2008 Underpass beneath the railway (Suzhou) 9.1 7.4 37 Earth pressure balance
2009 Subway pedestrian passage (Shanghai) 64 23 Earth pressure balance
2010 Subway pedestrian passage (Shanghai) 6.9 4.2 49.1 Earth pressure balance
2012 Passage over street (Foshan) 6.0 4.3 43.5 Slurry balance
2012 Subway pedestrian passage (Wuhan) 64 62.4 Earth pressure balance
2013 Underpass beneath the road (Zhengzhou) 10.4 7.5 110 Earth pressure balance
2016 Utility tunnel (Baotou) 7 4.3 85.65 Earth pressure balance
2016 Subway pedestrian passage (Shenzhen) 7.7 4.3 133.5 Earth pressure balance
X.L. Chen et al. / Underground Space 6 (2021) 101–125 103
3 Key techniques
Table 2
Physical and mechanical parameters of the soil.
Layer x q e a1-2 c u kh kv
(%) (g/cm3) (MPa 1) (kPa) (°) (cm/s) (cm/s)
①-5 30.4 1.92 0.865 0.33 27.9 16.8 4.4 10–6 3.2 10 6
⑥-1 30.2 1.91 0.836 0.20 4.6 31.4 2.9 10–3 1.6 10 3
⑥-2 28.9 1.94 0.789 0.19 3.8 33.4 3.8 10–3 2.1 10 3
⑨-1 27.4 1.97 0.765 0.26 31.5 17.4 5.1 10–6 3.8 10 6
Notes: x is the natural moisture content, q is the natural density, e is the void ratio, a1-2 is the coefficient of compressibility, c is the cohesion, u is the
internal fiction angle, k is the horizontal permeability coefficient, and kv is the vertical permeability coefficient.
curtain would lose efficiency during the excavation of 3.2 Selection of the box jacking machine
shafts. Therefore, high-pressure jet grouting piles with a
diameter of 800 mm and a center-to-center distance of It is critical to select a suitable box jacking machine
400 mm were used between the waterproof curtain and based on the engineering properties (e.g., site conditions,
the drilling piles as well as inside the drilling piles. formation property, and groundwater level). Referring to
To prevent soil deformation caused by the box jacking, the aforementioned cases of rectangular box jacking, we
we used triaxial mixing piles with a diameter of 800 mm used two common types of rectangular box jacking
and a center-to-center distance of 650 mm to reinforce machine, namely, a slurry balance pipe jacking machine
the backrest soil; the reinforced area was approximately and an earth pressure one. However, the earth pressure bal-
348 m2, and the soil of the exit opening was also reinforced ance pipe jacking machine was selected in the vast majority
by the same triaxial piles with a reinforced area of approx- of cases.
imately 68 m2. The bottom of the launching shaft was rein- During the construction of the earth pressure balance
forced with a thickness of 5 m; high-pressure jet grouting pipe jacking, the treatment of the soil is simple and conve-
piles as referred to above were also applied between the nient. It does not need to occupy excessive ground space
foundation and the drilling piles. As shown in Fig. 5, an compared with the separation device of sludge water used
internal bracing system consisting of one reinforced con- in the construction of the slurry balance pipe jacking. What
crete support and four steel supports was used during the is more, the main type of cutterheads used for the earth
excavation of the shaft. Before the inner walls of 1 m thick- pressure balance pipe jacking machine is the spoke type,
ness were constructed, the steel supports were gradually whose cutter opening rate is high, and, therefore, the earth
removed and the second reinforced concrete support was pressure measured by the earth pressure gauge in the soil
installed at the initial location of the third steel support. chamber is almost equal to that of the excavation face, as
Figure 6 illustrates the field scene of the completed launch- it is convenient to control the earth pressure. Generally,
ing shaft. earth pressure balance construction also has the advan-
The receiving shaft was constructed with a length of tages of high speed and low cost. Most important of all,
14.1 m, a width of 10 m, and a depth of 16.72 m; the retain- the overburden can be shallow during the construction of
ing structures and supporting method are the same as those the earth pressure balance pipe jacking (Ma, 2008), and,
of the launching shaft, the only difference being the scope therefore, it is more suitable for the pass underneath the
of the construction. Yuanhetang River, where the minimum depth of
X.L. Chen et al. / Underground Space 6 (2021) 101–125 105
overburden is only 3.5 m. Therefore, an earth pressure bal- performance and durability of ordinary concrete). The
ance pipe jacking machine with 9.12 m width and 5.52 m of weight of each box segment was approximately 66.8 t,
height was chosen for the project. and the allowable design value for jacking of the box seg-
As shown in Fig. 7, a combined cutter plate was selected ment was 156 169 kN. The cross section and the side view
to reduce the disturbance to the surrounding soil and to are shown diagrammatically in Fig. 9(a) and (b), respec-
control the ground deformation. There were seven cutter- tively. Two types of grouting holes were reserved in the
heads in total with four different diameters aimed at walls of the box segment. There were 14 grouting holes
increasing the cutting area, including one largest cutter- with inbuilt DN25 (nominal diameter of 25 mm) steel tubes
head with a diameter of 4200 mm, two medium cutterheads per box segment distributed near the spigot joint; they were
with a diameter of 2980 mm, two medium cutterheads with used for injecting the thixotropic slurry. In addition, twelve
a diameter of 2520 mm, and two small cutterheads with a grouting holes with inbuilt DN66 (nominal diameter of
diameter of 1450 mm. These cutterheads were installed 66 mm) steel tubes, which were placed in the middle of
symmetrically about the vertical axis of the box jacking the box segment, were reserved for replacing the slurry at
machine. The total cutting area was 41.082 m2, and the rate the end of the jacking operation. The outer wall of the
of cutting was 82.2%. The box jacking machine was assem- box segment was pre-embedded with eight steel tubes,
bled in the launching shaft. Figure 8 illustrates the struc- whose external diameter was 119 mm and thickness was
tures of the box jacking machine used in the construction. 8 mm. These steel tubes were embedded with every two
on each side for hoisting of the box segment. Figure 10
shows the box segment used in the construction.
3.3 Box structures
In this project, precast reinforced concrete boxes with 3.4 Launch and reception of the large-section box jacking
dimensions of 9.1 m in width, 5.5 m in height, and 1.5 m machine
in length were used. The wall thickness was 650 mm. An
F-shaped bell and a spigot joint fitted with two sealing rub- The smooth launch and reception of the box jacking
ber rings were used for sealing between segments. The machine are very important in a jacking project. When
strength of the concrete was C50 (50 N/mm2), and the the box jacking machine is to be launched or received,
anti-seepage grade was P8 (0.8 MPa, according to the the alignment and slope must be strictly controlled to avoid
GB/T 50082–2009 standard for test methods of long-term excessive deviation. Furthermore, owing to the poor
106 X.L. Chen et al. / Underground Space 6 (2021) 101–125
stability of the silty sand layer and the presence of extensive 3.4.1 Launch of the box jacking machine
groundwater in the construction area, ground deformation 3.4.1.1 Chiseling of the shaft opening. Before the box jack-
caused by soil erosion can easily occur during the launch ing machine is launched or received, it is necessary to chisel
and reception, which threatens the construction safety. the drilling piles in the scope of the shaft opening. Steel
Therefore, taking the corresponding water stop measures bars on the side unexposed to soil should be first chiseled
is critical. until the steel bars on the other side are exposed, and then
X.L. Chen et al. / Underground Space 6 (2021) 101–125 107
Fig. 8. Structures of the box jacking machine used in construction: (a) upper half, (b) bottom half, (c) cutterhead, and (d) assembled machine.
108 X.L. Chen et al. / Underground Space 6 (2021) 101–125
Fig. 9. Schematic diagram of the box segment: (a) diagrammatic cross-section, and (b) diagrammatic side elevation.
Fig. 10. Box segment. Fig. 11. Chiseling of the shaft opening.
Fig. 12. Sealing device of the shaft opening: (a) installation of the rubber water stop, and (b) sealing effect.
Table 3
Parametric test results.
Number x(Na-bentonite) (%) x(CMC) (%) x(NaOH) (%) x(PHP) (%) Viscosity (s) API filtration loss (mL/h)
1 5 0.5 0.5 0.3 36 34
2 5 1.0 1.0 0.6 48 24
3 5 1.5 1.5 0.9 49 26
4 7.5 0.5 1.0 0.9 37 28
5 7.5 1.0 1.5 0.3 50 26
6 7.5 1.5 0.5 0.6 62 20
7 10 0.5 1.5 0.6 68 24
8 10 1.0 0.5 0.9 72 20
9 10 1.5 1.0 0.3 78 16
Notes: The proportion of each material is expressed as a percentage of the total mass of the slurry. The viscosity was measured using the Markov funnel
method.
amount of raw materials is large and the viscosity of the was also installed at the connection between the branch
slurry is too high to pump for a long distance, and, there- pipe and the DN25 grouting hole, to realize positioning
fore, it can only be used in a local district where the amount grouting through the valve switch. A check valve was
of water loss is large. installed on the other end of the DN25 grouting hole to
When the slurry passes through the silty sand layer, its prevent slurry backflow and soil blockage. A schematic
viscosity should be greater than 45 s and the API filtration diagram of the grouting pipelines is shown in Fig. 16.
loss should be less than 30 mL/h. Therefore, for the general Among them, only 10 grouting holes were put into service
district, a mixture ratio of 5% Na-bentonite, 1.0% CMC, during the construction. A field scene of the grouting
1.0% NaOH, and 0.6% PHP was used; the viscosity of pipelines is shown in Fig. 17.
the slurry was 48 s; and the API filtration loss was The box jacking machine and the subsequent four box
24 mL/h. When the slurry passed through a district with segments were simultaneously grouted during the jacking
high water pressure beneath the Yuanhetang River, a spe- process. The box jacking machine was mainly grouted on
cial slurry formula of 7.5% bentonite, 1.5% CMC, 0.5% the upper surface to prevent the soil from moving together
NaOH, and 0.6% PHP was adopted, wherein the propor- with the machine owing to friction resistance; the subse-
tions of Na-bentonite and CMC were correspondingly quent four box segments were fully grouted around the
increased to increase the viscosity and decrease the API fil- box to make the slurry completely fill the gap. The sec-
tration loss. ondary grouting was carried out for every one or two
box segments from the box segment located in the passage
3.5.1.3 Grouting technology in construction. Grouting con- hole to the fifth box segment behind the box jacking
sists of synchronous grouting and secondary grouting. machine. In general, the secondary grouting is only applied
The purpose of the synchronous grouting is to fill the exca- on the upper surface of the box. When the loss of slurry is
vation gap immediately after the box jacking machine serious, the secondary grouting should also be done on the
passes to reduce the instantaneous settlement of soil, and two sides or on the bottom. The grouting parameters
a slurry jacket can be formed gradually to reduce the fric- mainly include the grouting volume and the grouting pres-
tion resistance during the jacking process. The purpose of sure, of which the grouting volume is mainly controlled
the secondary grouting is to further maintain the effect of and the grouting pressure control is supplemented. Consid-
the synchronous grouting, supplement the volume of lost ering that the project mainly passes through a silty sand
slurry owing to leakage or consolidation, and ensure the layer where the slurry is prone to leak and the groundwater
integrity of the slurry jacket. The grouting steps consist is plentiful, the synchronous grouting volume of each seg-
of grouting before jacking, grouting coupled with jacking, ment was set to 4 times of the theoretical grouting volume
and timely replenishing (Yang, Rong, & Xu, 2016). and the secondary grouting volume of each segment was set
Because of the shallow overburden, a screw pump was to 0.3 times of the synchronous grouting volume. The
used for grouting. The screw pump had a strong self- grouting pressure was set from 1.1 to 1.3 times of the for-
suction capacity; there was no pulsation during the grout- mation pressure. The grouting volume and pressure were
ing process, and the grouting pressure was stable (Yang adjusted reasonably according to the data records during
et al., 2016). Grouting included a main pipe and several the construction.
branch pipes, wherein a steel pipe of DN50 (nominal diam-
eter of 50 mm) was adopted for the main pipe and a hose of 3.5.2 Other friction resistance reduction measures
DN25 (nominal diameter of 25 mm) was adopted for the 3.5.2.1 Waxing on the surface of boxes. Figure 18 illustrates
branch pipe. One ball valve was disposed at the joint the waxing and baking on the box surface. A fully refined
between each branch pipe and the main pipe. The ball valve no. 60 paraffin wax with a high melting point was used. The
112 X.L. Chen et al. / Underground Space 6 (2021) 101–125
Fig. 18. Box surface waxing and baking: (a) waxing, and (b) baking.
X.L. Chen et al. / Underground Space 6 (2021) 101–125 113
was used. Except for some sections where the construction 70 m. It shows that the thixotropic slurry can better adapt
was stopped, the friction resistance per unit area was to the formation conditions and form a good slurry jacket
rapidly reduced; it was less than 7 kPa when jacking to around the box to play a lubricating role. After the jacking
X.L. Chen et al. / Underground Space 6 (2021) 101–125 115
Fig. 24. Connection between box jacking machine and box segments. (1) Initial attitude control to ensure the high-precision
launching of the box jacking machine
obtained through real-time measurements. The rectifica- (4) Selection of reasonable corrective measures
tion was performed in time according to the measurement
results. Figure 25 shows the measuring apparatus used in When the box jacking machine was deflected because of
the project. an imbalance in earth pressure, the speed of the double
X.L. Chen et al. / Underground Space 6 (2021) 101–125 117
Fig. 28. Schematic plan of the anti-buoyancy slab and steel pipe pile cofferdams.
helix machine and the volume of the soil conveyed out the top and the bottom side in the soil cabin. When the
from the soil cabin were adjusted to control the pressure box jacking machine was seriously deflected, the co-
difference between the left and the right side or between rotation of several cutterheads was controlled to enable
118 X.L. Chen et al. / Underground Space 6 (2021) 101–125
When the tunnel was jacked beneath the Yuanhetang Fig. 31. Steel pipe pile cofferdam: (a) construction equipment, (b)
River, the minimum depth of overburden was only approx- construction process, and (c) backfilling clay.
imately 3.5 m. Disturbance of the construction may cause
the penetration of the riverbed, resulting in seepage of on the river, we divided the cofferdam construction divided
the machine or box joints. The shallow buried box seg- into two phases. In the first phase, the construction of the
ments may float upward, and there is a hidden danger after steel pipe pile cofferdam was carried out from the west side
being put into use in the later stage. To this end, temporary of the Yuanhetang River to the east side; in the second
steel pipe pile cofferdams were built in the Yuanhetang phase, the construction was carried out from the east side
River and an anti-buoyancy slab was constructed after to the west side. An earth cofferdam was adopted at the
pumping, dredging, and leveling. To minimize the impact junction of the two steel pipe pile cofferdams. Figure 28
X.L. Chen et al. / Underground Space 6 (2021) 101–125 119
illustrates the schematic plan of the anti-buoyancy slab and 9 m, the wall thickness was 7 mm, and the outer diameter
the steel pipe pile cofferdams. was 27.3 cm. The elevation of the pile bottom was
Double-row steel pipe piles were adopted for the steel 5.9 m, and the elevation of the pile top was 3.1 m; the
pipe pile cofferdam with a width of 3 m. The cross- center-to-center distance between the steel pipe piles was
section diagram and schematic plan are shown in Figs. 29 50 cm. To strengthen the rigidity of the steel pipe pile wall,
and 30, respectively. The length of the steel pipe pile was we welded steel pipes with an outer diameter of 15.9 cm
120 X.L. Chen et al. / Underground Space 6 (2021) 101–125
(a) (c)
(b) (d)
Fig. 35. Daily ground deformations of monitoring points on the CJ1 section: (a) x = ±3 m, (b) x = ±7 m, (c) x = ±11 m, and (d) x = ±17 m.
and a wall thickness of 4.5 mm on the outer side of the steel elevation of the cushion was controlled strictly to ensure
pipe piles and pulled the wire ropes between the two rows the flatness of the anti-buoyancy slab, and a sump pit
of the steel pipe piles. On the inner side of the steel pipe pile was set to prevent partial seepage from interfering with
wall, an earthwork cloth was laid on the steel pipe pile the construction.
through the geotechnical grille. After the sludge on the riv- The anti-buoyancy slab achieved good results. During
erbed was removed, the clay was backfilled until above the the process of jacking beneath the Yuanhetang River, there
water level to ensure the water-proof effect of the cofferdam was neither uplifting of the box segments nor seepage of
body. A snapshot of the construction of the steel pipe pile the machine or box joints. After the steel pipe piles were
cofferdam on site is shown in Fig. 31. removed, the holes left were backfilled and grouted in time
The anti-buoyancy slab was constructed with 800-mm- to prevent the displacement and settlement of the sur-
thick reinforced concrete slabs. The construction area is rounding soil.
shown in Fig. 28. The cross-section diagram is shown in
Fig. 32. C20 concrete (strength of 20 N/mm2) and 4 Ground deformation caused by box jacking
HRB400 steel bars (strength of 360 N/mm2) were used in
the construction; the diameter of the steel bars was 4.1 Field monitoring plan
18 mm along the jacking direction and 25 mm along the
traverse direction. Before the construction of the anti- Box jacking will inevitably cause ground deformation;
buoyancy slab, dredging and leveling were first carried excessive deformation will endanger the safety of the struc-
out and then the concrete cushion was constructed. The tures on the surface. Therefore, three ground deformation
X.L. Chen et al. / Underground Space 6 (2021) 101–125 121
Fig. 36. Daily ground deformations of monitoring points at different transverse distances on the CJ1 section.
monitoring sections (CJ1, CJ2, and CJ3 sections), as shown tion conditions, deflection of the box jacking machine,
in Fig. 33, were arranged along the jacking direction. The and differences in grouting volume will cause different
CJ1, CJ2, and CJ3 sections were, respectively, 69.37, ground deformations. It is obvious that the daily defor-
111.35, and 182.9 m away from the launching shaft. As mation of each monitoring point fluctuates repeatedly
shown in Fig. 34, twenty-three monitoring points were between the settlement and the uplift, which is mainly
arranged perpendicular to the jacking direction on the caused by the artificial control of the grouting and the
CJ1 and CJ3 sections. There were only 17 monitoring attitude adjustment. For instance, owing to the stoppage
points on the CJ2 section owing to the space limit. of grouting on November 7, the above eight monitoring
points all showed a large settlement, and then a large
4.2 Monitoring results uplift occurred on November 8 because of the injection
of a large amount of slurry. The effect of grouting on
For convenience, the transverse distance between a the ground deformation in the project with shallow over-
monitoring point and the tunnel medial axis is expressed burden was very noteworthy.
as the letter ‘‘x”, e.g., on the CJ1 section, x = –1 m repre- Figure 36 illustrates the daily ground deformations at
sents the CJ1-1 monitoring point. different monitoring points on the CJ1 section. It has been
concluded from the above analysis that the monitoring
4.2.1 Daily ground deformation points equidistant from the jacking axis are closely affected
In this study, four groups of monitoring points on the by the construction, and, therefore, only the monitoring
CJ1 section, i.e., x = ±3 m, x = ±7 m, x = ±11 m, and points on the right side of the jacking direction are selected
x = ±17 m, were selected to analyze the variation in in Fig. 36. As shown in Fig. 36, deformations of the mon-
daily ground deformation. The two monitoring points itoring points at different distances vary with a similar ten-
of each group were symmetrically distributed on both dency. However, the daily ground deformation at x = 0 m
sides of the jacking axis. The monitoring results are fluctuates most sharply compared with that at another dis-
shown in Fig. 35. It can be seen in the figure that the tance; the deformation shows a gradual decrease as the dis-
monitoring points equidistant from the jacking axis are tance to the jacking axis increases, which indicates that the
closely affected by the construction; the daily ground construction has a greater impact on the monitoring point
deformation is approximately the same, but not com- closer to the axis. When the distance from the monitoring
pletely coincident. Even though the monitoring points point to the jacking axis reaches 17 m, the daily ground
are symmetrically distributed, small differences in forma- deformation is basically within ± 3 mm.
122 X.L. Chen et al. / Underground Space 6 (2021) 101–125
(a)
(b) (c)
Fig. 37. Deformation-time curves of monitoring points at different transverse distances: (a) CJ1, (b) CJ2, and (c) CJ3.
4.2.2 Cumulative ground deformation 2016). When the box jacking machine arrived at the mon-
Figure 37 presents the deformation-time curves of the itoring section, the ground quickly settled and reached a
monitoring points at different transverse distances of the maximum settlement after the box jacking machine had
CJ1 [Fig. 37(a)], CJ2 [Fig. 37(b)], and CJ3 [Fig. 37(c)] sec- completely passed. This may be because the outer dimen-
tions. For any monitoring section, it can be seen in the fig- sions of the box jacking machine were slightly larger than
ure that the trends of cumulative deformations at different those of the subsequent box (the outer dimensions of the
transverse distances are similar and that the closer the box jacking machine were 9.12 m in width, 5.52 m in
monitoring point is to the jacking axis, the greater is the height, while the outer dimensions of the box segment were
influence degree of the jacking process. These characteris- 9.1 m in width 5.5 m in height), and the synchronous grout-
tics are consistent with the characteristics of daily ing could not fill the peripheral gap around the box in a
deformations. short time, which caused the collapse of the upper soil
At the same time, common characteristics can be found and resulted in large surface subsidence. It can be seen in
from different monitoring sections. When the box jacking Fig. 37 that the settlement on the CJ2 and CJ3 sections
machine was at a certain distance from the monitoring sec- was significantly larger than that on the CJ1 section; this
tion, because of the disturbance to the surrounding soil, a was due to the fact that a slurry spillover occurred near the
small amount of settlement occurred at each monitoring CJ2 section, while the amount of grouting was less on the
point. As the box jacking machine approached, additional CJ3 section. After the box jacking machine had completely
stress was generated on the front soil, which caused a cer- passed, a slurry jacket gradually formed and remained intact
tain degree of uplift on the ground. The uplift is beneficial through the secondary grouting. The ground settlement on
for reducing the final surface settlement (Zhang et al., the CJ1 and CJ2 sections was alleviated to a certain extent;
X.L. Chen et al. / Underground Space 6 (2021) 101–125 123
(a) (b)
(c)
Fig. 38. Settlement trench on the monitoring section: (a) CJ1, (b) CJ2, and (c) CJ3.
however, there was a subsequent settlement on the CJ3 sec- process, a slurry spillover occurred near the CJ2-1 point,
tion due to the small grouting volume; the maximum ground and, therefore, the maximum settlement appeared at the
settlement exceeded 70 mm. CJ2-1 point, followed by a lack of subsequent monitoring
values, and the surface settlement on the CJ2 section was
4.2.3 Settlement trench larger than that on the CJ1 section. For the CJ3 section,
Figure 38 shows deformations of the monitoring points owing to the relatively small amount of grouting, the settle-
at different times on the CJ1 [Fig. 38(a)], CJ2 [Fig. 38(b)], ment was larger than that on the CJ1 and CJ2 sections.
and CJ3 [Fig. 38(c)] sections, wherein the transverse dis- After the box jacking machine passed completely on Octo-
tance on the horizontal labels represents the relative dis- ber 24, 2017, the surface settlement continued to increase.
tance between the monitoring point and the jacking axis. Moreover, the settlement curve showed an obvious form
Overall, the ground deformation curves on the three sec- of ‘‘W”, which was due to the amount of grouting in the
tions are approximately symmetrically distributed with middle part being large at the end of the process.
respect to the jacking axis and are basically in the form
of a settlement trench. For the CJ1 and CJ2 sections, when 5 Summary and conclusions
the box jacking machine passed completely on September
17, 2017, and September 30, 2017, respectively, the surface In this paper, a case study of the longest large-section
settlement reached a maximum value and then gradually rectangular box jacking project in China is presented.
decreased under the action of grouting. Owing to frequent The box jacking passed through a silty sand layer with
and uneven grouting, the ground settlement on the CJ1 sec- groundwater, and the minimum depth of overburden was
tion was small but fluctuated frequently; during the jacking only 3.5 m when crossing underneath the Yuanhetang
124 X.L. Chen et al. / Underground Space 6 (2021) 101–125
River. In this case, key techniques of the construction were to the ground. During the construction, the grouting
described in detail and the ground deformation caused by pressure needed to be reasonably controlled and the
box jacking was analyzed. The experience encountered slurry should be injected in time. A slurry spillover
and the technology used in the construction can be summa- occurred near the CJ2 section owing to excessive
rized as follows: grouting pressure, resulting in larger surface settle-
ment; the maximum settlement on the CJ3 section
(1) Considering that the box jacking passed through a was over 70 mm because of insufficient grouting.
silty sand layer with high potential groundwater
flows, a combination system of the waterproof cur-
tain and high-pressure jet grouting piles was selected Acknowledgments
and the soil in front of the shaft opening was rein-
forced with triaxial mixing piles. A rubber water stop The authors thank Shanghai Civil Engineering Co.,
was installed to avoid the phenomenon of soil erosion Ltd., of CREC for cooperation in the field tests and data
during the launch of the box jacking machine, which collection of rectangular box jacking.
ensured the safety of the launching shaft.
(2) Various measures were taken for trajectory control. Declaration of Competing Interest
The flatness and verticality of the reaction wall and
the reaction steel box were strictly controlled, and The authors declare that there are no conflicts of interest
the center line, elevation, and slope of the guide rails to this work.
were checked repeatedly to meet the requirements,
and the head was raised 5 mm when the box jacking References
machine was in position to control the launching atti-
tude. The box jacking machine and the subsequent Barla, M., Camusso, M., & Aiassa, S. (2006). Analysis of jacking forces
during microtunnelling in limestone. Tunnelling and Underground
five specially reinforced concrete boxes were con- Space Technology, 21(6), 668–683.
nected by welding the steel bars to prevent the box Bergeson, W. (2014). Review of long drive microtunneling technology for
jacking machine from drifting and loosening during use on large scale projects. Tunnelling and Underground Space
Technology, 39, 66–72.
long-distance jacking. An automatic measuring sys- Chapman, D. N., Rogers, C. D. F., Burd, H. J., Norris, P. M., & Milligan,
tem was developed to obtain the deflection and devi- G. W. E. (2007). Research needs for new construction using trenchless
ation data of the box jacking machine. Corrective technologies. Tunnelling and Underground Space Technology, 22(5/6),
491–502.
measures were reasonably selected to ensure that Cheng, M., & Lu, Y. (2015). Developing a risk assessment method for
the tunnel was jacked according to the planned complex pipe jacking construction projects. Automation in Construc-
alignment. tion, 58, 48–59.
Choo, C. S., & Ong, D. E. L. (2015). Evaluation of pipe-jacking forces
(3) For the reduction of the friction resistance during the based on direct shear testing of reconstituted tunneling rock spoils.
jacking process, paraffin wax was melted and smeared Journal of Geotechnical and Geoenvironmental Engineering, 141(10),
on the outer surface of the box and was fired to guar- 04015044.
Gao, Y., Feng, C. Y., & Cheng, P. (2018). Overall-carrying-soil effect of
antee the infiltration of the paraffin wax into the con- shallow buried rectangular pipe jacking. Chinese Journal of Geotech-
crete, which not only could increase the smoothness nical Engineering, 40(10), 1936–1942 (in Chinese).
of the concrete wall but also could prevent the box GB (National Standard of the People’s Republic of China) (2009).
Standard for test methods of long-term performance and durability of
structure from being affected by the external corro- ordinary concrete. GB/T 50082-2009. Beijing: China Architecture and
sive environment. Parametric tests were conducted Building Press (pp. 31) (in Chinese).
on site to determine a suitable formula of the thixo- Khazaei, S., Shimada, H., Kawai, T., Yotsumoto, J., & Matsui, K. (2006).
Monitoring of over cutting area and lubrication distribution in a large
tropic slurry, and a thick mud, which had a good fill- slurry pipe jacking operation. Geotechnical and Geological Engineering,
ing and supporting effect, was also used to ensure the 24(3), 735–755.
integrity and lubricity of the slurry jacket. Li, H., Yang, Y., Tu, X., & Wang, T. (2012). Analysis of jacking force for
rectangular pipe-jacking machine. Przeglaz d Elektrotechniczny, 88(9b),
(4) Temporary steel pipe pile cofferdams were built in the 200–203.
Yuanhetang River, and an anti-buoyancy slab was Ma, B. S., Stein, D., & Jiang, G. S. (2004). Pipe jacking and microtun-
constructed after pumping, dredging, and leveling. nelling technology. Beijing: China Communications Press (pp. 4–8) (in
Chinese).
The cofferdam construction was divided into two Ma, B. S. (2008). The science of trenchless engineering. Beijing: China
phases and had little impact on the flow. The anti- Communications Press (pp. 341–349) (in Chinese).
buoyancy slab achieved good engineering results; Mamaqani, B. H., & Najafi, M. (2014). Settlement analysis of box jacking
projects. Pipelines 2014, August 3–6, 2014, Portland, Oregon. Reston,
there was neither uplifting of the box segments nor VA, USA: American Society of Civil Engineers.
seepage of the machine or box joints. Milligan, G. W. E. (1996). Site-based research in pipe jacking: Objectives,
(5) For the large-section rectangular box jacking project procedures and a case history. Tunnelling and Underground Space
Technology, 11(1), 3–24.
with shallow overburden, an earth pressure balance Pellet-Beaucour, A. L., & Kastner, R. (2002). Experimental and analytical
box jacking machine was selected and a combined study of friction forces during microtunneling operations. Tunnelling
cutter plate was adopted to reduce the disturbance and Underground Space Technology, 17(1), 83–97.
X.L. Chen et al. / Underground Space 6 (2021) 101–125 125
Peng, L., Wang, Z., Ye, Y., & Yang, W. (2015). Technological pipe-jacking. Tunnelling and Underground Space Technology, 25(4),
development and research status of rectangular pipe jacking method. 469–477.
Tunnel Construction, 35(1), 1–8 (in Chinese). Sofianos, A. I., Loukas, P., & Chantzakos, C. (2004). Pipe jacking a sewer
Shimada, H., Sasaoka, T., Khazaei, S., Yoshida, Y., & Matsui, K. (2006). under Athens. Tunnelling and Underground Space Technology, 19(2),
Performance of mortar and chemical grout injection into surrounding 193–203.
soil when slurry pipe-jacking method is used. Geotechnical & Geological Sun, Y., Wu, F., Sun, W., Li, H., & Shao, G. (2018). Two underground
Engineering, 24(1), 57–77. pedestrian passages using pipe jacking: Case study. Journal of
Shou, K. J., & Liu, Y. C. (2004). Modeling of soft rock tunneling in western Geotechnical and Geoenvironmental Engineering, 145(2), 05018004.
Taiwan. Tunnelling and Underground Space Technology. Under- Yang, H. J., Rong, L., & Xu, H. C. (2016). Application of drag reduction
ground Space for Sustainable Urban Development. In Proceedings of technology to extra-large cross-sectional rectangular pipe jacking: Case
the 30th ITA-AITES World Tunnel Congress Singapore, 22–27 May study of tunnel crossing underneath Zhongzhou Road in Zhengzhou.
2004 (Vol. 19(4/5)). Tunnel Construction, 36(4), 458–464 (in Chinese).
Shou, K. J., & Chang, F. W. (2006). Analysis of pipe-soil interaction for a Zhang, D., Liu, B., & Qin, Y. (2016). Construction of a large-section long
miniature pipejacking. Journal of Mechanics, 22(3), 213–220. pedestrian underpass using pipe jacking in muddy silty clay: A case
Shou, K., Yen, J., & Liu, M. (2010). On the frictional property of study. Tunnelling and Underground Space Technology, 60, 151–164.
lubricants and its impact on jacking force and soil–pipe interaction of