Professional Documents
Culture Documents
Seminar 19
FRS 115 – Application to
Construction Contracts
Semester 1, AY 2017/2018
Step 1
Identify whether there is a construction contract with a
customer
5 criteria to be met (FRS 115, para. 9):
a. The parties to the contract have approved the contract
and are committed to perform their respective
obligations.
Copyright © Nanyang Business School 2
Step 1 - Identify the contract with
the customer
For criterion c)
- the “alternative use” argument may be problematic if
customisation of the asset occurs relatively late in the
construction process.
- the cumulative amount of payments must at all times
throughout the contract, at least correspond to the
amount that would be necessary to compensate the
entity for performance completed to date.
Point in time
No
Over time
Progress Billings
• JE2: Progress billings
Dr Account receivable $400k In SFP
Cr Progress billings $400k Contra against CIP in SFP
Copyright © Nanyang Business School 20
Progress Billings
An account (in statement of financial position) to
record the amounts billed to the customers for work
performed on a contract whether or not they have
been paid by the customers.
Cash Collection
• JE3: Cash collection
Dr Cash $300k In SFP
Cr Account receivable $300k In SFP
Copyright © Nanyang Business School 22
At the end of each reporting
period,
Construction-in-progress
Costs incurred to date $S
Add/(less) attributable profit/(loss) $T
$X
Less Progress billings $Y
Under (over) billings $Z
Illustration 1 – Project B
Contract price = $6m; to be completed in 4 yrs
At the end of Year 20x4
(STEP 1):
Cumulative costs incurred = $6,500k
Estimated additional costs-to-complete = $0k
Total costs = $6,500k
Total LOSS on Project = $6,000k – $6,500k = -$500k
Overall net loss!
End of Project!
Illustration 1 – Project C
Contract price = $15m; to be completed in 3 years
At end of Year 20x3
Current costs incurred = $5,000k
Additional costs-to-complete Cannot be estimated reliably
% completed to-date (cost-to-cost basis) = ?
Revenue to be recognized = $5,000k
Current profit = $0