Professional Documents
Culture Documents
A Group
Brand
ALPIMATIC – AUTOMATIC BX
capacitor banks fitted with
ALPTEC controllers 3-5-7-12 steps
Protection - connection
Commissioning
Maintenance
CONTENTS
I - PROTECTION - CONNECTIONS
A - PROTECTION 4
B - CONNECTIONS 4
1) Power circuit 4
2) Auxiliary circuits 4
C - OPERATION ON GENSET 5
B - APPLY POWER 7
III - MAINTENANCE 8
VI - APPENDICES
A - MANUAL MODE OPERATION 13
Page 3
Une marque
du Groupe
ALPES TECHNOLOGIES
I - PROTECTION - CONNECTIONS
A - PROTECTION
For capacitor banks which do not have a factory-fitted general protection system, a protective
device must be fitted at the head of the power cable:
- either a circuit breaker:
thermal relay: set to between 1.3 times the nominal current
magnetic relay: set to between 6 and 8 times the nominal current.
- or a HRC fuse-switch, type gG, rating of between 1.4 and 1.6 times the nominal current.
B - CONNECTIONS
1) Power circuit
The capacitor and its accessories require power cables with a minimum rating of:
2) Auxiliary circuits
For correct operation of the power factor controller, a current transformer must be connected
to ALPIMATIC units.
It must be fitted on phase L1 of the unit to be compensated, upline from all receivers and the
capacitor bank.
The current transformer secondary must be connected on the auxiliary terminal block, marked
S1 and S2 (see diagram below).
Page 4
Une marque
du Groupe
ALPES TECHNOLOGIES
Network P1 P2 load
C.T.
S1 S2
phase L1 of network
Capacitor bank auxiliary terminal block
S1 S2
Network P1 P2 Load
C.T.
S1 S2
A
phase L1 of network
Capacitor bank auxiliary terminal block
S1 S2
Particular cases:
• If the installation has an existing C.T you may use it, provided it meets the recommendations
on page 4 (position, characteristics, power, etc.).
In this case, the power factor controller is connected in series with the existing ammeter
(diagram 2).
• If the installation has two or more power transformers in parallel, compensated by a
single capacitor bank, you must plan:
- one C.T on phase L1 of each transformer
- one overall C.T, adding type 5 + 5 ... / 5 A
In this case, the equivalent C.T primary to be programmed in the controller is calculated by
adding the primary values of each C.T.
C - OPERATION ON GENSET
If the installation can be powered by a generator unit in the event of a mains power cut, we
recommend to automatically disconnect the capacitor bank when the generator is operating.
To achieve this, simply remove the shunt between terminals G and E (see diagrams on pages
10, 11 and 12) and connect between them a contact which is opened when the generator is
operating.
When the generator is started, the capacitor bank will be disconnected automatically.
Page 5
Une marque
du Groupe
ALPES TECHNOLOGIES
Check the protective device settings and the power cable connections (page 4).
Check the C.T is located on phase L1 of the main installation, upline from all
receivers to be compensated and the capacitor bank (see diagram 3 below)
n° 1 n° 2 n° 3
C.T C.T.
C.T
Ventilation
Install the capacitor bank in electrical room properly ventilated
* temperature maxi: 40° C and average over 24 h : 35°C
Ventilation of the capacitor bank is made by an airflow
* entry by the bottom (ventilation area on front door and back - sides)
* output by the top:
9Capacitor bank without detuned reactors: ventilation area on front door
and back – sides
9Capacitor bank with detuned reactors: extracting fan
Make sure these ventilation areas have a clearance distance at least 100mm from any
obstacle (wall, electrical enclosure…
Make the airflow is sufficient by removing any obstacle from air input and output
Make sure the capacitor bank is installed in a dry and non dusty electrical room
Page 6
Une marque
du Groupe
ALPES TECHNOLOGIES
B - APPLY POWER
If the power factor controller displays the message “Ct”, you must enter the primary
value of your C.T, using the arrows ∆ and ∇: enter this value
(Examples : T.C. 800/5 A : P01 = 800 ; T.C. 1000/5 A : P01 = 1.00 ; T.C. 1250/5 A : P01 = 1.25)
Switch to manual mode by pressing the key MAN / AUT the led “MAN” flashes and all
steps connected are disconnected
Check the location of the current transformer: a simple method of checking that the C.T is
correctly located on phase L1 of the installation involves checking that there is zero
voltage difference between network phase L1, on which the C.T is installed, and phase
L1 of the capacitor bank.
P1 P2
L1
L2 C.T. V
capacitor bank busbar
L3 U=0V
L1 L2 L3
network
Switch to automatic mode by pressing key MAN / AUT the led “AUT” light-on and the
capacitor bank starts to operate.
Page 7
Une marque
du Groupe
ALPES TECHNOLOGIES
III - MAINTENANCE
1) open the fuse-switch on the auxiliary circuits (ref. F1 on pages 10, 11 and 12)
The capacitors are fitted with discharge resistors which reduce the residual voltage to 75V in
3 minutes (in compliance with applicable standards). Before short-circuiting the terminals
and earthing the capacitors,
check that the equipment is clean, as accumulated dust can hamper correct
ventilation and insulation.
check the condition of the contacts of switching devices (contactors, switches, etc.).
The contactors are heavy loaded during closing and opening on capacitive
currents. We ask for their replacement every 5 years.
check the ventilation of the local where the equipment is installed (maximum
temperature 40°C and an average value of 35°C during 24h must be respected)..
check the temperature inside the capacitor enclosure (maximum temperature 45°C
and an average value of 40°C during 24h must be respected).
Page 8
Une marque
du Groupe
ALPES TECHNOLOGIES
A Indicator lit : inductive network J Indicator lit : display “C” shows the cos ϕ set
point value
B Indicator lit : capacitive network K This key is used to set the various
parameters and scroll through the functions.
C Digital display L Indicator lit : manual mode operation
D Indicator lit : display “C” shows the network M Indicator lit : automatic mode operation
voltage
E Indicator lit : display “C” shows the current N Indicators lit: indicates the steps triggered.
value for phase L1 of the installation
F Indicator lit : display “C” shows the power O This key toggles between manual and
value in kvar to attain the cos ϕ set point automatic mode
G Indicator lit : display “C” shows the average P Parameter selection or modification key
weekly power factor (increase ∆)
H Indicator lit : display “C” shows the Q Parameter selection or modification key
percentage of overload current caused by (decrease ∇)
the harmonic current at the capacitor
terminals
I Indicator lit : display “C” shows the electric
panel temperature (valid after 20-30
minutes after power up).
A L
B M
C
D N
E
F
G
H
I
J
O
K
P
Q
Page 9
Une marque
du Groupe
ALPES TECHNOLOGIES
: customer connection P2 P1
C.T
T.C. customer busbar
L1
S2 S1
L2
load network
L3
D J
E capacitor bank busbar
L1
L2
L3
FU
K F1
L3 G E
S2 S1 L2
L
capacitor bank terminal
R
1 2 3 4---- 12
Co S2 S1 C 0 220/240V TTL
RS232
ALPTEC terminal block
Page 10
Une marque
du Groupe
ALPES TECHNOLOGIES
FU
K F1
L3 G E
S2 S1 L2
L
capacitor bank terminal
R
1 2 3 4---- 12
Co S2 S1 C 0 380/415V TTL
RS232
ALPTEC terminal block
Page 11
Une marque
du Groupe
ALPES TECHNOLOGIES
: customer connection
P2 P1
customer busbar
C.T
L1
S2 S1
L2
load network
L3
E D J
customer busbar
L1
L2
L3
FU
K TR1
capacitor bank terminal block
F2
L F1
S2 S1 G E
R
1 2 3 4---- 12
Co S2 S1 0 C TTL
380/415V
RS232
Page 12
Une marque
du Groupe
ALPES TECHNOLOGIES
VI - APPENDICES
If you wish you may operate your capacitor bank in manual or "forced" mode.
Enter manual mode by pressing the MAN / AUT key. The "MAN" indicator will be lit.
All the steps under voltage are disconnected.
Press the arrows ∆ and ∇ as many times as necessary to select the step that you wish
to connect or disconnect: the selection is obtained as soon as the corresponding led
flashes.
Press the "MODE" key to validate this selection.
Repeat the operation for each step you wish to connect or disconnect.
Note:
In manual mode, the selected steps remain connected.
Considering the discharging time of the capacitors, the power factor controller avoids the
re-connection of the same step within 3 minutes. In that case the led “MAN” flashes until
the time is elapsed.
Page 13
Une marque
du Groupe
ALPES TECHNOLOGIES
VI - APPENDICES
Page 14
Une marque
du Groupe
ALPES TECHNOLOGIES
Voltage failure duration is more than 8ms. All the steps are disconnected
Nota: following 8 alarms: A01 to A08 can be remoted by dry contacts. (terminals 7&8 for Alptec 5
and Alptec 7 – terminals 12&13 for Alptec 12. For more information, please consult our technical
department
* press the key MODE several times, until the led “SET COS ϕ” indicator on the front panel lit.
* using the arrow keys ∆ and ∇, set the cos ϕ to the target value.
* in the factory we set the cos ϕ set point to 0.96 inductive
D – KEYPAD LOCK
Locking:
It is possible to lock the keypad to avoid any modification of the parameters:
Keep pressed MODE key, press 3 times key ∆ and 2 times key ∇: then release MODE key
and “Loc” will appears on the screen
Unlocking:
Keep pressed MODE key, press 3 times key ∆ and 2 times key ∇: then release MODE key
and “UnL” will appears on the screen
Note: any modifications of the power factor controller parameters (except parameter
P01) will cancel the manufacturer warranty on the complete equipment.
Page 15