Professional Documents
Culture Documents
Updated Term Paper (5310) PDF
Updated Term Paper (5310) PDF
Roll:-5310
Term Paper
INDEX
Q.No. Question Name and description Page no.
1 Introduction 3
2
Sourae Mridha
Roll:-5310
Question No 1:-
Introduction
Answer to the question no 1
Madam, this is Sourae Mridha. Roll no is 5310. Since this roll number is
an even number. That is why the answer to my term paper is given
below for even number. But before that I want to say something about
the course.
3
Sourae Mridha
Roll:-5310
Question No 2:-
Objectives and applications of laterally loaded and
machine foundation.
Answer to the question no 2
P.T.O.
4
Sourae Mridha
Roll:-5310
To carry out design of structures as per the principles of
structural catalysis and design. He should also ensure that
the design is safe, durable, and economical.
To prepare the estimates to know the probable cost of
completion of work.
Applications:
1. Foundations
The loads from any structure have to be ultimately transmitted to a soil
through the foundation for the structure. Thus, the foundation is an
important part of a structure, the type and details of which can be
decided upon only with the knowledge and application of the principles
of soil mechanics.
5
P.T.O.
Sourae Mridha
Roll:-5310
3. Pavement Design
6
Sourae Mridha
Roll:-5310
Question No 3(a):-
Describe and classify Sheet Pile Wall.
Answer to the question no 3(a)
Sheet piles are structural sections that can be interconnected to form a
continuous sheet pile wall. Sheet piles rely on their structural stiffness to
resist lateral forces due to earth, water, or other loads. While different
types of sheet piles are available, steel sheet piles are the most common
in modern construction. The following paragraphs describe the main
types of sheet piles.
2. Increased strength
7
P.T.O.
Sourae Mridha
Roll:-5310
The main drawback of steel sheet piles versus other sheet pile types is
that corrosion protection is required in highly corrosive environments.
Also, with the exception of precast concrete sheet piles, steel sheet piles
are more expensive.
8
P.T.O.
Sourae Mridha
Roll:-5310
construction. Their most common application today is in relatively
shallow excavations for utilities when groundwater is not present.
Timber sheet piles could potentially be used in long-term or marine
environments when the timbers are properly treated. However, their
durability would be questionable.
9
P.T.O.
Sourae Mridha
Roll:-5310
the type of synthetic sheet pile material that is used, vinyl sheet piles can
perform differently under long term exposure to sunlight or chemicals.
Vinyl sheet piles have smaller yield strengths and are less stiff when
compared to steel sheet piles. An engineer specifying vinyl sheet piles
should consult with the individual manufacturer regarding any
restrictions or applicability of using a specific product.
10
P.T.O.
Sourae Mridha
Roll:-5310
concentration of copper, chrome and salt. This problem may be solved
simply by placing a membrane between the lumber and the aluminum.
Fibre Reinforced Polymer (FRP sheet piles) products have been used in
many areas, FRP threaded bars, FRP rebar, FRP pipe, FRP fully
threaded tie rod, FRP waler etc. Superload Sheet Piling is manufactured
with electrical grade fiberglass and high strength resins. The pile
transfers pressure from the high side of the wall to the soil in front of the
wall.
12
Sourae Mridha
Roll:-5310
Question No 3(b):-
State the uses of sheet pile wall.
Answer to the question no 3(b)
Sheet piling retains soil, using steel sheets with interlocking edges and is
applied using both vibratory and vibration-free installation rigs.
Common uses of sheet piles -
Support excavations
Construct cofferdams
Construct seawalls and bulkheads
Create barriers to groundwater flow
Retaining walls
Bridge abutments
Tunnels
Pumping station
Water treatment plants
Basement
Underground car parks
Port facilities
Locks and dams
Waterfront structures
Piled foundations
Excavations and trenches
13
P.T.O.
Sourae Mridha
Roll:-5310
Cofferdams
Ground water diversion
Barrier for ground water treatment systems
Containment walls
Flood protection
Coastal protection
Tunnel cut and cover
Bulkheads and seawalls
Weir walls
Slope stabilization
Landfill
14
Sourae Mridha
Roll:-5310
Question No 3(c):-
List the advantage of sheet piling over other retaining
structures.
Answer to the question no 3(c)
There are various types of earth-retaining structures. Where a
differential surface level is to be established with a vertical interface, a
retaining wall is used. Steel sheet piling is one form of retaining wall
construction. Sheet piles resist soil and water pressures by functioning as
abeam spanning vertically between points of support.
Steel sheet piles are used for temporary and permanent retaining walls.
In temporary works and cofferdams the sheet piles enable deep
excavations to be made to facilitate construction below ground and
water level of other permanent works. On completion of construction the
sheet piles are usually extracted for reuse on other projects.
Applications have seen the use of steel sheet piles as permanent
retaining walls for structures including quay walls, bridge abutments,
underground storage tanks, basements and underground carparks.
Where retained heights are large, such as for underground transport
station access combined walls are used. These retaining walls require
propping at various positions and the retaining wall can comprise of high
modulus piles.
15
P.T.O.
Sourae Mridha
Roll:-5310
The advantages of using steel sheet pile retaining walls can be
summarised as follows:
16
Sourae Mridha
Roll:-5310
Question No 3(d):-
An anchor sheet pile bulkhead is shown in figure.
d) Calculate the actual depth of penetration (Use,D actual = 1.5 Dtheory)
e) Draw the pressure distribution diagram, and
f) Determine the anchor force per unit length of wall.
l1 = 2.5 m Sand
3 0
L1 = 8 m γ = 18kN/m , φ = 30
Sand
L2 = 18 m 3 0
γsat = 22kN/m , φ = 30
Dredge Line
Sand
3 0
D γsat = 22kN/m , φ = 30
Solution:-
l1 = 2.5 m Sand
L1=8 m 3 0
L1 = 8 m F γ = 18kN/m , φ = 30
𝜎′1
Sand
Pa
L2 = 18 m L2=18 m 3 0
γsat = 22kN/m , φ = 30
P.T.O.
Sourae Mridha
Roll:-5310
l2 = L1 - l1
= 8 - 2.5
= 5.5 m
Step 1:-
Rankine active earth pressure coefficient,
𝜑 𝜑
Ka = tan2 (45 − ) = tan2 (45 − ) = 0.33
2 2
Step 2:-
Lateral pressure, when L1 = 8 m
𝜎′1 = 𝛾 L1 Ka = 18 x 8 x 0.33
= 47.52 kN/m2
Lateral pressure, when L2 = 18 m
𝜎′2 = 𝜎′1 + 𝛾′ L2 Ka
= 47.52 + (22 - 11) x 18 x 0.33
= 112.86 kN/m2
Step 3:-
𝜎′ 2
L3 =
𝛾 ′ (𝐾𝑝 − 𝐾𝑎 )
112.86
=
22−11 (3−0.33)
= 3.84 m
18
P.T.O.
Sourae Mridha
Roll:-5310
Step 4:-
Net active pressure
1 1 1
Pa = L1 𝜎′1 + L2 𝜎′2 + L2(𝜎′2 - 𝜎′1) + 𝜎′2 L3
2 2 2
1 1 1
= (8 x 47.52) + (18 x 47.52) + 18(112.86 − 47.52) + (112.86 x 3.84)
2 2 2
𝑀𝐸 21982.29
Z= = = 11.88 m
𝑃𝑎 1850.19
Step 6:-
3𝑃𝑎 [ 𝐿1 + 𝐿2 + 𝐿3 −(𝑍+𝑙 1 )]
L42 + 1.5 L42 (l2 + L2+L3) - =0
𝛾′ (𝐾𝑝 − 𝐾𝑎 )
3×1850.19[ 8+18+3.84 −(11.88−2.5)]
L42 + 1.5 L42 (5.5+ 18 +3.84) - =0
22−11 (3−0.33)
L42 + 41.01 L42 - 2921.75 = 0
L4 = 8.34 m
∴ L4 = 8.34 m
19
P.T.O.
Sourae Mridha
Roll:-5310
Step 7:-
Theoritical depth of penetration,
Dtheory = L3+L4
= 3.84 + 8.34
= 12.18 m
Actual depth of penetration,
Dactual = 1.5 x Dtheory
= 1.5 x 12.18
= 18.27 m (Answer)
Step 8:-
Anchor force per unit length,
1
F = Pa - 𝛾 ′ (𝐾𝑝 − 𝐾𝑎 ) L42
2
1
= 1850.19 - (22 - 11) x (3 - 0.33) x (8.34)2
2
20
Sourae Mridha
Roll:-5310
Question No 4:-
Conclusion
Answer to the question no 4
To become a civil engineer first of all to focus on foundation
engineering. Because the structure may be strong but for the durability
and stability of the structure its foundation needs to be strong enough for
which one should have thorough knowledge of foundation engineering.
The basic objective of this study is to discover improvements in practice
and procedures that will enable planning and conducting more effective
geotechnical site investigation programs. This subject presents the
subcommittee's judgments on matters that bear on achieving the study
objective. Civil engineer can apply their knowledge to specific fields
such as, foundation engineering, geotechnical engineering,
transportation engineering, surveying, construction engineering,
environmental engineering, and structural engineering, to become a civil
engineer must be obtained. Foundation Engineering is one of the most
necessary subjects of civil engineering since all the structures are to be
built on foundations. By knowing about the foundation engineering we
can improve the durability of any civil engineering structures.
21