Professional Documents
Culture Documents
ABSTRACT
In jointed rock a potential mode of slope failure is a step path where the failure surface follows a combina-
tion of joints from two sets. This step path geometry can be defined using the dip, length, spacing, and overlap
characteristics. The sets that make up the step path should have similar strikes; usually, one set is shallow
dipping ( 20° - 50°) and the other steep dipping ( 50° - 90°).
Detail line mapping or joint set mapping is used to acquire the data for estimating the distributions of the
joint set characteristics. These distributions are Monte Carlo sampled and the results are used in an algorithm
of logic and decision making. The algorithm assumes the flattest step path will be followed by the failure. The
step path follows a flat joint until the last steep joint is intersected. The path proceeds up the steep joint
to the next flat joint. When joint lengths are short relative to joint spacings, the step path may not be con-
tinuous over the specified slope height. An estimate of percent intact rock can be made from the number of rock
bridges required to complete the step path geometry for the specified slope heiqht.
The step path modeling gives distributions of both step path angles and percent intact rock. These distribu-
tions can then be used in conjunction with Jaeger's step path stability analysis to determine the probability of
failure.
Preliminary field checking at the Cyprus Bagdad mine and at 3amangwato Concessions' Pikwe mine indicates an
average step path angle can be predicted. Additional work is required to relate stress conditions to the step
path geometry, to include more than two joint sets in the model, and to develop a more complex algorithm to pre-
dict other than the flattest step paths.
l
suitable for 2-dimensional analysis.
"Ste~ p1tn angle-- 4) Under tensile stress, a pre-existing fracture
_,I will propagate to intersect the first fracture,
A.vq~fdlg ;ie,..cent tanstle·· • S1 • 5 ?
but not beyond.
lt 100
1usttl"" Intact rocx.
Jo Int 5) A rock bridge is more likely to fail in ten-
sion than in shear.
Figure 4. Steo Path Angle and 6) Cross joints that do not intersect, but that
Percent Intact Rock fall within approximately 5 cm of the end of
a master joint, are still taken to allow the
step path geometry to continue to the next
DESCRIPTION OF STEP PATH MODEL master joint.
The step path geometry is fanned by the interaction 7) The flattest path will be followed, that is,
of 2 joint sets that have similar strikes. The master the step path will follow a master joint to
joint set is gently dipping (usually 20° - 50°), while the cross joint farthest out (Figure 7). The
the cross joint set is steeply dipping (usually 50° - path will then follow the cross joint until
90°). The path with least resistance is the one with it intersects and continues along another mas-
continuously intersecting cross joints and master ter joint.
joints (Figure 5). Intact rock "bridges" may occur
if the fracture lengths are short in comparison to
the fracture spacing (Figure 6). INPUT FOR STEP PATH MODEL
Assumptions for the minimum resistance step path Distributions of fracture dip, length, spacing, and
Richard D. Call and David E. Nicholas
3
' \
\
GENERATION OF STEP PATH MODEL I
I
I
\
A logic flow chart and a step path diagram (Figure I
I
\
pY, SY
Yes 1Y
/2Y, 7N
& SPICJIC
/7N
TO ClOSS JOIUI") UP MSTU JOllT
n CIOSS JQIU(I)
6N ~I 7Y. 81
6Y Yes /(1N,2N
UJECT ClOSS olOUT
x3N,41
y /4f~
~I:::::
Cf.Jl[UT( CtOSS JOUT
l(llliTH, L(lllGTM', OIP
l VAClllG
r ~ Hl, 2N
No
8N
~:::::·Sil,"
:.,~C JLAT [ I .UO 'I'
~:::::
COOIOlll\T[S FIO" LAST
lllTEll:HCTIOIC Of
ClOSS JOlllT l IUSTUJOIJIT
~171,81
x/::.
S.U•ll MSTER JOUT
2
IJACIH '91 HUil[ HCI
Hf DI(
:1. 81<, 9N
CAL.tULAU
~
I UO f COOHJUU
31, 71. SN, 9N, ION
60
...
"
~
:•orth-5outh
....""' 50
~
-;: 40
;"'
u
:o
/ Nortn-South
?O
z,.:J ooser"VdtlOn'i
50 10 80
S ttP ?11 ttl Ang I e ( deqrees}
68 90
/
i
l. TS.""\
66 f ~tahn l onqtlls
80 '
64
70
I
.
~
~ 6Z
::'
" ,..,
60
II
\
!
"'c
60 c
., I
...f
< so
"'
~ 58 u
..
Q.
~ 56
.,
~
~
40
~
'-'
JO
54
52
!O 20 JO 40 50 60 70 ao
so 60 70 aa
Figure 12. Median Step Path Angle Step ?ath Angle {deqrees)
l
/
too
0.5'1
'"l
80
(Hadian
Sp1cin9s
66
1al 64
6Z
..
~ 60
c
Ill
~ ;o *6
M
O'
QJ
~5
I
.....QJ
O'
'"l
30
~
.c:
.._,
56
"'a.
p. 5
.._,QJ
20 Ul
52
50 60 70 80 90 too l!O 11
Figure 14. Step Path Angle Cumulative Frequency Figure 15. Step Path Angle Versus
Curves at Various Median Master Median Master Joint
Joint Spacings Length
Table 1.
Comparison of Mapped with Cl•mputer
Generated Step Path Geometry at Cyprus-Bagdad
Mapped in
Field 43° 1. 5' 12 I goo 4' 18' 60° 18'
Using Detail
Line Struc- 60.30° 5.65° 120'
ture Data 59.19° 4.21° 200'
59.54° 3.69° 280'
59.70° 3.28° 360'
59.69° 2.69° 480'
Richard D. Call and David E. Nicholas
8
H
85
80
<II
.....
g'70
..:
.i::
µ
<1l -1-----190 E
"'65
p,
<II
µ
CJl
60
,;
. 10 . 20 .JO . 40 . 50 . 60 . 70 . 80 . 90 !. '
Figure 16. Step Path Angle Versus Median Figure 17. Lower Hem1sphere Schmidt Point Plot of
Master Joint Spacing Step Path Structure, Bagdad Mine
CONCLUSIONS
and Kim, 1978) but the volume of material in the
In rock slopes were fracture lengths are not failure is less.
sufficiently long to produce full slope failure, a
combination of 2 joints can form a step path geometry.
It is possible from the distributions of dip, length, REFERENCES
and spacing to predict the minimum resistance step
path geometry. Distributions of both the step path Barton, Nicholas, "Progressive Failure of Excavated
angles and percent intact rock result from the step Rock Slopes", Stability of Rock Slopes - 13th
path model. Symposium on Rock Mechanics, ed. by E.J. Cording,
ASCE, New York, 1972, pp. 139-170.
Preliminary field checking at Bamangwato Conces-
sions' Pikwe mine shows the calculation of the step Call, R.D. and Kim, Y.C., "Composite Probability of
path angle to be sensitive to the spacing distribu- Instability for Optimizing Pit Slope Des·ign",
tion. Sensitivity to the lenqth distribution paoer for 19th U.S. Symposium on Rock Mechanics,
decreases as the slope height increases above about 1978, 4 pp.
25 m.
Call, R.D., Savely, J.P., and Nicholas, D.E., "Esti-
At the Cyprus-Bagdad mine, comparisons were made mation of Joint Set Characteristics from Surface
between observed step paths and computer generated Mapping Data", Ch. 9 in Monograph on Rock
step paths. Agreement within 1 standard deviation Mechanics ApQlications in Mining, ed. by W.S.
of the true value can be expected. It is likely Brown, S.H. Green, and \J.A. Austrulid, AIME, New
that the model predicts the average step path angle York, 1977, pp. 65-73.
more closely for high slope heights.
Jaeger, J.C., "Friction of Rocks and Stability of
Additional work is required to develop a more Rock Slopes", Geotechnigue, vol. 21, no. 2, 1971,
complex algorithm to predict other than the flattest pp. 97-134.
possible step paths, to include more than 2 joint
sets in the model, and to relate stress conditions Jennings, J.E., "A Mathematical Theory for the Calcu-
to the step path geometry. By storing the location lation of the Stability of Slopes in Open Cast
of all master joints and cross joints generated, a Mines", Planning Open Pit Mines, ed. by P.W.J.
steeper, more continuous path can be defined. This Van Rensburg, South African Inst. of Mining and
creates a higher probability of failure, PF, (Call Metallurgy, Cape Town, South Africa, 1970, pp. 87-
102.