LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

ANNUAL AND COMPOUNDED LIFE CYCLE COST ANALYSIS OF A


STEAM BOILER

I. O. Ohijeagbona,*, M. A. Waheedb, S. O. Jekayinfac

a
Mechanical Engineering Department, University of Ilorin,
P. M. B. 1515, Ilorin, Nigeria.
b
Mechanical Engineering Department,
University of Agriculture, Abeokuta, Nigeria.
c
Agricultural Engineering Department,
Ladoke Akintola University of Technology, Ogbomoso, Nigeria.
*
Corresponding Author. Tel: 07030092411
E-mail: idehaiohi@yahoo.com, ohijeagbon.io@unilorin.edu.ng (I. O. Ohijeagbon)

ABSTRACT
The generic total economic cost of an industrial steam boiler over the service life of the boiler in relation to initial
cost and discounted future expenditures was investigated. The present value method of life cycle cost analysis
(LCCA) was used to analyse the yearly and compounded cycle cost; annually and compounded future fuel cost of
an industrial steam boiler from the initial investment cost, generating cost per annum and disposal cost. For a
steam boiler utilizing 754 kg/hr of low pour fuel oil (LPFO) in an estimated operating period of 4,186 hr/yr, the
generating and operating costs per annum were obtained as 13,019,355.00 /yr (85,344.84 S/ / yr ) and
15,623.226.00 /yr (102,413.81 S/ / yr ) respectively. Inflation rate of fuel cost was responsible for the break-even
period in the life cycle cost of steam boiler operation.
The LCCA methodology presented in this study is a veritable tool for economic and managerial planning and
implementation for sustainable use of industrial boilers.

Keywords: life cycle, cost analysis, steam boiler, fuel cost, break-even, inflation rate.

1 Introduction initial and long-term operating costs (Lutz et al.,


Most financial people in any organization 2006). LCC analysis should be performed early in the
will say that the best way to evaluate the actual cost design process while there is still a chance to refine
for a long term asset is through the life cycle costing the design to ensure a reduction in life-cycle costs.
(LCC) discipline (CleaverBrooks, 2010). It can The option identified with the lowest total present
incorporate fuel cost escalation into the economic value is the most economical or least cost
model and it considers the cost over the life of the option/approach (Oeveren and Wilks, 2009).
system rather than just the first cost (Thumann and LCCA had been used in many studies, such
Mehta, 2001). as bridge for use by transportation agencies (NCHRP,
LCC is based on an understanding that the 2003). It was used in ensuring delivery of adequate,
value of money changes with time and as a result, equitable and sustainable water, sanitation, and
expenditures made at different times are not equal. hygiene services to a specific population (Fonseca et
This concept, referred to as the ‘time value of al., 2010). Growing interest in “green” building
money’, is the basis for life cycle cost analysis technologies that rely in part on the durability and
(LCCA) (Rahman and Vanier, 2004). Life-cycle sustainability of building materials to minimize
costing is a standard engineering economic approach environmental impacts had also led to LCCA
for choosing between alternative products or designs applications (Hoff, 2006).
that provide roughly equal service to the user. It Applying LCC to roofing investments uses
allows comparison between products having different the simple payback period to identify projects that
I. O. Ohijeagbon et al./LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

will be unusually profitable or unprofitable early in CF/E = fuel cost in naira per energy value, /kJ
their life. Suggested that the simple payback period hs = enthalpy of steam, kJ/kg
should not be used as the primary indicator to hw = enthalpy of boiler feed water, kJ/kg
evaluate a project, it is useful as a secondary measure ηB = overall boiler efficiency, fractional
to indicate the level of risk of an investment – a CNaira/litre = cost of fuel in naira/litre, /litre
quicker payback period is usually an indicator of less dfuel = relative density of fuel
risk (ATHENA Institute, 2007). LHV = Calorific value of fuel, kJ/kg
The present study investigates the Qf = Fuel use, kg/hr
relationships in the yearly and compounded cycle It was assumed that extra steam generated, X = 20%
costs; and the yearly and future fuel cost of an In principle, one should calculate the
industrial steam boiler over the service life of the individual cost components for the site-specific
boiler. conditions. In practice, it is usually sufficient to use
an approximation:
2 Method CG = C F (1 + 0.3) (6)
The first step, which has several components
to calculate the cost of generating steam from a The number 0.3 represents a typical value for the sum
boiler, comprises of the fuel cost (CF); raw water of all the cost components that may be incurred in
oil- and gas-fired facilities.
supply cost (CW); boiler feed water treatment cost-
The operating cost per annum is given by:
including clarification, softening, demineralization
(CBFW); feed water pumping power cost (CP); CO / annim = (1 + X ) × Q f × CG × Op Hrs (7)
combustion air fan power cost (CA); sewer charges The generating cost per annum is given by:
for boiler blowdown cost (CB); ash disposal cost CO / annum
(CD); environmental emissions control cost (CE) and CG / annum = = CG × Q f × OpHrs (8)
(1 + X )
maintenance materials and labour cost (CM) (U.S.
DOE, 2003). It can be deduced from equation (6) that the cost of
The total variable cost of raising steam, CG, fuel per annum is given by:
is the sum of all these individual contributions, C
C F / annum = G / annum (9)
expressed as naira per kilogram ( /Kg) of steam (1 + 0.3)
generated: Life cycle cost analysis (LCCA) is a process
CG = C F + CW + CBFW + CP + C A + CB + C D + C E + CM (1) for evaluating the total economic cost of an asset by
If the operating cost of a boiler is CO per analyzing initial costs and discounted future
hour and the process requires Qf kg/hr of steam. To expenditures, such as maintenance, repair and
deliver this quantity of steam, it is necessary to renewal costs, and user and social costs over the
actually generate (1+X) Qf kg/hr of steam, where X is service life of the asset (Rahman and Vanier, 2004).
a factor typically ranging from 5 to 20%. Hence, two The LCCA of a facility can be represented
distinct equations to determine the cost of steam are by the following expression (Jekayinfa et al., 2005):
as follows: LCC = Cic + Ce + Co + C m + Cd (10)
CO (2) where,
Generating cost, C ( N / kg ) =
G
(1 + X ) × Q f LCC = life cycle cost
CO
Cic = initial investment cost
Consumptio n cost, C C ( N / kg ) = (3)
Ce = energy cost
Qf
Co = operational (labour) cost
Equation (2) is used when we are interested in Cm = maintenance and repair cost
making the generation system more efficient. Cd = disposal cost
Equation (3) is used when we are interested in A comparison of equation (1) and (10)
determining the true cost of process operation and shows that energy (Ce) cost, operational (labour) cost
when we are evaluating energy conservation projects. (Co) and maintenance and repair cost (Cm) in the life
Fuel cost is usually the dominant cycle cost (LCC) are included in the cost of raising
component, accounting for as much as 90% of the steam (CG). Hence, equation (10) of the LCC may be
total. It is given by: re-written as;
C F = C F / E × ( hs − hw ) × η B (4) C L = C I + CG / a + C D (11)
1 1 (5) where,
C F / E = C Naira / litre × ×
d fuel LHV CL = CLCC
where, CI = Cic = initial investment cost
CF = fuel cost, /kg CG/a = CG/annum = generating cost per annum

92
I. O. Ohijeagbon et al./LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

CD = Cd = disposal cost RUSD/NGN = exchange rate of 1 USD to NGN = 152.55


The future value of the steam boiler at any (@ 24 January 2011)
particular year t can be determined by a cash flow Specific gravity, SGLPFO = 0.943
model which illustrates the effect of compounding of Calorific value of fuel, LHVLPFO = 40,515.15 kJ/kg
discount payments which is given by the expression Fuel use, Qf = 754 kg/hr
below (Thumann and Mehta, 2001; Rahman and It was assumed that X = 20%
Vanier, 2004): Estimated operating hours OpHrs = 4,186 hr/yr
n Hence,
C f = CT × ∑ (1 + id ) t (12)
80 1 1
t =0 CF / E = × × = 1.3726 × 10 − 5 S/ / kJ
where, 152.55 0.943 40,515.15
Cf = future value of LCC C F = 1.3726×10−5 × (2,778.07 − 431.90) × 0.6456 = S/ 0.0208 (3.172N / kg )
CT = present value of LCC CG = 0.0208 × (1 + 0.3) = 0.02704 S/ kg (4.125 N kg )
t = the reference year in which the CL was occurring
The operating cost per annum is given by:
id = annual depreciation rate
n = length of analysed period CO / annim = (1 + X ) × Q f × CG × Op Hrs
The value of CT can be expressed by (Rahman and ∴ CO / annim = (1 + 0.2) × 754 × 0.02704 × 4,186
Vanier, 2004): = 102,413.81 S/ / yr (15,623,226.00 N / yr )
CT = C L − SV (13)
The generating cost per annum is given by:
where, SV = salvage value, that is, the estimated value CO / annum
of the boiler at the end of its useful life. CG / annum = = CG × Q f × OpHrs
The annual depreciation of a fixed asset (1 + X )
without a salvage value can be determined by ∴ CG / annum = 0.02704 × 754 × 4,186
straight-lined depreciation method (Thumann and = 85,344.84 S/ / yr (13,019,355.00 N / yr )
Mehta, 2001; SLDM, 2011): The consumption cost per annum is given by:
Cost C I (14) CC / annum = CO / annum = 102,413.81 S/ / yr (15,623,226.00 N / yr )
A =
d =
Life n
It can be deduced from equation (6) that the cost of
where, Ad = annual depreciation, by implication, the
fuel per annum is given by:
book value of the asset would be zero at the end of n
years. Hence, the annual depreciation rate can be CG / annum
C F / annum = (17)
estimated by the following expression, (1 + 0.3)
A 1 (15) 85,344.84
id = d = C F / annum =
CI n (1 + 0.3)
Assuming disposal cost, CD = SV, then, from equation
= 65,649.88 S/ / yr (10,014,888.46 N / yr )
(11) and (13),
(16) The average life expectancy of a fire tube
CT = C I + CG / a
boiler is 30 years (CleaverBrooks, 2010; Bryan
0<t ≤n Boilers, 2008; VHA Directive, 2008; ETSAP, 2010).
The annual depreciation rate was estimated at n = 30 The initial investment cost (unit and installation cost)
years was estimated as $30,000.00 ( 4,576,500.00)
1 1 (Devotion, 2011; ETSAP, 2010).
∴ id = = = 0.0333 or 3.33% With:
n 30
CI = $ 30,000.00 ( 4,576,500.00)
3 Analysis CG/a = 85,344.84 $/yr (13,019,355.00 /yr)
The following data outlined below were ∴ CT = C I + CG / a = S/ 115,344.84 ( N 17,595,855.34)
used in the analytical computations of the simulation 0<t ≤n
process (Ohijeagbon, 2011). The annual depreciation rate was estimated at n = 30
CF = fuel cost, $ years
CF/E = fuel cost in dollars per energy value, $/kJ
1 1
hs = enthalpy of steam = 2,778.07 kJ/kg ∴ id = = = 0.0333 or 3.33%
hw = enthalpy of boiler feed water = 431.90 kJ/kg n 30
ηB = overall boiler efficiency, fractional = 0.6456 Assuming cost of fuel per annum is at an
CNGN/litre = cost of fuel in naira/litre = 80/litre (In inflation rate of 1%, and 3% respectively, hence, the
Nigeria @ 11 January 2011) future value of fuel can be estimated as follows:

93
I. O. Ohijeagbon et al./LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

n
Cf /F = C F / annum × ∑ (1 + i f ) t (18) Table 1: Yearly and compounded cycle costs at
t =0 specific intervals
Yearly cycle cost Compounded LCC
where, Year
USD NGN USD NGN
Cf/F = future value of fuel 1 111,503.86 17,009,913.36 226,848.70 34,605,768.70
if = inflation rate = 1%, and 3% 5 97,377.08 14,854,874.12 636,949.35 97,166,622.58
10 82,208.24 12,540,867.20 1,077,301.30 164,342,312.98
15 69,402.31 10,587,322.97 1,449,057.75 221,053,760.38
4 Results and discussions 20 58,591.22 8,938,090.65 1,762,904.13 268,931,024.42
The yearly and compounded cycle and 25 49,464.22 7,545,766.25 2,027,861.31 309,350,243.41
30 41,758.97 6,370,330.15 2,251,544.99 343,473,188.75
future fuel costs of an LPFO utilized steam boiler at
specific time intervals of 5 years are presented in
Figure 1 shows the yearly and compounded cycle
Table 1and Table 2 respectively. The detail-yearly
costs of LPFO utilized steam boiler in Nigerian naira
values of the yearly and compounded cycle and
(NGN), the equivalent values in US dollars (USD)
future fuel costs throughout the entire life of the
are presented in Table 1. From Table 1 and Figure 1,
steam boiler are shown in Figure 1, while the
the yearly cycle cost decreased steadily from about
graphical representations of the yearly and
17 million to 6.37 million ($ 111,503.86 to $
compounded cycle and future fuel costs at specific
41,758.97) in the first year to its expiration time of 30
time intervals are shown in Figure 2 and Figure 3
years. This accounted for a decrease of 62.53% at a
respectively.
depreciation rate of 3.33% throughout the lifespan of
the boiler.

Table 2: Yearly and compounded future fuel costs at specific intervals


Yearly future fuel cost Compounded future fuel cost
Year Inflation rate = 1% Inflation rate = 3% Inflation rate = 1% Inflation rate = 3%
USD NGN USD NGN USD NGN USD NGN
1 66,306.38 10,115,037.34 67,619.38 10,315,335.11 131,956.00 20,129,926.00 133,269.00 20,330,224.00
5 68,998.68 10,525,748.42 76,106.20 11,610,000.55 403,879.00 61,611,745.00 424,650.00 64,780,404.00
10 72518.31 11,062,667.38 88,227.95 13,459,172.64 759,361.00 115,840,559.00 840,830.00 128,268,645.00
15 76,217.47 11,626,974.59 102,280.40 15,602,869.90 1,132,977.00 172,835,588.00 1,323,297.00 201,868,918.00
20 80,105.33 12,220,067.15 118,571.00 18,088,002.56 1,525,650.00 232,737,936.00 1,882,608.00 287,191,806.00
25 84,191.51 12,843,413.39 137,456.30 20,968,952.43 1,938,354.00 295,695,906.00 2,531,003.00 386,104,418.00
30 88,486.12 13,498,556.55 159,349.50 24,308,762.91 2,372,110.00 361,865,365.00 3,282,670.00 500,771,245.00

The compounded life cycle cost (LCC) increased compounded LCC was 89.93% at a depreciation rate
from 34.6 million 343.47 million ($ of 3.33% from the first year throughout the lifespan
226,848.70 to $ 2.25 million). The increase in the of the boiler.
The yearly future fuel cost and compounded 1% inflation rate at the 18th and 27th year as shown in
future fuel cost respectively investigated at 1% and Figure 1 and Figure 3 respectively.
3% inflation rate are shown in Table 2, Figure 2 and Since the average life expectancy of a fire
Figure 3. The yearly future fuel cost at 1% and 3% tube boiler is 30 years (CleaverBrooks, 2010; Bryan
intersects the yearly cycle cost at about the 13th and Boilers, 2008; VHA Directive, 2008; ETSAP, 2010),
9th year as shown in Figure 1 and Figure 2 it would make for good economic and technical
respectively. That is, the yearly future fuel cost will judgement to replace the boiler once the future fuel
quickly attain and surpass the yearly cycle cost at 3% cost exceeds the compounded LCC of the boiler due
inflation rate compared with the yearly future fuel to reduced boiler performance with age.
cost of 1% inflation rate. Similarly, the compounded
future fuel cost will attain and surpass the
compounded LCC faster at 3% inflation rate
compared with the compounded future fuel cost of

94
I. O. Ohijeagbon et al./LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

The yearly future fuel cost attains and


surpass the yearly cycle cost at 3% inflation rate
compared with the yearly future fuel cost of 1%
inflation rate. Similarly, the compounded future fuel
cost attains and surpass the compounded LCC faster
at 3% inflation rate compared with the compounded
future fuel cost of 1% inflation rate. Therefore, the
rate of inflation of fuel cost was responsible for the
break-even period in the life cycle cost of steam
boiler operation.

References
ATHENA Institute (2007), Applying Life Cycle
Costing (LCC) to Roofing Investments: A
Guide to Using Green Roofs for Healthy
Cities GreenSave Calculator,
www.greenroofs.org
Bryan Boilers (2008), Boiler Comparison Guide,
Bryan Steam LLC, USA.
CleaverBrooks (2010), High Efficiency, Low
Emissions Wet-Back/Dry-Back Fire tube
Boilers, Cleaver-Brooks, Inc, USA.
Devotion (2011), Guangzhou Devotion Thermal
Facility Co., Ltd. [online], [Accessed 27th
January 2011], http://boiler-
manufacturer.en.made-in-china.com
ETSAP (Energy Technology Systems Analysis
Programme) (2010), Industrial Combustion
Boilers, IEA ETSAP-Technology Brief 101-
May 2010, www.etsap.org
Fonseca, C., Franceys, R., Batchelor, C., McIntyre,
P., Klutse, A., Komives, K., Moriarty, P.,
Naafs, A., Nyarko, K., Pezon, C., Potter, A.,
Reddy, R., and Snehalatha, M. (2010),
IRCInternational Water and Sanitation
Centre.
Hoff, J (2006), Equivalent Uniform Annual Cost: A
New Approach to Roof Life Cycle Analysis,
RCI 21st International Convention and
Trade Show in Phoenix, Arizona, in March
2006.
Jekayinfa, S. O., Adebiyi, K. A., Waheed, M. A. and
Owolabi, O. O. (2005), Appraisal of Farm
5 Conclusion tractor maintenance Practices and Costs in
The LCCA of an LPFO operated steam Nigeria, Journal of Quality in Maintenance
boiler reveals that the yearly cycle cost decreased engineering, Vol. 11 (2), pp152-168.
steadily from about 17 million to 6.37 million ($ Lutz, J., Lekov, A., Chan, P., Whitehead, C. D.,
111,503.86 to $ 41,758.97) in the first year to its Meyers, S. and McMahon (2006), Life-
expiration time of 30 years. This accounted for a Cycle Cost Analysis of Energy Efficiency
decrease of 62.53% at a depreciation rate of 3.33% Design Options for Residential Furnaces and
throughout the lifespan of the boiler. The Boilers, Energy, Vol. 31, pp311-329.
compounded life cycle cost (LCC) increased from NCHRP (National Cooperative Highway Research
34.6 million to 343.47 million ($ 226,848.70 to $ Program) (2003), Life-Cycle Cost Analysis
2.25 million). The increase in the compounded LCC for Bridges, NCHRP Report, Project 12-43,
was 89.93% at a depreciation rate of 3.33% from the Transportation Research Board,
first year throughout the lifespan of the boiler. Washington, D.C.

95
I. O. Ohijeagbon et al./LAUTECH Journal of Engineering and Technology 6(2) 2011: 91 – 96

Oeveren, K. and Wilks, M. (2009), Life Cycle Department of Mechanical Engineering,


Costing Qualification document - Rev 3, Ladoke Akintola University of Technology,
KEMA Consulting. Ogbomoso, Nigeria.
Ohijeagbon, I. O. (2011), Life Cycle Energetic Rahman, S. and Vanier, D. J. (2004), Life Cycle Cost
Studies of Steam Boilers Operation in Analysis as a Decision Support Tool for
Selected Production Industries in Nigeria, Managing Municipal Infrastructure,
Post-data Thesis for Ph.D. Research Degree, National Research Council Canada (NRCC).
SLDM (Straight Line Depreciation Method) (2011), U.S. Department of Energy (DOE) (2003), How to
One Squared Productions [online]. Calculate the True Cost of Steam, Industrial
[Accessed 26th January 2011], Technologies Program Energy Efficiency
www.assetaide.com/depreciation/sl-sv.html and Renewable Energy, U.S. Department
Thumann, A. and Mehta, D. P. (2001), Hand Book of of Energy Washington, DC.
Energy Engineering, the Fairmont Press VHA Directive (2008). Boiler Plant Operations,
Inc., 700 Indian Trail, 5th Ed. Department of Veterans Affairs, Veterans
Health Administration, Washington, DC,
USA.

96