You are on page 1of 14

KAPRPT King Abdulaziz Project For Riyadh

PK2 | Line 3 BILL OF QUANTITY


RFQ. # DATE : 8-Mar-18
02.41 4.3.1_Road Works, Section 02A | Preamble REVISION : 01 (01-Aug-18)

ITEM ITEM DESCRIPTION

PREAMBLE

P.01 The quantities identified in the Bill of Quantities for the works to be carried out under this
contract have been measured based on the Tender Drawings. The Bill of Quantities herein,
including all notes and instructions, form an integral part of the Tender Documents.
However, the descriptions contained in the Bill of Quantities for each item are not
necessarily complete. The Subcontractor is referred to the Conditions of the Subcontract
and other Documents, Specifications, and Drawings as well as relevant Standards and Codes
of Practice for further information as no claim or variation will be considered on account of
the Contractor's failure to do so.
P.02 The Subcontractor is cautioned to familiarize himself with the full content of other Tender
Documents including the General Conditions of Subcontracts, Contract Drawings and
Specifications or any other information that can be reasonably inferred from any of them
and all obligations contained in the documents shall be included in the item rates and
prices.
P.03 The whole of the quantities shall be treated as approximate only and are given to provide
common basis for tendering which shall be subject to rechecking by the Subcontractor. The
basis of payment will be made based on the quantities shown & no extra amount or
quantity will be given whatsoever.
P.04 Drawings, Specifications and Bill of Quantities and all other documents are complementary
and if any item is included in any of them, it shall be deemed included in all.
P.05 Amendment shall not be made to this Bill of Quantities without the authority, in writing of
the Main Contractor. Any insertion of additional items or changes in description and
quantity will not be accepted.
P.06 The Contractor shall not use the Bill of Quantities as the basis for a construction program or
for the purpose of ordering materials or arranging subcontracts. The references for these
activities shall be the drawings, specifications and instructions issued by the Main
Contractor.
P.07 Units of Measurement
The following units of measurement and abbreviations have been used where ever
applicable.
Unit Abbreviation
Cubic meter Cu.m, M3
Lump Sum L.S
Linear Meter L.M
Meter M, or m
Millimetre mm
Number No., no. or EA
Square meter Sq.m, or M2
Tonne Ton

P.08 Abbreviation
The following abbreviations have been used where ever applicable.
Diameter Dia., , or dia.,
Drawing Dwg.
Ductile Iron DI
Low Voltage LV
Minimum Min., or min.
Not Applicable N.A
Polyvinyl Chloride PVC
Polyethylene PE

P.09 Continuation of Abbreviation


Quantity Qty
Reference Ref.
Stainless Steel SS
Specification Specs.
Thickness Thk.
Unplasticised Polyvinyl Chloride uPVC
Tonne Ton
P.10 Method of Measurement
The Bill of Quantities have been measured in accordance with the Rules of the Civil
Engineering Standard amended to suit to local conditions and practices.

Asphalt Pavement
Prime coat, tack coat, wearing course and binder course is considered as a complete system
Asphalt concrete paving including binder & wearing courses etc. are given in cubic meters.
Work deemed to include:
-Spreading and compaction
-Surface preparation and protective measures to avoid staining or damage
-Blotting of prime coat when required and cleaning of stains and repairing damage caused
by equipment.

Pavement Markings
Each kind of Marking is given separately. Pavement marking lines and painted pavement
markings are given in Number of each type or each (EA). Retroreflective and Ceramic
Raised Pavement Markers shall be measured by the unit EA based on the number required
by the drawings or ordered by the Company's Representative for each type of markers of
each authorized, completed and accepted by the Company's Representative.
For Pavement Ceramic raised markers and all related furniture, work deemed to include all
required materials, equipment, tools, labor, surface preparation, site pre-marking, and all
other items necessary for the proper completion of the Work as per drawings and
specifications.

P.11 All measurements are net and the rates shall include for all laps, waste, working space and
trade or traditional allowances.

P.12 Rates and Prices shall be in Saudi Riyals


P.13 Prices & Rates
The prices and rates shall be comprehensive and must include for complying in all respects
with the Bill of Quantities, Instruction to Tenderers, General Conditions of Subcontract,
Specifications and Drawings and for all matters and things necessary for the proper
construction, completion, and maintenance of the whole of the Works. No claims for
additional payment will be allowed for any error or misunderstanding by the Contractor of
the work involved.

P.14 In case of discrepancies between the prices or rates quoted and total amount for any item in
the Bill of Quantities, the unit rate or price shall be binding.

P.15 The Subcontractor is to ensure that identical items occurring in separate bills are not priced
at different rates.

P.16 A price or rate is to be entered against each item in the Bill of Quantities and any item left
unpriced shall be deemed to have been included for elsewhere in the Bill of Quantities and
hence the rate for the item shall be taken as “NIL” (even if not so noted).

P.17 Where fix or install only items are specified, the rate shall be deemed to include for taking
delivery, storing and installation of goods or materials in works where appropriate.

P.18 The rates and sums inserted in the Bill of Quantities are deemed to include for the following:
i) Labour and all costs in connection herewith.
ii) Materials, goods and all costs in connection therewith (e.g. carriage freightage delivery,
unloading, storing, returning, packing, handling, hoisting or lowering, replacing work,
goods or materials damaged, broken, lost or stolen until the issue of a Certificate of
Completion).
iii) Fittings and fixing materials or goods in position.
iv) Plant.
v) Land required for tips and stock piles including all costs for obtaining any necessary
licenses and approvals.
vi) Allowance for phasing requirements of works, effect on programming of the works of all
traffic diversions and construction activity associated with diversion or installation of
services.
vii) For taking measures for the support and full protection of pipes, cables and other
apparatus required during the progress of the Works as required by Service Authority &
Main Contractor.
viii) Overhead charges and profit. Overhead shall include for all costs in connection with
Letter of Credit, bank charges, interest charges and insurance after the material come
under the control of the Contractor
ix) Preparation and supply of shop drawings.
x) The Tenderer is to allow in his rates for the production of all shop drawings, working
drawings, as built drawings and operations and maintenance instructions called for in the
Specifications.

Specific Items

P.19 Road Works


The Unit Prices for Road Works, include all operation costs for execution, completion and
maintenance of the various items of the Road works finished & operational road completely
in every respect till the final acceptance by relevant Authorities as specified in the Contract
Documents.

MRL3
DATE : 8-Mar-18
4.3.2_Roads Works, Sections 02A | BOQ REVISION : 01 (01-Aug-18)

SUPPLY TOTAL RATE TOTAL SUPPLY & TOTAL


ITEM DESCRIPTION UNIT QTY
RATE SUPPLY INSTALL INSTALLATION INSTALLATION AMOUNT (SAR.)

100% DD, Roadworks, REv. 01, TXN-012964A, June 06, 2018


Road Pavement Reports M-ANM-P2-SBM-009448

DIVISION 02 - SITE CONSTRUCTION

REMOVAL OF EXISTING LIGHT POLES FOUNDATION

Demolition of Existing Light Poles foundation and chambers / other


concrete structures (wherever required) includes all necessary
machinery, labour for dismantling, complete as instructed by
engineer in charge including Transportation & Disposing of the same
02260-01
debris to the authorized location by authority from the point of No. 0.00
(Optional)
demolition. The Subcontractor will take all the necessary steps to
protect the surrounding structure & environment. The excavated
area to be backfilled, compacted & tested as per attached Technical
Specifications.

ADJUSTMENT OF EXISITING MANHOLES LEVEL

Adjustment of level of existing Manholes (Sewer, Water, Telephone,


Electrical, Septic Tanks, Storm water, etc.) in any diameter or size to
the required level, to suit the new situation. Replacing covers,
frames, rings if defected and all materials and work required to
complete the task. The work includes decreasing / increasing the
height of manholes by demolishing the extra parts or increasing the
height by supplying & installing precast concrete ring, otherwise
casting of concrete may be used, also include( if need) cast iron cover
and all required materials. The work also includes cleaning of
existing manholes.

02260-02
Size Less than or equal to 200 mm No. 12.00
(Optional)
02260-03
Size 200 mm - 1000 mm No. 25.00
(Optional)
02260-04
Size 1000 mm - 2000 mm No. 25.00
(Optional)
02260-05
Size greater that 2000 mm No. 12.00
(Optional)
Supply & installation of Ducts, Sleeves & trenches ec. for any other
02260-06
necessary future utilities and relocation of utilities if any found LS 1.00
(Optional)
under the construction area (Ref. to Note "H" at end of BOQ)

SECTION 02741 - BITUMINOUS CONCRETE PAVEMENT

Note: Rolling shall continue until the entire thickness of each Base
layer is thoroughly and uniformly compacted to 100%, as per
AASHTO T-180, of maximum density through the full depth of the
layer.

MILLING & FILLING


Milling & Filling of the structural pavement, treatment including
the removal of the existing surface layer (Asphalt pavement specific
thickness) with a milling machine and transporting the milled
material to disposal site & Supply & Installation of New asphalt to
replace the milled location. Activities for Mill & Fill includes :
(a). For Mill & Fill Grade Activity, Fill ≤ 10 Cm:
2 Cm (minimum) milling of existing Asphalt surface, Add asphalt
layers (5-cm thick wearing course, variable thickness of binder
course) to reach the new project level.
(b). Mill & Fill Grade Activity 10 Cm < Fill ≤ 20 Cm:
2-cm milling of the existing asphalt surface, 5 Cm thick Wearing
Course, 10 Cm thick Binder Course over a variable thickness
Bituminous base course to reach the new project level.
(c) Mill & Fill Grade Activity Fill > 20 Cm:
Remove existing asphalt, Adjust levels with new base course,
Reconstruct the pavement to the required design level with min. new
asphalt layers of 15 cm (5 cm wearing course and 10 cm binder
course).
All relevant Base layers compacted to 100%, as per AASHTO T-180, of
maximum density through the full depth of the each relevant layer,
with all measures & materials required for proper execution,
complete as per AMANA / MOT / ADA acceptable Standards, attached
Road Pavement Reports, Technical Specification, 100 % Design
Drawings and Engineers instructions at site.

MILL & FILL GRADE ACTIVITY 0 < FILL ≤ 10


02741-01
2 Cm (minimum) Milling of Existing Asphalt Surface M2 2,805.00
REv.01
02741-02
Variable Thickness of New Binder Course Layer M3 134.00
REv.01
02741-03
5 Cm New Wearing Course Layer M2 2,805.00
REv.01

MILL & FILL GRADE ACTIVITY 10 CM < FILL ≤ 20 CM:


02741-04
2 Cm Milling of the Existing Asphalt Surface M2 8,085.00
REv.01
02741-05
Variable Thickness of New Bituminous Base Course Layer M2 8,085.00
REv.01
02741-06
10 Cm New Binder Course Layer M2 8,085.00
REv.01
02741-07
5 Cm New Wearing Course Layer M2 8,085.00
REv.01

MILL & FILL GRADE ACTIVITY FILL > 20 CM:


02741-08
Remove Existing Asphalt Layer M3 658.00
REv.01
02741-09
Adjust Levels with New Base Course Layer M3 986.00
REv.01
02741-10
10 Cm Binder Course New Layer M2 3,713.00
REv.01
02741-11
5 Cm Wearing Course New Layer M2 3,713.00
REv.01

CRACK SEALING
Crack Sealing of the structural pavement, treatment including the
removal of the existing surface layer (Asphalt pavement specific
thickness) with a milling machine and transporting the milled
material to disposal site, Supply & Installation of New asphalt to
replace the milled location & Cracks Sealing (sealing asphalt to the
cracks). Activities includes :
This is one of the maintenance methods and its used to fill several
types of cracks after selecting the appropriate filler, hot air, injection
tool and brush. In this activity, the asphalt surface after milling, will
receive crack sealing then the new asphalt layers will be added to
match the profile grade.
All relevant Base layers compacted to 100%, as per AASHTO T-180, of
maximum density through the full depth of the each relevant layer,
with all measures & materials required for proper execution,
complete as per AMANA / MOT / ADA acceptable Standards, attached
Road Pavement Reports, Technical Specification, 100 % Design
Drawings and Engineers instructions at site.

02741-12
Milling of the Existing Asphalt Surface M2 12,210.00
REv.01
02741-13
Crack Sealing M2 12,210.00
REv.01
02741-14
10 Cm (variable) Binder Course New Layer M2 12,210.00
REv.01
02741-15
5 Cm (variable) Wearing Course New Layer M2 12,210.00
REv.01

DEEP PATCHING

Deep Patching of the structural pavement, treatment including of


the existing asphalt layers (wearing and binder courses) are
removed, compaction of the existing base course and disposal the
removed material to site and Supply & Installation of New asphalt
in the patching area.
(a). Deep Patching Activity in Fill includes :
Remove AC (and part of ABC if required) to minimum depth of 15 cm
below road design level, Re-compact the existing aggregate base
course, Reconstruct the pavement to the required design level with
min. new asphalt layers of 15 cm (5 cm wearing course and mini. 10
cm binder course)
(b). For Deep Patching Activity in Cut includes :
Remove AC (and part of ABC if required) to minimum depth of 15 cm
below road design level, Re-compact the existing aggregate base
course, Reconstruct the pavement to the required design level with
min. new asphalt layers of 15 cm (5 cm wearing course and min. 10 cm
binder course).
All relevant Base layers compacted to 100%, as per AASHTO T-180, of
maximum density through the full depth of the each relevant layer,
with all measures & materials required for proper execution,
complete as per AMANA / MOT / ADA acceptable Standards, attached
Road Pavement Reports, Technical Specification, 100 % Design
Drawings and Engineers instructions at site.

DEEP PATCHING IN FILL:


02741-16
Remove Existing Asphalt Layers (and part of ABC if required) M3 1,646.00
REv.01
02741-17
Re-compacting of Existing Aggregate Base Course M2 10,973.00
REv.01
02741-18
Variable Thickness of New Base Course Layer M3 832.00
REv.01
02741-19
10 Cm Binder Course New Layer M2 10,973.00
REv.01
02741-20
5 Cm Wearing Course New Layer M2 10,973.00
REv.01
DEEP PATCHING IN CUT:

02741-21
Remove Existing Asphalt Layers (and part of ABC if required) M3 558.00
REv.01
02741-22
Re-compacting of Existing Aggregate Base Course M2 2,888.00
REv.01
02741-23
10 Cm Binder Course New Layer M2 2,888.00
REv.01
02741-24
5 Cm Wearing Course New Layer M2 2,888.00
REv.01

RECONSTRUCTION OF PAVEMENT

Reconstruction for the structural pavement, treatment including


the removal of Asphalt Concrete Aggregate Base Course, disposal the
removed material to site, Re-compacting the existing subgrade,
Reconstruct the pavement to the required level with supply &
Installation of new Asphalt Layers of 15 Cm (5 Cm Wearing Course
& 10 Cm Binder Course), minimum 34 Cm Aggregate Base Course for
CBR=9 and minimum 15 Cm Aggregate Base Course for CBR ≥ 50.
All relevant Base layers compacted to 100%, as per AASHTO T-180, of
maximum density through the full depth of the each relevant layer,
with all measures & materials required for proper execution,
complete as per AMANA / MOT / ADA acceptable Standards, attached
Road Pavement Reports, Technical Specification, 100 % Design
Drawings and Engineers instructions at site.

RECONSTRUCTION OVER SUBGRADE WITH CBR ≥ 9

02741-25 Remove Existing Pavement Layers (asphalt AC and aggregate base


M3 14,683.00
REv.01 course ABC)
02741-26
New Aggregate Base Course Layer min. 34 Cm M3 15,372.00
REv.01
02741-27
Re-compacting the Existing Subgrade M2 18,810.00
REv.01
02741-28
10 Cm Binder Course New Layer M2 18,810.00
REv.01
02741-29
5 Cm Wearing Course New Layer M2 18,810.00
REv.01

RECONSTRUCTION OVER SUBGRADE WITH CBR ≥ 50

02741-30 Remove Existing Pavement Layers (Asphalt AC & Aggregate Base


M3 5,359.00
REv.01 Course)
02741-31
New Aggregate Base Course Layer min. 15 Cm M3 6,105.00
REv.01
02741-32
Re-compacting the Existing Subgrade M2 11,220.00
REv.01
02741-33
10 Cm Binder Course New Layer M2 11,220.00
REv.01
02741-34
5 Cm Wearing Course New Layer M2 11,220.00
REv.01

MINOR CUT
02741-35
Milling of the Existing Asphalt Surface M2 3,300.00
REv.01
02741-36
10 Cm Binder Course New Layer M2 3,300.00
REv.01
02741-37
5 Cm Wearing Course New Layer M2 3,300.00
REv.01

SECTION 02763 - PAINTED TRAFFIC LINES AND MARKING


BROKEN LINE ON FREEWAY > 65 Km/h (D-01)

Supply & Installation of Broken Line on Freeway > 65km/h (White


line or Yellow line) Type D-01, comprising of Road Markers Non
Reflective white Ceramic Dia. 100 mm and 19 mm thick with c/c
distance 1500 mm & Reflective White Ceramic 100 x 100 x 19 mm
thick with c/c distance 18000 mm, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-01 Non Reflective White Ceramic of Ø 100 mm No. 4,000.00


02763-02
Reflective White Ceramic of 100 x 100 x 19 mm No. 2,400.00
REv.01

EDGE LINE (Yellow line) (D-03)

Supply & Installation of Edge Line (Yellow line) Type D-03,


comprising of Road Markers Reflective Yellow Ceramic dia 100 mm
and 19 mm thick with c/c distance 1500 mm, as per Detailed Drawing
No. M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-03
Reflective Yellow Ceramic of Ø 100 mm No. 11,414.00
REv.01

NO PASSING (White line) (D-04)

Supply & Installation of No Passing (White line) Type D-04,


comprising of Road Markers Non Reflective White Ceramic dia 100
mm and 19 mm thick with c/c distance 1000 mm, as per Detailed
Drawing No. M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-04
Non Reflective White Ceramic of Ø 100 mm No. 2,139.00
REv.01

WHITE STOP LINE (D-05)

Supply & Installation of White Stop Line Type D-05, comprising of


Road Markers Non Reflective White Ceramic dia 100 mm and 19 mm
thick with c/c distance 500 mm, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-05
Non Reflective White Ceramic of Ø 100 mm No. 1,130.00
REv.01

TRANSVERSAL CROSSWALK (White line) (D-06)


Supply & Installation of Transversal Crosswalk (White line) Type
D-06, comprising of Road Markers Non Reflective White Ceramic dia
100 mm and 19 mm thick with c/c distance 500 mm, as per Detailed
Drawing No. M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-06
Non Reflective White Ceramic of Ø 100 mm No. 2,250.00
REv.01

COMBINATION ARROW (White line) (D-07)

Supply & Installation of Combination Arrow (White Line) Type


D-07, comprising of Road Markers Non Reflective White Ceramic dia
100 mm and 19 mm thick, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001 including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-07
Non Reflective White Ceramic of Ø 100 mm No. 2,625.00
REv.01

PERMANENT MARKING STRAIGHT ARROW (White line) (D-08)

Supply & Installation of Permanent Marking Straight Arrow (White


Line) Type D-08, comprising of Road Markers Non Reflective White
Ceramic dia 100 mm and 19 mm thick, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-08
Non Reflective White Ceramic of Ø 100 mm No. 5,429.00
REv.01

TURN LEFT / RIGHT ARROW (White line) (D-09)

Supply & Installation of Turn Left / Right Arrow (White Line) Type
D-09, comprising of Road Markers Non Reflective White Ceramic dia
100 mm and 19 mm thick, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-09
Non Reflective White Ceramic of Ø 100 mm No. 726.00
REv.01

COMBINATION LEFT & RIGHT ARROW (White line) (D-10)


Supply & Installation of Combination Left & Right Arrow (White
Line) Type D-10, comprising of Road Markers Non Reflective White
Ceramic dia 100 mm and 19 mm thick, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-10
Non Reflective White Ceramic of Ø 100 mm No. 71.00
REv.01

PARALLEL PARKING (White line) (D-18)

Supply & Installation of Parallel Parking (White Line) Type D-18,


comprising of Road Markers Non Reflective White Ceramic dia 100
mm and 19 mm thick with c/c distance 500 mm, as per Detailed
Drawing No. M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-11
Non Reflective White Ceramic of Ø 100 mm No. 1,030.00
REv.01

HATCH MARKING (White line) (D-20)

Supply & Installation of Hatch Marking (White Line) Type D-20,


comprising of Road Markers Non Reflective White Ceramic dia 100
mm and 19 mm thick with c/c distance 500 mm, as per Detailed
Drawing No. M-ANM-300000-CHLM-EDR-200001 &
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

02763-12
Non Reflective White Ceramic of Ø 100 mm No. 440.00
REv.01

BERLIN SPEED CUSHION

Supply & Installation of Berlin Speed Cushion Size 3000 x 1800 mm


as per Detailed Drawing No. M-ANM-3C1VD1-CHLM-EDR-200001 &
02763-13 M-ANM-300000-CHBR-EDR-200003, including all necessary materials
No. 93.00
REv.01 & accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

TRAFFIC DELINEATORS

Supply & Installation of Traffic Delineators with 75mm Height,


Reflective area & installed at 150mm c/c as per Detailed Drawing No.
M-ANM-3C1VD1-CHLM-EDR-200001 &
02763-14
M-ANM-300000-CHBR-EDR-200003, including all necessary materials No. 5.00
REv.01
& accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.
SPEED HUMP
Supply & Installation of Speed Hump Size 4000 x 3300 mm per
Detailed Drawing No. M-ANM-300000-CHBR-EDR-200003 &
02763-15 M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
No. 12.00
REv.01 & accessories required for proper execution & fixing, complete in all
respect as per attached Technical Specification & Engineers
instructions at site.

PAINTING

TRANSVERSAL CROSSWALK (D-06)

Supply and Applying of white Thermoplastic Reflectorized Paint


(TRP) for Transversal Crosswalk White Line Type D-06 as per
Detailed Drawing No. M-ANM-300000-CHLM-EDR-200001 &
02763-16
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials M2 631.00
REv.01
& accessories required for proper execution & painting/Laying,
complete in all respect as per attached Technical Specification &
Engineers instructions at site.

DROP OFF PARKING AND TAXI RANK PAINTING (D-12)

Supply and Applying of Non Reflective Orange Path Thermoplastic


Painting Type D-12 for Drop Off Parking and Taxi Rank as per
Detailed Drawing No. M-ANM-300000-CHLM-EDR-200001 &
02763-17
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials No. 6.00
REv.01
& accessories required for proper execution & painting/Laying,
complete in all respect as per attached Technical Specification &
Engineers instructions at site.

MAINTENANCE PARKING (Orange path) (D-14)

Supply and Applying of Non Reflective Orange Path Thermoplastic


Painting Type D-14 for Orange Sidewalk Path Painting Maintenance
Parking, as per Detailed Drawing No.
02763-18 M-ANM-300000-CHLM-EDR-200001 &
No. 3.00
REv.01 M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & painting/Laying,
complete in all respect as per attached Technical Specification &
Engineers instructions at site.

BUS STOP PATH PAINTING (Orange path) (D-15)

Supply and Applying of Non Reflective Orange Path Thermoplastic


Painting Type D-15 for Bus Stop Path (English & Arabic both
languages), as per Detailed Drawing No.
02763-19 M-ANM-300000-CHLM-EDR-200001 &
No. 14.00
REv.01 M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials
& accessories required for proper execution & painting/Laying,
complete in all respect as per attached Technical Specification &
Engineers instructions at site.

DISABLED PARKING PAINTING (D-19)

Supply and Applying of Non Reflective Black Line Thermoplastic


Painting Type D-19 for Disabled Parking, as per Detailed Drawing No.
M-ANM-300000-CHLM-EDR-200001 &
02763-20
M-ANM-3C1VD1-CHLM-EDR-200001, including all necessary materials No. 21.00
REv.01
& accessories required for proper execution & painting/Laying,
complete in all respect as per attached Technical Specification &
Engineers instructions at site.
Note : For all the above relevant items, subcontractor scope includes
:
A. All Testing as per AMANA / ADA / MOT requirements and standard.
B. Handover of completed work to AMANA / ADA / MOT
C. Coordination with local authorities, to protect existing utilities.
Any damage to existing utility is the responsibility of the
subcontractor to repair at no cost to main Contractor.
D. All Engineering work to include shop drawing, material submittal,
As built and O & M (operation & Maintenance) manuals.
E. All relevant work includes connection to exiting network.
F. All relevant items testing cost shall be included in unit price.
G.Unit rates are deemed to include all ancillary scope to deliver a
complete & operational relevant system ready for handover to
relevant Authority.
H. The Supply & installation of Ducts, Sleeves & trenches ec. for any
other necessary future utilities and relocation of utilities if any found
under the construction area based upon the approved Shop
Drawings by subcontractor as per site condition.

MRL3 Total Amount for Supply & Installation for Roads Works, Sections 02A (3C2).
Total Total Supply & Installation
Supply Installation (SAR.)