Cost Estimate Class and

Accuracy
AACE International Recommended Practice No. 18R-97

PRESENTED BY
REZA ISMIRIADI

REZA ISMIRIADI 1
What we will learn?
Subject of Discussion

1 Understanding the Concepts of Classifying Project Cost Estimates

Fully defines and correlates the major characteristics used in classifying cost
2 estimates

Uses the maturity level of project definition deliverables as the primary characteristic
3 to categorize estimate classes

Provide the process industry definition deliverable maturity matrix


4 (specified on 18R-97)

Understanding the relationship design input data and design deliverable maturity to
5 the estimate accuracy and methodology used to produce the cost estimate (specified
on 18R-97)

REZA ISMIRIADI 2
Comparison of Cost Estimate Classification

Norwegian Project
AACE International Association of Cost American Society of
ANSI Standard AACE Mgmt Association
Recommended Engineers Professional
Z.94.2-1989 Pre-1972 NFP
Practice UK-ACE Estimators (ASPE)
(NACPE)
Increasing Project Definition

Order of Magnitude Order of Magnitude Concession Est.


Order of Magnitude
Class 5 Estimate Estimate Exploration Est. Level 1
Estimate
-30 / +50 -30 / +50
Feasibility Est.

Study Estimate Authorization


Class 4 Study Estimate
Class III Estimate Level 2
Budget Estimate - -20 / +30
15 / +30
Preliminary Master Control
Class 3 Budget Estimate Level 3
Estimate Estimate
Class II -10 / +10

Level 4
Class 2 Definitive Estimate
Definitive Estimate Definitive Estimate Current Control
-5 / +15 Class I -5 / +5 Estimate Level 5
Class 1 Detailed Estimate
Level 6

REZA ISMIRIADI 3
AACE’s Recommended Practice
Related Recommended Practice

▪ Cost Estimate Classification System (17R-97)


▪ Cost Estimate Classification System – As Applied in EPC for
The Process Industries (18R-97)
▪ Cost Estimate Classification System – As Applied in The
Mining and Mineral (47R-11)
▪ Cost Estimate Classification System – As Applied in Building
and General Construction (56R-08)
▪ Cost Estimate Classification System – As Applied in EPC
Hydropower (69R-12)

REZA ISMIRIADI 4
Variability in Accuracy Range for Cost Estimate Classification Matrix for Process
Process Industry Estimate Industries (AACE)

REZA ISMIRIADI 5
Class-5

Description: Estimating Methodology:


• Class 5 estimates are generally prepared based on very • cost/capacity curves and factors, scale of operations
limited information, and subsequently have wide factors, Lang factors, Hand factors, Chilton factors,
accuracy ranges Peters-Timmerhaus factors, Guthrie factors, and other
parametric and modeling techniques.

Maturity Level of Project Definition Deliverables:


Expected Accuracy Range:
• Key deliverable and target status: Block flow diagram
agreed by key stakeholders. 0% to 2% of full project • -20% to -50% on the low side, and +30% to +100% on
definition the high side

End Usage: Alternate Estimate Names, Terms, Expressions,


Synonyms:
• Strategic business planning purposes, such as but not
limited to market studies, assessment of initial viability, • Ratio, ballpark, blue sky, seat-of-pants, ROM, idea
evaluation of alternate schemes, project screening, study, prospect estimate, concession license estimate,
project location studies, evaluation of resource needs guesstimate, rule-of-thumb.
and budgeting, long-range capital planning, etc.

REZA ISMIRIADI 6
Class-4

Description: Estimating Methodology:


• Class 4 estimates are generally prepared based on • equipment factors, Lang factors, Hand factors, Chilton
limited information and subsequently have fairly wide factors, Peters-Timmerhaus factors, Guthrie factors, the
accuracy ranges. Miller method, gross unit costs/ratios, and other
parametric and modeling techniques.

Maturity Level of Project Definition Deliverables:


Expected Accuracy Range:
• Key deliverable and target status: Process flow
diagrams (PFDs) issued for design. 1% to 15% of full • -15% to -30% on the low side, and +20% to +50% on the
project definition high side

End Usage: Alternate Estimate Names, Terms, Expressions,


Synonyms:
• detailed strategic planning, business development,
project screening at more developed stages, alternative • Screening, top-down, feasibility (pre-feasibility for
scheme analysis, confirmation of economic and/or metals processes), authorization, factored, pre-design,
technical feasibility, and preliminary budget approval or pre-study
approval to proceed to next stage.

REZA ISMIRIADI 7
Class-3

Description: Estimating Methodology:


• Class 3 estimates are generally prepared to form the • involve more deterministic estimating methods than
basis for budget authorization, appropriation, and/or stochastic methods
funding

Expected Accuracy Range:


Maturity Level of Project Definition Deliverables:
• -10% to -20% on the low side, and +10% to +30% on the
• Key deliverable and target status: Piping and high side
instrumentation diagrams (P&IDs) issued for design.
10% to 40% of full project definition.
Alternate Estimate Names, Terms, Expressions,
Synonyms:
End Usage:
• Budget, scope, sanction, semi-detailed, authorization,
• to support full project funding requests, and become the preliminary control, concept study, feasibility (for metals
first of the project phase control estimates against processes) development, basic engineering phase
which all actual costs and resources will be monitored estimate, target estimate.
for variations to the budget

REZA ISMIRIADI 8
Class-2

Description: Estimating Methodology:


• Class 2 estimates are generally prepared to form a • involve a high degree of deterministic estimating
detailed contractor control baseline (and update the methods.
owner control baseline) against which all project work is
monitored in terms of cost and progress control. • For those areas of the project still undefined, an
assumed level of detail takeoff (forced detail) may be
developed to use as line items in the estimate instead of
relying on factoring methods.
Maturity Level of Project Definition Deliverables:
• Key deliverable and target status: All specifications and
datasheets complete including for instrumentation. 30% Expected Accuracy Range:
to 75% of full project definition.
• -5% to -15% on the low side, and +5% to +20% on the
high side
End Usage:
• Class 2 estimates are typically prepared as the detailed Alternate Estimate Names, Terms, Expressions,
contractor control baseline Synonyms:
• Detailed control, forced detail, execution phase, master
control, engineering, bid, tender, change order estimate

REZA ISMIRIADI 9
Class-1

Description: Estimating Methodology:


• Class 1 estimates are generally prepared for discrete • Class 1 estimates generally involve the highest degree of
parts or sections of the total project rather than deterministic estimating methods, and require a great
generating this level of detail for the entire project. amount of effort

Maturity Level of Project Definition Deliverables: Expected Accuracy Range:


• Key deliverable and target status: All deliverables in the • -3% to -10% on the low side, and +3% to +15% on the
maturity matrix complete. 65% to 100% of full project high side
definition.

Alternate Estimate Names, Terms, Expressions,


End Usage: Synonyms:
• to support change management process • Full detail, release, fall-out, tender, firm price, bottoms-
up, final, detailed control, forced detail, execution phase,
• to support vendor/contractor negotiations master control, fair price, definitive, change order
• for claim evaluations and dispute resolution estimate.

REZA ISMIRIADI 10
Estimate Input Checklist

REZA ISMIRIADI 11
Cost Estimate Methodology

• Conceptual
• End-Product Units Method
• Physical Dimensions Method
• Capacity Factored Method
• Ratio or Factor Method
• Parametric Method
• Etc.
• Deterministic (Detailed)

REZA ISMIRIADI 12
Estimate Accuracy

Estimate accuracy is also driven by:


▪ Level of non-familiar technology in the project.
▪ Complexity of the project.
▪ Quality of reference cost estimating data.
▪ Quality of assumptions used in preparing the estimate.
▪ Experience and skill level of the estimator.
▪ Estimating techniques employed.
▪ Time and level of effort budgeted to prepare the estimate

REZA ISMIRIADI 13