Find the critical path and the expected duration of the following project.
2
A(5)
C(11)
H(6)
B(7) 7
1 3 5
E(7) K(3)
I(5)
D(3)
4 8
6
G(12) J(8)
Question No 2:
A project has the following time schedule.
Activity Time(hours)
1-2 2
1-3 2
1-4 1
2-5 4
3-6 8
3-7 5
4-6 3
5-8 1
6-9 5
7-8 4
8-9 3
5 3
2 4
3 7 8 9
1
8
1
5
4 6
3
Find the critical path and the expected duration of the project.
Question No 4:
A small marketing project consists of the jobs as shown in the table below.
Activity 1-2 2-3 2-4 3-5 4-5 4-6 4-7 5-7 6-7 7-8
Duration 1 5 3 4 2 5 9 4 2 2