Recalling
Schedule Planning
Create
WBS
• WBS
Define
Activities
• Activities & Milestones Lists
Estimate &
Allocate Activity
Resources
• Activities Resource Estimates & Allocation
Sequence
Activities
• Network Diagram
Estimate
Durations
• Activities Durations Estimates
•
Develop (using Multiple Methods)
Schedule
• Schedule
MEhsanSaeed • Schedule Baseline 2
1
Schedule, Schedule Baseline & Project Schedule … 1/2
Planning Execution
Add actual
Approve Schedule
Develop (Baseline) the
Schedule • Schedule • Schedule Performance • Project
Schedule Data Schedule
Baseline
B
2
A C D E
ST END
3 5 4 6
MEhsanSaeed 3
Schedule (Pre-Baseline)
MEhsanSaeed
Schedule
Baseline
(Gray bars)
Project Schedule 4
2
Schedule Baseline vs Project Schedule … 1/2
Schedule Baseline Project Schedule
▪ Approved Version of the Schedule ▪ Schedule Model that tracks the
Model, comprising: Schedule Progress such as:
‒ Start & Finish Dates ‒ Actual Start & Finish Dates
‒ Sequencing & Logical Relationship ‒ Sequencing & Logical Relationship
(Dependencies) (Dependencies)
‒ Milestones ‒ Activities completed, activities in
progress, % completion of activities
‒ Hours spent
‒ Resource allocations
‒ etc
Cont’d ….
Schedule Model. A representation of the Plan for executing the Project’s activities
including durations, dependencies, and other planning information, used to produce a
Project Schedule along with other Scheduling Artifacts.
MEhsanSaeed 5
Project
Manager
3
What does ‘Control Schedule’ entail?
MEhsanSaeed 7
MEhsanSaeed
Methods of Controlling Schedule – Data Analysis
Tool Description
EVA Schedule Variance (SV) & Schedule Performance Index (SPI) are used to
assess the magnitude of Variation to the original Schedule Baseline
Burn Charts Used to monitor Schedule progress, particularly in the Agile & Sprint
concepts
Performance Measure, compare, and analyze Schedule Performance against
Reviews the Schedule Baseline such as actual start and finish dates, percent
complete, and remaining duration for work in progress
Trend Examines Project Performance over time to determine if performance is
Analysis improving or deteriorating. Graphical analysis techniques are valuable for
understanding performance to date and for comparing to future
performance goals in the form of completion dates
Variance • Looks at Variances in planned versus actual start and finish dates, planned
Analysis versus actual durations, and variances in float
• Determines the cause and degree of Variance relative to the Schedule
Baseline, estimating the implications of those Variances for future work to
completion, and deciding whether corrective or preventive action is reqd
What If Used to assess the various scenarios guided by the output from the Proj
Scenario Risk Mgt processes to bring the schedule model into alignment with the
Analysis PMP and approved Baseline 8
4
MEhsanSaeed
Methods of Controlling Schedule – Others
Tool Description
CPM Comparing the progress along the Critical Path can help determine
Schedule status. The Variance on the Critical Path will have a direct
impact on the project end date. Evaluating the progress of activities on
Near Critical Paths can identify schedule risk
PMIS Include scheduling softwares like MS Project, Primavera, that provide
the ability to track planned dates versus actual dates, to report
Variances to and progress made against the Schedule Baseline, and to
forecast the effects of changes to the Project Schedule Model
Resource Involve the scheduling of activities and the resources required by those
Optimization activities while taking into consideration both the resource availability
and the project time, through Resource Levelling & Resource
Smoothing
Leads & Lags Leads & Lags adjusted during Network Analysis to find ways to bring
project activities that are behind into alignment with the plan
Schedule Used to find ways to bring project activities that are behind into
Compression alignment with the plan by Fast Tracking or Crashing the Schedule for
the remaining work
10
5
Iteration Burndown Chart
3,500 Scope
Increase
3,000
2,500
MEhsanSaeed
Project Value: 3,000
Remaining Work
1,000
Project Completion
Forecast
500
0
0 5 10 15 20 25 30 35 40
Iteration Time
11
11
3,000
2,500
Ideal Work Completion
Scope of Work
Project Completion
Remaining Work
1,500
1,000
0
0 5 10 15 20 25 30 35 40
Iteration Time
12
12
6
Burndown vs Burnup Chart … Change in Scope
MEhsanSaeed
3,500
3,000
2,500
Remaining Work
2,000
Very Different Project
Completion Forecasts,
1,500 due to Scope Change
(different Graph Shapes
1,000
500
0
0 5 10 15 20 25 30 35 40
Iteration Time
13
13
MEhsanSaeed
3,500
3,000
2,500
Remaining Work
2,000
1,000
500
0
0 5 10 15 20 25 30 35
Iteration Time
14
14
7
Variance Analysis
▪ Variance analysis looks at variances in Planned versus 11 4 14
Actual Start and Finish dates, Planned versus Actual E
Durations, and Variances in Float 11 0 14
MEhsanSaeed 15
15
MEhsanSaeed 16
16
8
Critical Path Method – MC Challenges when Multiple Paths Near
Critical … 1/2
A B C D E
4 8 5 7 8
F G H J
Start End
6 7 10 8
K L M N P
4 8 5 7 6
MEhsanSaeed
Paths Duration
Start-A-B-C-D-E-End 32
Start-F-G-H-J-End 31 3 Near Critical Paths
Start-K-L-M-N=P-End 30
• Variance on Critical Path have a direct impact on the Project
• Variance on Near Critical Paths can identify Schedule Risk; more the Near Critical Paths, more the
Risks of Delays
• Status of Floats; more the remaining float more the flexibility, security. In a way this is RESERVE
ANALYSIS
• Avoid such a situation by exploring the possibility of fast tracking on any near critical path, or even
introducing a dummy activity on the critical path as a reserve margin; a dummy activity, of say 8,
would help eliminate the other two near critical paths 17
17
Paths Duration
MEhsanSaeed
Start-D-E-G-H-C-End 32
Start-D-F-G-H-C-End 31
3 Near Critical Paths
Start-D-F-B-End 16
Start-A-F-G-H-C-End 33
Start-A-F-B-End 18
• Another peculiar case in which near critical paths a number of common activities; in such a case the
three near critical paths may be considered as one critical path. In any case, fast tracking on any
near critical path, or even introducing a dummy activity on the critical path as a reserve margin,
would not be of much help in any way
18
18
9
Performance Review
Performance reviews measure, compare, and analyze schedule
performance against the Schedule Baseline such as actual start and
finish dates, percent complete, and remaining duration for work in
progress
Trend Analysis
▪ Uses mathematical models to forecast future outcomes based on
historical results
▪ Examines graphically the project performance over time to determine
whether performance is improving or deteriorating
▪ Monitors performance to date and comparing to future performance
goals in the form of completion dates
▪ Forms part of BurnUp/BurnDown Charts and EVA
MEhsanSaeed 19
19
Resource Optimization
Resource optimization techniques involve the scheduling of Activities
and the Resources required by those activities while taking into
consideration both the Resource Availability and the Project Time.
Achieved by:
▪ Resource Levelling
▪ Resource Smoothing
MEhsanSaeed 20
20
10
Resource Levelling … 1/3
Day 1 Day 2 Day 3
A R1: 8 hrs
R2: 8 hrs - Activity C dependent
Start on Activities A & B
B R1: 8 hrs - Duration 2 Days, but
- R1 over-allocated
C R2: 8 hrs
- Over-allocation of R1
A R1: 8 hrs resolved by delaying
R2: 8 hrs Activities B & C by one
Start day each
- New Duration 3 Days
B R1: 8 hrs
- This is Resource
Levelling
C R2: 8 hrs
21
MEhsanSaeed 22
22
11
Resource Levelling … 3/3
A to A
Lag
B B
Lag
A to A
B B
23
Resource Smoothing
• A technique that adjusts the activities of a Schedule Model such that
the requirements for Resources on the Project do not exceed certain
Predefined Source Limits; consider the following the Resources Reqts:
10 10 10 10
Short/Hire
8 8 8 8
6 6 6 Smoothing 6
4 4 4 4
2 2 2 2
0 0 0 0
24
12
Schedule Compression - Crashing
Schedule compression techniques are used to find ways to bring
project activities that are behind into alignment with the plan by Fast
Tracking or Crashing the Schedule for the Remaining Work
Crashing
x days x/2 days
R1, R2,
R1, R2
R3, R4
MEhsanSaeed 25
25
26
13
Leads & Lags … 1/2
• Applied during Network Analysis to find ways to:
- bring Project Activities that are behind into alignment with the
Plan, (Leads) or
- make adjustments to the Start or Finish Dates of Activities to
meet certain technical or other requirements (Lags)
• Lead Amount of time a Successor (Dependent) activity can be
advanced with respect to a Predecessor activity. Akin to Fast Tracking
• Lag Amount of time a Successor (Dependent) activity can be delayed
with respect to a Predecessor Activity. Akin to Resource Levelling
Example 1: On a New Office Building project, Landscaping can be adjusted to
start before the Exterior Work of the building is completed by increasing the
Lead time in the relationship
Example 2: On a Report Writing project, Technical Writing Team can adjust the
start of Editing the Draft after the document is written, by eliminating or
decreasing Lag time
MEhsanSaeed 27
27
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
18
FS
10
18
FS-8
10
Lead
Consider the following two activities in FS dependency, with a Total Dur of 28 days. Rather
than wait for the Draft to complete, what can be done to complete the two activities in, say,
20 days? Ans: Apply LEAD on Dep Activity. How much? Draw or Calculate
0 18 0 18
Lead
Write Draft: 18 d Write Draft: 24 d =New-Prev Dur
FS-8 (Lead)
=20-(18+10)
Edit Draft: 10 d Edit Draft: 10 d =-8
18 28 10 20 Note: FS-8=SS+10
28
14
What-If Scenario Analysis … 1/3
• Akin to Risk Management
• Provides a method of indirect ‘Schedule Control’ through Risk
Management
• An analytical technique that evaluates scenarios in order to predict
their Effect (+ve or –ve) on Project Objectives
• It is used to assess the various scenarios guided by the output from the
Project Risk Management processes to bring the schedule model into
alignment with the project management plan and approved baseline
• It is an analysis of the question: “What if the situation represented by
scenario ‘X’ happens?”
MEhsanSaeed
29
29
30
15
What-If Scenario Analysis … 3/3
In General,
• Schedule Network Analysis is performed using Schedule to compute
difference scenarios such as delays in major component delivery,
extension of specific engineering durations, force majeure etc
• Outcome of analysis used to assess the Feasibility of the Project
Schedule under adverse conditions, preparing Contingency &
Response Plans to overcome or mitigate the impact of the
MEhsanSaeed
unexpected situations
• Often, there is no way to meet the Schedule if these scenarios occur.
But it always makes sense to try to understand the impact they will
have on the Schedule
31
31
32
16