Professional Documents
Culture Documents
Casey Ayers
MBA • PMP® • CBAP®
@caseyayers | study.pm
PMP® is a registered mark of the Project Management Institute, Inc. CBAP® is a registered mark of the International Institute of Business Analysis.
Preparing for the PMP® Exam
Organizational
Influences & Project Project Scope
Management Lifecycle Management
Organizational
Influences & Project Project Scope Developing
Management Lifecycle Management Project
Schedules
Organizational
Influences & Project Project Scope Developing
Management Lifecycle Management Project Schedules
Define Activities
Sequence Activities
Management
•
Management
•
individual activities
Catalogs and develops various
•
Management
•
relationships
Determines which tasks must/
•
Management
•
Sequencing
Activities
Defining Estimating
Activities Duration
Plan Schedule
Management
Project Time Management Processes
Sequencing
Activities Control
Defining Estimating Project Schedule
Activities Duration
Plan Schedule
Management
Developing Project Schedules
Develop Project Schedules:
Involves compiling information including desired
activity sequences, projected durations, resource
allocations, dependencies, and various constraints in
order to assemble a holistic schedule model
Developing Project Schedules
Activities
Durations
Scheduling Schedule
Resources Method & Model
Tools
Resource Availability
Logical Relationships
Project Schedule
Develop Project Schedule Planning
•
Management
•
Schedule Model:
•
Management
•
Schedule Model:
•
quality of inputs
Duration and resource estimates
•
Management
•
Schedule Model:
•
start/finish dates…
Comply with dependencies
•
duration
Determines where flexibility
•
Critical Path:
•
Critical Path:
•
Activity One
Six months
Activity Three
Two months
The Critical Path Method
Activity One
Six months
Activity Three
Two months
The Critical Path Method
A1 A2 A3 A4
Start B1 B2 B3 Finish
C1 C2 C3 C4 C5
The Critical Path Method
A1 A2 A3 A4
Start B1 B2 B3 Finish
C1 C2 C3 C4 C5
The Critical Path Method
Activity
activities will likely delay the Activity
Two Three
whole project Three
months
Activity
activities will likely delay the Activity
Two Three
whole project Three
months
{
Activities not on the critical
•
Activity Activity
path can have float or slack Two Three
Three
months
Schedule compression
{
•
{
•
Greater flexibility
The Critical Path Method
Activity One
activity may be delayed Six months
{
How it’s calculated:
•
Greater flexibility
Why Use the Critical Path Method?
activities
Shows when action may be
•
Early Start:
•
Activity Duration:
•
Early Finish:
•
Late Finish:
•
Late Start:
•
Total Float:
•
Finish
Start
Late
Start
Total
Float
Late
Finish
Late
Start
Total
Float
Late
Finish Activity Duration:
•
Activity Name
Late Start Total Float Late Finish
•
1 5 5 Early
Start
Activity
Duration
Early
Finish Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish
Late
Start
Total
Float
Late
Finish Activity Duration:
•
Early Finish:
•
1 5 5 Early
Start
Activity
Duration
Early
Finish Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish
Late
Start
Total
Float
Late
Finish Activity Duration:
•
Early Finish:
•
1 5 5 Early
Start
Activity
Duration
Early
Finish Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish
Late
Start
Total
Float
Late
Finish Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish
Late
Start
Total
Float
Late
Finish Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
Late
Start
Total
Float
Late
Finish 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•
Early Finish:
•
1 5 5 16 15 30 Late Finish:
•
Finish
Start
1 0 5 16 0 30 Activity Duration:
•
6 10 15
Activity C Total Float:
•