Professional Documents
Culture Documents
PROJECT SCHEDULE
MANAGEMENT
1
KEY
CONCEPT
⮚ Provides a detailed plan representing how and when the product/service will be delivered
Network diagram
4
TRENDS AND EMERGING PRACTICES
On-demand scheduling
This approach, typically used in a Kanban system, is based on the theory-of-
constraints and pull-based scheduling concepts
Define Activities
9
6.2 Define Activities
10
6.2 Define Activities
Tools &
Technology
Decomposition:
Technique used for dividing and subdividing
the project scope and
deliverables into smaller, more manageable
parts
Ex. Work Breakdown Structure
11
Rolling Wave Planning — a project management methodology in which near term activities
are planned in details while future activities are planned in high level. As the project progresses, more
information becomes available so that future activities can be planned in more details.
Progressive Elaboration — More details are added to the project plan as more
information becomes available while the project progresses.
12
Milestone — An important event in the project timeline that has no duration.
13
Identifying and documenting relationships among the project activities.
14
Sequence Activities
Inputs Tools & Techniques Outputs
15
is a technique used for constructing a schedule model
17
PDM RELATIONSHIP EXAMPLE
1. FS: Award ceremony (S) cannot start until the race (P) has finished
2. FF: Writing a document (predecessor) is required to finish before editing
(successor) the document can finish
3. SS: To apply a coating (successor) , you also need to clean the wall
(predecessor). Both activities can be started at the same
4. SF: The first security guard shift (predecessor) cannot finish until the
second security guard shift (successor) starts.
Around 95% of all relationships in a network diagram use the finish-to-start relationship and the
very rare case is Start to Finish.
18
LET’S HAVE A BREAK
Event Relation
You cannot start development until you finish the design Finish-Start
Marketing brochure preparation cannot start until user documentation has begun Start-Start
Broadcast of a football match cannot finish until the match is finished Finish-Finish
Level concrete (successor) cannot begin until pour foundation (predecessor) begins Start-Start
Though there are four types of dependency, two types are happen at the same time. i.e. external
mandatory or internal discretionary. 20
BRAINSTROM
Event Relation
Bake cake
Decorate cake
FS +2h
22
SCHEDULE NETWORK DIAGRAM
23
Estimate Activity Duration
24
Estimate Activity Duration
Inputs Tools & Techniques Outputs
25
ESTIMATIONS
▪ Analogous Estimating
▪ Parametric Estimating
▪ Three point Estimating
▪ Most likely
▪ Optimistic
▪ Pessimistic
▪ Bottom-up Estimation
Q
Dhaka to Savar travel time: best- 30 minutes, normal- 45 minutes, and worst- 90 minutes.
What is the expected time and standard deviation to travel?
26
DATA ANALYSIS
Alternative Analysis:
Reserve Analysis:
• Known-unknowns: Contingency Reserve
• Unknown-unknowns: Management Reserve
27
Decision Making
• Fist of Five
Meeting:
• Sprint or Iteration planning meetings
28
Develop Schedule
Inputs Tools & Techniques Outputs
Modeling Techniques
• What-if scenario analysis
• Simulation
PMBOK guide 32
SCHEDULE COMPRESSION
PMBOK guide 33
ES Duration EF
Activity name
LS Float LF
Free: The time an activity can be delayed without Float = LS-ES or LF-EF
delaying the early start of the successor.
34
NETWORK DIAGRAMS
Activity oriented
35
NETWORK DIAGRAMS
Work package Duration Predecessors
B. Furniture Selection 25 A
C. Office Preparation 20 A
E. Closeout 5 D
36
Exercise: Install new building fire alarm
Q
1. What is the critical path?
2. Where is the float or slack, if any?
37
ES Duration EF
25 32 57
Activity name
D
3 LS Float LF
10 15 25 60 5 65
B F
0 10 10 25 35 60 65 2 67 67 1 68
START A E G H
10 20 30
C
35
38
Control Schedule
Inputs Tools & Techniques Outputs
39
PROCESS CHECK
The process of establishing the policies, procedures, and documentation for Plan Schedule
planning, developing, managing, executing, and controlling the project schedule. Management
The process of estimating the number of work periods needed to complete Estimate Activity
individual activities with the estimated resources. Duration
The process of identifying and documenting the specific actions to be performed to Define Activities
produce the project deliverables.
The process of monitoring the status of the project to update the project schedule
Control Schedule
and manage changes to the schedule baseline.
40
MEMORY CHECK
1. The four types of precedence relationships are:________, ________, ________, _________
2. The completion of a key deliverable or a phase in the project is called a____________
3. Starting a successor activity before the predecessor is complete is called a ______, while a delay in
starting a successor activity is defined as a_______
4. The most accurate and time consuming of the estimates is called________estimating
5. The time an activity can be delayed without delaying the project end date is called __________
6. The_____________ in a network diagram is the longest path through the network that produces
the shortest possible completion time for the project
7. The time a project can be delayed without delaying the start of a successor project is called
___________
8. The two primary schedule compression techniques are called _________and _____________
9. Stabilizing the number of resources working in each time period to prevent resource over
allocation is known as_____________
10._____________describes the time an activity can be delayed before delaying the early start (ES) of
a successor activity
11.Higher-level summary activities that occur between milestones in a bar chart are frequently
called_____________
12.An activity that has no duration is called a___________
41