• Scheduling methodology
• Scheduling tool
• Level of accuracy for duration estimates
• Units of measure
• Variance thresholds
• Schedule reporting information and format
• Process for identifying all the activities
• Process and guidelines for sequencing activities
• Process for estimating resources needs
• Process for estimating effort and duration
• Process for updating, managing, and controlling the schedule
In addition, the Schedule Management Plan may include information on the level of detail and timing for
WBS decomposition based on rolling wave planning.
• Project Charter
• Project Management Plan
• Activity List
• Activity Attributes
• Network Diagram
• Activity Resource Requirements
• Resource Breakdown Structure
• Activity Duration Estimates
• Project Schedule
• Schedule Baseline
The Schedule Management Plan is an output from the process 6.1 Plan Schedule Management in the
PMBOK® Guide—Fifth Edition.
You can use the element descriptions in Table 2.11 to assist you in developing a Schedule Management Plan.