Budget
Budget Budget Budget Total Budget Total Budget
Components Amount (AED) Aug'20 Sep'20 Till Sep'20 Oct'20 Till Oct'20 Nov'20
License cost (1 year) 100000 200 200 400 200 600 200
Contingency 50000 0 0
0 0 0
1. Procured licenses for 500 @ AED .4 per user per month till Dec'20.
2. Procured licenses for 35000 @ AED 4 per user per month from Jan'21 till July'21
3. Post this licenses will be renewed at the same rate for next 3 years without any increase
This is milestone based and fixed cost will be paid to the implementation partner. Milestones are:
1. Review and Sign off – configuration workbook post familiarisation session- 5%
2. Review and Sign off – Global Process and configuration workbook post process playback 2 - 10%
3. UAT Sign off - 35%
4. Go live - 35%
5. Post go live support & transition - 15%
10% of the overall project cost is reserved for unforeseen work that is within scope of the project
10% of the overall project cost is reserved for known-unknowns that may impact the project schedule
known unknowns such as:
1. Being a cloud product it may not meet the critical requirements and we may have to wait for next update
2. GPO being available for this project only 50%, this schedule may get impacted in case of any unforeseen
circumstances
3. Due to time / developing tools constraints we may have to outsource developing the training materials
4. We may have to take external consultant advise on defining global process