Professional Documents
Culture Documents
Lesson 8
Customizing Views
Views in Microsoft® Project 2013 are designed to display information in a logical manner. The following options are
provided for selecting a view when you click the View tab:
Task View
• It allows to select the Gantt Chart, Network Diagram, Task Usage,
Calendar, Timeline View, or Task Sheet
Resource View
• It allows to select the Resource Usage, Resource Sheet, Team
Planner, or Resource Form View
Other Views
• It allows to change Timescale, zoom into a view, sort data etc.,
Some views in Microsoft® Project 2013 are used more than others. The commonly used views in Microsoft® Project
2013 are as follows:
Gantt Chart : it is used to plan and review a project schedule. An example of a Gantt chart view is shown below.
Network diagram : it is used to fine-tune a project plan. An example of a Gantt chart view is shown below.
Graph: It is used to display remaining work or availability of resources. An example of a Graph view is shown below.
The various options to work with views in Microsoft® Project 2013 are highlighted in the screenshot.
Sort command
Data ribbon
Arranges items in
a particular order Changes the data
displayed in a view
Outline command
Shows or hides
subtasks
Task Usage Report : It is used by the Project Manager to view all the resources assigned to a particular task. An example
of a Task Usage report is shown below.
Resource Usage Report : It is used by the Project Manager to group all tasks performed by a particular resource. An
example of a Resource Usage report is shown below.
Group by command : It is used by the Project Manager to group items according to a specific criterion. An example of a
Group by command is shown below.
Filters can be applied to views in Microsoft® Project 2013 to sort and locate data quickly in a view. Steps to apply filters
are shown here:
The AutoFilter option can be used to sort information alphabetically, numerically, or chronologically and find data quickly
in a view.
• To clear all the filters, click the Clear All Filters option.
Creating a new view is essential when information of a plan is required to be viewed in a way that is not defined in the
predefined views.
In Microsoft® Project 2013, a view can be shared with another project in the following ways:
● By sharing views, reports, and calendars, with other projects or copying the view to the global MS Project template.
● By clicking the File Organizer to see all the elements that are in the global template and the elements that are
specific to the views in the project.
● By using the Organizer to copy reports, tables, filters, calendars, groups, and custom text styles to the global template.
Tables can be used to find specific information quickly without having to sift through data. The steps to explore the table
option in Microsoft® Project 2013 is shown below.
By hiding columns
By adding columns
By rearranging columns
By adjusting Timescale
By formatting text
By using highlights
a. Sort command
b. No Group
c. Data Ribbon
d. Outline command
a. Sort command
b. No Group
c. Data Ribbon
d. Outline command
Answer: b. No Group
Explanation: Project Managers can use the “No Group” command to remove a group.
Which of the following views is used by the Project Manager to fine-tune a project plan?
Select the answer.
b. Graph view
d. Timeline view
Which of the following views is used by the Project Manager to fine-tune a project plan?
b. Graph view
d. Timeline view
Explanation: A Project Manager uses the Network Diagram view to fine tune the project plan.
Which of the following options is an appropriate reason for a Project Manager to apply a filter?
Which of the following options is an appropriate reason for a Project Manager to apply a filter?
Explanation: A Project Manager applies a filter to focus on a specific task or a resource in a view.
Which of the following can be used to share a view with another project?
a. By using the organizer to copy reports, tables, etc., to the global template
b. By adding the desired values in the given options in the View Definition window
Which of the following can be used to share a view with another project?
a. By using the organizer to copy reports, tables, etc., to the global template
b. By adding the desired values in the given options in the View Definition window
Answer: a. By using the organizer to copy reports, tables, etc., to the global template
Explanation: A view can be shared with another project by using the organizer to copy reports, tables, etc., to
the global template.
Which of the following commands can be used to change the text style in a view?
a. Timescale
b. Text Styles
c. Highlight
d. Insert Column
Which of the following commands can be used to change the text style in a view?
a. Timescale
b. Text Styles
c. Highlight
d. Insert Column
Explanation: The “Text Styles” command can be used to change the text style in a view.
b. Resource view allows you to select the Resource Usage, Resource Sheet, etc.
b. Resource view allows you to select the Resource Usage, Resource Sheet, etc.
Answer: b. Resource view allows you to select the Resource Usage, Resource Sheet, etc.
Explanation: Resource view allows you to select the Resource Usage, Resource Sheet, etc.
• The commonly used views in Microsoft® Project 2013 are Gantt Chart View,
Network Diagram View, and Graphs.
• Some options to customize views are working with panes, resizing panes, resetting
views, etc.
• Project Managers can apply a filter in Microsoft® Project 2013 to focus on a specific
task or a resource in a view.
• Tables can be used to find specific information quickly without having to sift
through data.