Professional Documents
Culture Documents
SYNOP SJS
that the subsoil of the plant consists of a deposit of soft silt and clay ,
wit h a maximum depth of several hundred feet , and I wanted to
collect some specimens to be tested in my make-shift laboratory.
Whe n I arrived at the site, I found , in addition to the excavation,
a heap of precast reinforced concrete piles and the setup for a pile
loading test. Thi s fact aroused my interest , because I knew that the
predecessors to the new structure rested on mat foundations . There-
fo re, I called on the general manager of the plant , whom I had met
socially, and asked him to explain the project to me.
According to the construction drawings which I was shown , one-
half of the proposed structure would have rested on point-bearing piles
and the other half on friction piles embedded in soft clay. I was
shocked and explained to the manager that the piles would do more
harm than good. The portion resting on point-bearing piles is rigidly
supported, whereas the portion on friction piles would settle at least
several inches, whereupon the pile-supported foundation would fail
like an overloaded cantilever beam by bending. Therefore , I sug-
gested that the Company should sell the piles or throw them into the
Bosporus.
After lengthy discussions , the manager began to realize the weight
of my arguments but , he added, he would never succeed in inducing
the design department of his organization, with headquarters in
France, to accept my unconventional proposal. Therefore, he invited
me to make a trip to France and try it myself. At the headquarters
of the organization I , an obscure teacher, faced engineers with a well-
established reputation, full of confidence in the soundness of their
judgment. My arguments were received with utmost skepticism . The
pile loading test had already shown that the settlement of the friction
piles under the design load was negligible and, as a consequence , my
pessimistic settlement forecast was considered to be wrong. Neverthe-
less , the mere existence of arguments in favor of the gloomy prediction
made the designers of the foundation somewhat uneasy. Therefore, a
compromise solution was proposed and accepted . The piles were re-
tained as part of the foundation , but the site of the building was
shifted away from the slope, whereupon all the piles assumed the
func tion of friction piles.
I left France with the conviction that the structure would settle
as if the piles had not been driven, whereas my clients believed that
the results of the settlement observations would demonstrate the ab-
BO T O:\! "OClETY F CIVTL E:'\ GI.'JEER S
ltles. The con truction men blame the design personnel for paying
no attention to the construction angle of their projects , but they are
blissfully unaware of their own shortcomings. The design engineers
claim that the construction men have no conception of the reasoning
behind their de ign , but they forget that the ame end in design can
be achieved by various means ome of which can be easily realized
in the field, whereas others may be almost impracticable. If none of
the men in charge of de ign has previously been engaged in construc-
tion , the design may be unneces arily awkward from a construction
point of view. In any event, the con truction men have no incentive
to find out whether or not the design as umptions are in accordance
with what they experience in the field during construction, and serious
discrepancies may pass unnoticed. If conditions are encountered which
require local modifications of the original design , the construction en-
gineer may make these changes in accordance with his own judgment,
which he believes i sound , although it may be very poor. Important
changes of this kind have even been made on the job without indi-
cating the change on the field set of construction drawings.
Furthermore, the layout of temporary in tallations is commonly
left to the discretion of the superintendent of construction. The drain-
age provisions for unwatering the site for an earthdam and those for
the dispo al of the water coming out of a wet tunnel belong to this
category.
The drainage provisions for unwatering the site for an earthdam
prior to the beginning of the filling operation may introduce an ele-
ment of seriou weakness into the structure without the superintendent
of con truction suspecting it. In one instance the box drains leading
to the umps at the site for an earthdam were laid out in such a manner
that the completed structure would have failed by piping through the
drains. When I arrived at the ite the drains were already buried be-
neath fill material and no record was kept of the location of the drains.
Fortunately, the thickne s of the layer of fill located above the drains
was still moderate . After I reconstructed the layout of the drains
on the ba is of the results of cross-examination, it was not yet too late
to eliminate the source of weakness represented by the drain .
On another project the excavation for a powerhouse wa being
made at the foot of a fore t-covered talu slope . The talu consisted
of a m ixture of rubble and the sandy and silty products of rock
weathering. The slope rose at the an gle of repose of the talus material
COK SULTANTS, CLIENTS, AND CONTRACTORS
individual piles was much greater than the design load, and the settle-
ment was exclusively due to the consolidation of clay lenses. Some of
the piles had met refusal in the gravel above a clay lens and others
went through several clay lenses into the lower portion of the gravel
stratum. This was the reason for the erratic variation in the total
depth of penetration of the piles. If this variation had been brought
to the attention of the design department as soon as it was observed,
the causes would have been investigated and the pile driving proce-
dure modified in such a manner that all the piles could be driven to
bedrock.
PERFORMANCE BY THE CONTRACTOR
placed against older , dried out and uncompacted material. The gradi-
ent of the surface of the new fill was such that the next rainstorm will
produce a pool in the northeast corner of the new fill. The pumping
equipment is inadequate. Although the job calls for a large amount of
hand tamping, the contractor has made no provisions for tamping
equipment. On the upper level, in the upstream portion of the dam ,
filling operations should be discontinued because the water content of
the borrowpit material is at present too low and the contractor has
made no provisions for sprinkling.
" At the southeast corner the contractor has blocked the exit for
the accumulating rainwater by a pile of waste material. Originally
the lowest point of the saddle southeast of the site was 505 . Now it
is already 508.5 and the diversion of the rainwater towards the south-
east will require a substantial amount of excavation which could have
been avoided by intelligent planning.
" In my last memorandum I requested that the north end of the
cutoff trench should be excavated down to decomposed rock. The in-
spector assured me that he has passed this request on to the contrac-
tors. evertheless, I found that the fill was placed against the pocket
of very permeable alluvial materials.
" If the contractors continue to disregard the elementary rules
for the construction of earth dams and to ignore the instructions of
the inspector wherever they can , the resulting structure will be unsafe
in spite of conservative design."
CONSULTANTS OR SCAPEGOATS
Conditions like those described under the preceding heading pre-
vailed on many of the projects with which I was associated in the
course of my professional career. In some instances they were con-
siderably worse. Hence it is evident that the success of large-scale
earthwork operations depends on many factors other than the ade-
quacy of the original design. This fact introduces serious complica-
tions into the relationship be.tween the client and a consultant who
is retained in an advisory capacity in the design stage of a project.
The incentive for retaining a consultant commonly grows out of
the fact that the functions of most engineering organizations cover a
very broad field , including earthwork , structural , hydraulic, mechani-
cal and electrical engineering. Few, if any, of the members of such
an organization have the time and the opportunity to specialize.
BOS TO !\ 5 0U E.TY OF CIVI L ENGIN E ERS
the rlesign s tage are utterly at va riance with those encountered dur ing
cons truction.
If a consult ant is retained by an engineering o rganizat ion in
which the soil mechanic. department maintain. a con tinuou and inti-
mate contact be tw een design d partment .;1.nd the job durin g the con-
tru ct ion period, the coo peration between con: ultant and client is com-
mon ly frictionle_ · and ati. factory , provided th e member. of the . oil
mechanics depa rtm ent a re well trained a nd competent. Furt hermore ,
the o n. ultant can rend er a maximum of ser ice in a minimum amou nt
of time becau se the . oil mechanics depa rtm ent keeps him in fo rmed
on whateve r differences b tween de ign assumption. and field condi-
tion. are detected during the constructi on ope rat ions and th e depart-
ment can be expected to take ca re that hi.· instruction.. will be carried
out o n the job .
H oweve r in mos t engin eerin g organi zation s . de- ign a nd s uper-
vision of construction are still divorc d , though this fact may be
cam ouflaged by a . mall soil mechanics departm eot with no fun ct ion
other tha n providing the design department with th e ba ic data for
design. If a con ul tant is invited by an engineering organization with
s uch an adminis trative setup to cooperate on a projec t in th e design
s tag , he sh ould wat ch hi. step. Fir. t o f all , he should turn down
the assign ment unless it in volves th duty to remain in active contac t
with th e project until th e end of the r,n iod of cons truction , and to
insp c t th e job whenever he considers it neces ·ary . In order to be
able to pe rform hi duty he must ge t d tai l d weekly repo rt s inform-
ing him of all tho. e observational facts which have a significa nt bea r-
ing on the validity of the design assumptions . uch a repo rt can be
prepared only by a competent soiL engineer , who _tay on the job
permanently . Second if the con ul tant accept th a ssignment he
should find out as soon as possible whe th er or not the inspec tion of the
con truction ope rati ons on the job is satisfactory . If he arrive. at the
co nclusion that the inspection is inadequate a nd his efforts to amelio-
rate the co ndition ar e un ucce s ful , he should s ubmit hi s resignatio n
lea ving no doubt conc ernin g th e reasons whi ch compelled him to do so.
The subject of this paper is of vital int eres t to consultant s a s well
as to th ei r client and to the per:ons who furni : h th e capital for
real izin c, their projects. The need for expert adv ice on difficult projects
is universally recog nized . H owever , the coop eration of cons ul ta nts
of high standing on · uch projects creates an unwarranted feeling of
CO. -~LI.T.\. TS, CU E~T.' . :-\:\"l CO~T IUCTOR .·
ecu rity, unle full advantage is taken of the . ervices they are able to
render. A satis factory formula for accomplishing thi: purpose has not
y t been established .
The preceding sugges tion - are based on my per · onal experience_
a nd observati ons, the scope of which is inevitably limited . Therefore .
other con ultant and engineering firm . employing con ultant could
render a valuable ervice to the engineering prof es ion by presenting
in the di.cu. ions to this paper some of their ex periences and opi nions
concerning the relationship between con: ultanL and client: .
Drscu · ·10N
Bv ARTHlJ R CASAGRA1" DE ,* Memb er
D1scuss10N
Bv M . H . C U TLER*
enced per onnel in all pha ·e of the work . Earthwork and founda-
tions particularly demand pecial care and cooperation between field
and office, since compatibility between a umptions and actual condi-
tions mu t be continuously checked wi th full appreciati on that th e
earth·s cru t is not a uniform and quality controlled product. such
a most of the element making up a building superst ructure. There
is more than a germ of truth in the generality that the greatest con-
sistency in foundation co nditions lies in the variability .
The remarks on wor k ca rried out on a contract ba i struck a
re pon ive note. If the interest of the Owner the Enginee r and the
Co ntractor are opposed " the Co ntractor can not be expected to be
interested or even aware of the reasoning behind the design. ' It is our
philosophy that the best solution to this dilemma lies in a contract
under which the interests of these parties are common.
There was a circumstance where we were constructing a plant
from de igns by others. Our ~uperin tendent 's experience yardstick
told him there was a discrepancy between the size of footings at the
allowable soil bearing and the load to be carried. His comment to this
effect was brushed off by the Engineer rather peremptorily but, being·
a persistent individual, the upe rintendent referred the matter to our
engineering department which quickly verified that an arithmetic
error had re ulted in footing ¼ the proper ize.
In another instance a manufacturer had placed the re ponsibility
for a proj ect design of hi s process enginee r, who, with the assistance
of a contractor , had selected a site, cut and driven more than 3,000
sp ruce piles 50 ft long and poured some of the foundation , without
benefit of uitable subsoil investigation . ome of the pile did not
'' fetch up and another 50 ft length of pile wa spliced weakly on th e
lower section. When three 50 ft length of piles , one on the other,
still did not '' fetch up", it was decided to obtain consulting advice, and
we were call ed in . Subsoil in ves tigation developed information that
a urface stratum of sand was underlain by a su bstantial and variable
depth of very so ft plastic clay. Below the clay and above bedrock was
another sand layer containing appreciable artesian pres ure . Further
!n ves tigation indicated that most of the piles as driven had their tips
in the soft clay and that prohibitive diff erential settlements must be
expected. During the investigation , evidence of suspec ted bank in-
stability wa proved and it appeared prudent to move the entire
plant construction to another portion of the site where rock founda-
BOSTO.'-J SOCIE TY OF C TVIL E:KGTK EERS
Bv D . J. BLEIFuss*
I have read Mr. Terzaghi 's paper with considerable interest ; the
subject is one which sho uld be given a good deal of attention . I must
start my discussion by disagreeing with him when he says his personal
experiences and observations are limited ; the scope of his experience
is about as unlimited as it is possible for any one man's to be. There
are few consultants as well qualified to discuss this subject.
He is quite right in saying that consultants are often not used
to the best advantage. A client may not employ a consultant at all,
when he really needs one badly. A client may select the wrong con-
sultant. A client may make the wrong arrangement with the right
consultant.
It is a curious fact that many laymen consider themselves quali-
fied to criticise an engineer , or to do their own engineering. Time and
education will take care of this, as the public comes more and more
to realize that this civilization of ours is based on the work of the
engineer. The roads we travel on ; the cars we ride in ; the machinery
we use; the energy to drive our machinery ; our communication sys-
tems; our water systems ; they are all based on the work of the
engineer.
A client may select the wrong consultant . To many people, an
engineer is an engineer; they make no distinction between bridge,
.. B le if uss, H os te tter & Associates, Consulting En g ineers , Sacramento, Ca liforni a.
CO ): · t;LTANTS, CLJl~\:T ~ . . \ \" D ·oN TR .\ 'T OR S
hydroelectric, anitary , and other en°in eers. The same peopl e would
not dream of employin an ob tetrician when they really ne d a skin
peciali t. Reputable con ultant will not accept mployment in a
fie ld where they feel they cannot do the best work. con sultant may
be hopele sly incompetent; fortunately. there are very few of this
cla s and they u ually do not la t long. A great nam e and reputation
are no good guide in lection, which hould be ba ed on only one
consideration , i.e ., what the con ultant has actually done in the fi Id
whe re hi advice i being ought.
A client may make the wrong arrangem nt with a consultant.
Wi hing to save money he may limit the con ultant'. employment to
one particular phase of the work, such as preliminary layout and
gathering data, design, or the supervision of construction. In the fir ·t
two case there may be no " follow through /' in the la t cas the con-
sultant may be called on to supervise the construction of something
he knows could be improved or is radically wrong. If limited to pre-
liminary layout and gathering data, the con ultant has no control
ove r detailed de ign or the field changes inevitably n cessary as con-
struction develops new information. If limited to detail design he
may find his data insufficient ( very common ) that it ha been mis-
interpreted, or that the preliminary layout i wrong. He will have
no assurance that his careful de ign will be carried out and again no
control over field change .
In such cases, if trouble develops , all the engineering on the job
gets tarred with the ame bru h regardless as to where the fault
specifically lies. It is difficult to see what can be done about this
since a consultant cannot very well ref u e employment on the grounds
he is not being asked to do enough.
I wi h to cite a few illu trations:
A. A dam ite had been chosen and inve tigated. On being called
upon to make a preliminary de ign and estimate, I found that a much
better site close by had been di regarded.
B. An earthfill dam project-it had been reported that perviou
material was plentiful and imperviou material scarce. When called
upon for detailed design , we wi hed to check these data in the field ,
?ut the client insisted this was unnecessary and that he placed
~mplicit reliance on his own engineers. The dam was designed accord-
~ngly. pon personal investigation later , I found the data wrong;
impervious material was plentiful, and pervious material scarce. The
BOS T O.:--1 SO lET'l: OF C l\ IL E GINEE RS
contractor had already tarted work but the dam had to be re-
designed. Then the client prote ted the extra expense .
C. We de igned an eartbfi 11 dam , but the client insisted on _uper-
vi ing construction with hi own force · we were to have nothing to
do with it. On casually vi iting the dam during con truction, I found
to my horror that where we had specified sand and gravel silt was
being placed , and very wet silt at that. It was merely the clients
and our own good luck that we caught this in time .
D. \\ e designed a concrete dam but were to have nothing to
do with supervision of con struction. However , when placing of con-
crete was started, I looked at the fir t test reports and found the
concrete was not up to specifications. Although it wa none of my
busine , i protested vigorously and the condition was corrected.
A consultant' relation hip with a contractor may be of two
kind , the contractor may be his client , or the con ultant may be the
owner client> repre entative. Many contractors consider the engi-
neer as an unmitigated nuisance and evi l and think they could very
well get along without him · some contractors have progressed to the
point where they admit the engineer is a necessary evil ; the best con-
tractor cooperate whole-heartedly with the engin eer. Quite often ,
the contractor employee regardless of his attitude , have a mi taken
idea of loyalty, and think that by cutting corners , they are serving
the contractors be t interest. Or they have not the slightest notion
as to the rea on why certain things mu t be done in a certain fa hion ,
and regard any requirement which may interfere with speed and pro-
duction as quite unneces ary . A foreman who two year ago was a
laborer will argue with an engineer of thirty years' experience. I
may cite one case: a lift of concrete had been placed , with dowel steel
projecting upward from it surface to tie in the next lift. As soon as
the concrete had attained its set and could be walked on without foot-
prints being left , the contractor men warmed over it, erecting form
for the next lift. The dowel steel was pushed around with the result
that each rod was oon standing in a hole with no bond at all for per-
haps twelve inches below the urface . It was a rush job, and my
prote t was regarded as unreasonable interference with progre . An-
other case: transmission tower foundation s had been placed a much
a three inches out of line and guide ; steel towers erected on them
were in con equence very much di torted and it was necessary to
take down the towers , dig up the foundation s and start over. A totally
unwarranted interference with progress.
CO'.\TSUL Tt\~TS, CLTE~T , _-\:'.\'D CO . TR _-\ CTOR
DISCUSSION
Bv R OBERT F. OGILVY*
In April 1957 , about half a year before Dr. Terzaghi read his
paper " Consult ants, lients, and ontractors ' at a meeting of the
Boston ociety of Civil Engineers, I wa a ked to talk at a luncheon
meeting of the Montreal oils Group on t.he topic " What the Struc-
tural Engineer Expect from the oi l Con ultant ' . This talk was
repeated in Ottawa in early October. My remarks on thi _ubject
upplement in many re pects the statements contained in Dr. Terza-
ghi s paper. Therefore , Dr . Terzaghi has uggested that I ubmit
the following abstract of my talk to the Montreal oils Group as a
contribution to the di. cu sion of his paper. Although my talk dealt
essentially with the relationship between the soils consultant and the
st ructural engineer, in many instance_ the _tructural engineer may
represent the owners or act as an intermediary between the soils
engineer and the owners, and as such may assume the po ition of
client as far as the soils con ·ultant i concerned. The oil consultant
and the structural engineer should be mutually and equally concerned
with the contractor's performance, and determined that the work
shall be carried out to con form to the basis of the design specifications.
The work of the soils consultant a nd of the structural engineer
lies quite largely within the field of general con truction work. Pos-
sibly a brief review of design and construction practices in North
America will provide some background for more detailed observations
later. On one of the first warm days of the spring of 1927 , several
engineers, engaged on the construction of the Gatineau mill for Cana-
dian International Paper Company, were itting in a quiet alcove
on the sunny side of the grind er building during noon hour discussing
the const ruction work which was ju t drawing to a close. An Austra-
lian engineer expressed great urprise in comparing his previous ex-
perience with what he con sidered the strange practices which had been
involved in the con truction of Gatineau Works . He de cribed the
procedure in Australia based on practice in Great Britain, which
required that all drawings for the entire project should be completed
and checked and approved before any construction work was started.
This was in very direct contra. t to the procedure followed at Gatineau
'Ge neral En gi ne eri ng D epa rtm e nt, Aluminum Company of Ca na da, Limit ed, M on treal ,
Ca nada.
co :s;-S l.! LT ANTS, CLIENTS, AND CONTRACTOR S
soil consultant , whereas the person using the data for design purposes
may not understand the limitations of its use. The soil consultant
should exercise great care to establish definitely that the data is under-
stood and is applied properly to the problem under consideration. This
further emphasizes the absolute necessity of close contact between
the soils engineer and the structural engineer. It is essential that
the soil consultant is absolutely sure that the test data obtained from
laboratory work does apply specifically to the structural engineer's
problem.
( c) Compilation of Data. This phase consists of assembly and
compilation of field and laboratory data covering the drill logs and
test results , and the presentation of this data in a concise and prob-
ably graphical form, in which it can be studied and digested. This is
drafting room work. It is essential that the vast mass of data obtained
on a large project should be summarized concisely in order that it
may be very much to the point and easily understandable by an en-
gineer not fully coversant with soil problems.
( d) Engineering Analysis and Report. This phase consists of
study and analysis of the data in relation to the engineering problem
by fully qualified professional personnel. This is the step in which
the closest liaison with the structural engineer is required.
( e) Inspection and Supervision of Construction. This phase in-
cludes review of actual field conditions in comparison to the assumed
conditions , field control testing to assure compliance with specifica-
tions in the case of earth construction, and provision of field soils en-
gineers as advisors to the construction engineering staff, when such
assistance is warranted. This is the final follow-up which is particu-
larly valuable in generating confidence in the owners as represented by
the structural engineering staff.
At the risk of repetition , it may be wise to run over in further
brief detail the factors which affect the close co-operation between the
structural engineer and the soil consultant. The basic problem of the
soil consultant is:
(a) To determine fro,n the structural engineer what conditions,
present and future, will be imposed upon the foundation soil
by the proposed structure.
(b ) To determine the soil conditions at the site by subsoil in-
vestigation.
no TO '.\ SOCIET Y OF CI \ 'IL E ~ G I~E ERS
of somewhat more than 20 feet , and the stripped material has been
replaced to the required grade by sand and gravel backfill. Com-
paction of this backfill material has been very good and practically no
sett lement takes place in this replaced layer. However , at a depth
of approximately 40 feet, varying som ewhat with the location , there
is a horizontal strata of compressible gray silt which compacts under
pressure and very appreciable settlement takes place as buildings
loads are applied. Our soils consultants estimated these settlements
five years ago, and es timated variations in the settlement according
to the location. These predictions have been proven to be quite satis-
factory although there have been some minor variations. However,
actual settlements have been observed and measured very closely
du ri ng the intervening years with the result that this experience has
been sufficient to enable the soils consultants to prepare predictions
with increasing accuracy, so that we believe that the predictions of
settlement. for Potline 8 will prove to be almost exactly what will be
experienced during the next 5 years at that location.
The soils consultant must be persistent and must have self-
confidence. On one job, we took exceptional care to consolidate the
rock on which a concrete storage dam was being constructed. Every
means was taken to ensure that the rock was sound and an extensive
grout curtain was drilled and placed under the upstream face of the
da m. There was the rewarding satisfaction derived from the comment
by an experienced consultant in dam construction that he had never
witnessed a dam built from which leakage had been cut to such an
absolute minimum. However, our satisfaction with this accomplish-
ment was tempered somewhat by the question from one of our own
engi nee rs as to whether such care was really justified or whether it
would be better to take less pains and permit certain leakage. The
soils engineer may be faced with a similar question as to whether a
full inves tigation of soils conditions is actually necessary, or whether
construction work can be carried out to somewhat less exacting stand-
ards. T he soils consul tant must have the answers to justify the work
he is doing.
Of course, a very definite example of that justification was the
experience with a timber pile wharf designed for the west coast. When
this design was well under way and the type of construction definitely
established, a soils consultan t was asked to confirm the fact that this
design was satisfact ory fo r this particular location. This investigation
BOSTON SOCIE TY OF C fVIL E?\GI.\:EERS
very promptly showed that normal loading of this wharf would stress
the piles at least 100 % and any combination of added wind loads or
wave action would very seriously overstress the piles. In thi s par-
ticular in stance , the soils consultant had to convince the owners that
his conclusions based on expert investigation were more reliable than
the owner's own previous experience with timber wharf construction
on the west coast but under somewhat different conditions.
The growth of soils engineering during the past 20 years has led
to an appreciation of the value of this work. However , it is still neces-
sary to increase this appreciation in some quarters and that is the
responsibility of the soils engineer. The structural engineer expects
from the soils consultant definite engineering advice presented with
sufficient confidence that it will be approved by the owners.
For material for this discussion, I am very much indebted to
personal contacts with the soils consultants in the Montreal district.
The engineering staff of the Aluminum Company of Canada, Limited,
has very kindly commented on specific details. Our soils consultant
on the west coast has provided invaluable information through dis-
cussion on what may be expected from the soils consultants.
DISCUSSION
BY RALPH B. PECK*
DISCUSSION
DISCUSS ION
'P.>nner, ~lo ran, P roctor, )l ueser & R utledge, Consulting Engineers, ew York i1y .
co.;\ l1LT.-\'.\1T ' CLIENTS, .-\~D C0 1 TR .-\ CT OR
DISCUSSION
Bv F. E. SCHMITT
DISCUSSION
BY ADOLPH J. ACKERMAN*
Dr. Terzaghi's services as an educator and his skillful wntmgs
in the technical field have had far-reaching effects on the engineering
profession . It is, therefore, all the more stimulating to gain a glimpse
of his personal philosophy as it has developed from his consulting
engineering practice.
Among the items in his paper which deserve special emphasis
are the following:
1. A prerequisite of a success£ ul consulting engineer is the
requirement that he must have " independence" and "time to think".
*Consuhing Enginee r, l\1adison. Wis con 9in.
BO ' TO S 1£TY OF CTVIL E NG ! EERS
DISCUSSION
DISCUSSION
BY H. J. B. HARDI NG*
DISCU SS ION
Bv G. L. McKENZIE* AND R. PETERSON**
and not shown on plans. The consultant will be more than pleased
to accept these shortcomings in the early stages in order to have
some assurance that investigational work will be carried on to pro-
vide the most useful information , rather than design studies which he
feels are not particularly pertinent.
The desirability of contact with the project through construction
~s becoming increasingly important with the tendency on major and
difficult earth work to modify the design as the job proceeds. This
makes it possible to utilize the more accurate soils information re-
vealed by excavations and also the observations which are generally
taken during construction . As pointed out by Professor Terzaghi,
there is a considerable difference between the necessity for such con-
tinuity in the fields of structural engineering and soils engineering.
There is an old adage which states that a poorly designed dam well
built may be far superior to a well designed dam poorly built. It is
therefore obvious that if a consultant is required at all, it would be
in the interests of those concerned to have him associated with the
project from its inception to its completion.
Professor Terzaghi has emphasized the importance of contact
between the design and construction departments in earthwork and
foundation engineering. In the Prairie Farm Rehabilitation Adminis-
tration we have found that good liaison between surveys and investiga-
tion , design, and construction can be accomplished by having an engi-
neering board composed of representatives of all three functions. This
board should function during the entire period of design and con-
struction and should inspect the project regularly during construction.
Our policy for years bas been to have all features of the design
of dams pertaining to or affected by the foundations and the materials
to be used in construction originate in the Soil Mechanics Section.
When construction is under way that section is required to maintain a
thoroughly qualified soils mechanics engineer on the project at all
times. He functions administ ratively under the Construction Engineer
and functionally under the direction of the Senior Soils Mechanics
Engineer. We have found from experience that this procedure works
satisfactorily and the Construction Engineer finds it relieves him of
tremendous responsibility. One important qualification is that the
soil specialist must be a practical man and recognize the fact that
textbook examples rarely occur in practice. Decisions must often
be made on the site without recourse to consultants or senior officers.
OCf ETY OF IL E 'G I:\f E ER
Dr cu IO
Bv JACOB Fno•
conditions and many deviations from safe and proper procedure. Yet
in the common law it is necessary to blame a single item that is known
as the proximate cause. It is one of the difficulties in expert testimony
for a consultant who is being pinned down and cross-examined on
this question of what caused it and what did not contribute to the
incident. The consultant in this type of_,work must be scrupulously
honest. If there is not p roof that a single cause existed, there is no
reduction in the value of his services to honestly say so.
The problem of how to treat a client soon becomes an important
question. Some consulting officers, usually the larger groups of
several partners and associates, find it necessary to maintain as either
associates or employees men who, although graduate engineers , are
really politicians. Possibly these men have previous background and
experience in related fields, but their purpose is to get work and
collect for it. Smaller organizations, fortunately , do not need such
help but a small or individual consultant should be warned to have
no connection with what in '\Vashington has been known as the ('Five
Percenters" group. If he cannot get the work on his own reputation,
he'd better do a little more studying and get a better reputation or
else leave the field.
The writer feels completely in accord with Dr. Terzaghi in the
over-all approach and agrees that if one is not interested in becoming
the largest firm in the world or the future owner of the most pre-
tentious mausoleum in the cemetery, the field of consulting engineer-
ing can be sufficiently remunerative to permit comfortable living and
sufficiently rewarding to permit a good life.
DIS CUSSION
BY R . M. HARDY *
the accuracy of their engineering data and that the contractor as-
sumed full responsibility for completion of the work at his bid prices
irrespective of the conditions encountered.
The job involved the excavation of a considerable yardage of
glacial till which the sub oil data classified as being dense but non-
cohesive. However, as the job progressed experience showed that
much of the glacial till was highly cemented and that it could not
be excavated by equipment usually used for " common excavation 11 •
It had to be quarried. Again , in this case, eventual adjustment of
payment for the work re ulted in the owner lo ing much of the ad-
vantages to him of competitive tenders for the work.
These two cases have the common factor that the contract docu-
ments attempted to make the contractor financially respon ible for
errors in judgment or even inadequate engineering on the part of the
owners ' engineering advisors. The inclusion of such clauses in con-
tracts and specifications may be dictated by the legal advisors to the
owners, and therefore the engineers concerned may have no say in
the matter. Moreover there is good reason to make a contractor
financially responsible for any risk on the job which can properly be
insured against, the cost of such protection becoming a part of the
cost of the work. However the ethical position of the professional
engineer is surely not too strong if he becomes a party to procedures
which place the financial responsibility for engineering deficiencies on
the contractor. Moreover the interests of the client, in the great ma-
jority of such cases, are not properly protected and the adequacy of
the engineering may be jeopardized. It is perhaps time that some
attention was given by professional engineers to the formulation
of a more equitable policy concerning responsibility in such circum-
stances.
DISCUSSION
Bv NORMAN D. LEA*
i commendable and much need d in the ngineer ing prof e ion where
the strange practi e has d veloped of r ferring to engine ring design
firms a con ulting firm · . lany engine ring acti itie are be t done
by a team but con ulting i basically an individual a tivity. It is true
that ometimes board of co n ultant are u ed. In medicine it is
common for doctor to be called in for con ultation. It i important
to note , however , that in both the_· in tances each individual con-
ultant opinion i con_idered on it own merit . \\'h en the chairman
of a con_ulting board i a wise administrator he weighs each consult-
ants opinion in the light of the con ultant's experience, training and
rep utation before reaching a decLion .
The ffici nt design and execution of the complex. engineering
a_.ignment now facing our profe_ ion require organization-oft n
into larg and complex companies. lost engineering is now being
done either by such ind pendent companies or by sim ilarly organized
ngineering depa rtmenL within even lar er co rporation or agencie .
Many individual spec ialL L within the e organizations perform in-
ternally th functions of a con ultant. They too are faced with ome
of the problem d scribed by the author. Engin ering organizations
do not normally have internally all of the specialized knowledge they
require and thus they may be exp cted to employ out ide consult-
ants whenever this will benefit a particular project.
From the author exten ive experience with engineering organi-
zations, he ha been able to point out four important shortcom ing ,
namely:
( 1) ompartmentaliz ed Organization. Organization ir1to depart-
ment for surveys de ign and con truction i not :\ defect
in it elf , but only when accompanied by inadequat com-
munications between groups or by incompetent taff. The
basic problem of communications i one receiving much
attention in admini trative ci rcl es the e day and it i cer-
tainly vital to engineering admini tration.
( 2) Incomp etent taff can get any organization into trouble.
, mid the pre ent lamoring for more engineer the prof e -
sion is in grave danger of de-emphasizing quality. There
i po iti evidenc indicating that there ha been no hort-
age of rank-and-file engineers in orth America during thi
century. There does eem to be a hortage in the upper
BO TON SOCIETY OF CIVIL EN ,fNEERS
The paper under discussion presented the thesis, that the success
of projects involving earthwork operations requires intimate coopera-
tion between the construction organization and the soil mechanics
division from start to finish, and not only during the design stage.
If this fundamental rule is disregarded failure may ensue in spite of
competent advice rendered by the consultant.
Although the paper was discussed by sixteen prominent engi-
neers with very different professional backgrounds, none of the dis-
cussers disagreed with the writer and each one of them contributed
thoughts, observations and experience records confirming the thesis.
The discussers represented the following categories: (a) Owners who
maintain permanent staffs for design or supervision, (b) Consulting
firms operating on a large scale in a great variety of fields, ( c) Full
time consultants assisted by a small organization or none at all, and
( d) Professor-Consultants .
(a) Owners Who Maintain Permanent Staffs for Design and
Supervision
G. L. MacKenzie and R. Peterson (Prairie Farm Rehabilitation
Administration, Saskatoon, Sask.) report that their organization in-
cludes a soil mechanics section, continuously engaged in maintaining
contact between the design section and the construction operations.
The soil mechanics section is assisted by a board of outside consult-
ants. R. F. Ogilvy (Aluminum Company of Canada) describes in
detail the duties which are assigned to the soils engineers in his
organization. They involve the maintenance of continuous contact
between the design department and the men engaged in construction
from start to finish for the purpose of detecting significant discrepan-
cies between assumed and real soil conditions before it is too late
to correct the design .
( b) Consulting Firms Operating on a Large Scale in a Great
Variety of Fields
Like all the other discussers, those associated with such firms
admit the importance of close cooperation between the design depart-
ment and the men in the field until the end of construction. M. H.
Cutler ( Stone and Webster Engineering Corporation) , F. A. Mars-
BOSTON SOCIETY OF CIVIL ENGL EERS
"no". "It is not necessary that every question that comes in be ac-
cepted as a commission " . Every independent consultant can limit
the commissions he accepts to the number compatible with his pro-
fessional development provided he has the required self-control.-
F. E. Schmitt ( formerly Editor of Engineering ews-Record ) ex-
amined the conditions described in the paper from a historic point
of view. He arrived at the conclusion that the recent rapid advance
of design and construction procedures was not matched by an equally
rapid development in the field of coordination. The discrepancy
between the improvement of the tools and the development of the
skills for coordinating the actions of the men using the tools has
temporarily thrown the mechanism of production in the field of earth-
work engineering out of gear.
(d) Professor-Consultants
A. Casagrande (Harvard University) discussed the dangers to
the consultant's reputation growing out of assignments which do not
permit the consultant to remain in intimate contact with the job until
construction is completed.-R. B. Peck (University of Illinois) points
out, that "the work ( of the Professor-Consultant) should not be rou-
tine or of a character within the ordinary scope of activities of the
practicing engineer." Compliance with this specification requires
rigorous self-control, which is by no means a common attribute of
the human species. However, if self-control prevails, a gifted Pro-
fessor-Consultant has a unique opportunity to become outstandingly
competent in his field. As R . 1\,1. Hardy (University of Alberta) says,
"contrary to opinions so widely held, experience in engineering work
is by itself no guarantee of a high degree of professional compe-
tence." Experience furnishes only the raw material and competence
is the result of a strenuous process of digestion.
Since each one of the participants in the discussion has a pro-
fessional personality of his own and since in addition, each one of
them has a broad background of experience in his particular line,
the discussions represent an outstandingly valuable supplement to
the contents of the paper. Therefore they deserve the attention of
every practising civil engineer and I wish to express my gratitude
to all those who gave the readers the benefit of their thoughtful con-
sideration of the topics of the paper.