Professional Documents
Culture Documents
Contoh Mining Cost & Road Construction Cost
Contoh Mining Cost & Road Construction Cost
2 3
Equipment type 1 PC 300 PC 300 PC 300
Material Ore OB direct dozing (60%) OB Hauling (40%) Total OB
Amount - WMT 953,753 1,532,457 1,021,638 2,554,095
Bucket cap - CUM (m3) 2.10 2.10 2.10
Bucket fill factor 1.10 1.10 1.10
TF 1.60 1.60 1.60
DT capacity - Ton 25.00 25.00 25.00
N - Number of bucket / truck 5.00 5.00 5.00
Load / truck - T 18.48 18.48 18.48
CP - Bucket cycle / pass - mins 0.50 0.50 0.50
TM - Truck manuevering - mins 1.50 1.50 1.50
FP - First pass bucket ~ mins 0.75 0.75 0.75
LT ~ Loading time / truck - mins 4.25 4.25 4.25
No of truck loaded / hr - ea 14.12 14.12 14.12
PC loading rate / hr - tons 260.89 521.79 782.68
PC total hours to complete 3,655.71 2,936.93 1,305.30
Eff working hour / day 14.00 14.00 14.00
Equiv number of days to complete 261.12 209.78 93.24
Number of days per week 7.00 7.00 7.00
Equiv week to complete 37.30 per month 29.97 13.32
Prod traget / week - T 25,568 102,270 51,135 76,703
D ~ haul distance - Km 12.00 4.00
S ~ ave truck speed, Km/h 25.00 25.00
TD - dumping time , mins 1.50 1.25
TM - Truck manuevering - mins 1.50 2.00
LT ~ Loading time / truck - mins 4.25 6.85
CT ~ truck cycle time - mins 64.85 29.30
Number of truck required ~ CT/LT 15.26 4.28
85 % PA 17.95 5.03
Rounded 20.00 5.00
Pre-Mining Works Hour-Meter N Total HM Rent cost Total Cost Total Item Cost Rp/Ton
1. Land Clearing
Bulldozer D85/D65 36 2.00 72.00 782,000 47,858,400
PC 200 36 2.00 72.00 450,000 27,540,000
Mining Works Hour-Meter N Total HM Rent cost Total Cost Total Item Cost Rp/Ton
6. TransShipment
Pc.300 (loading) 3,655.71 1.00 3,655.71 782,000 2,429,949,839
Pc.200 (Loading barges) 3,655.71 4.00 14,622.84 782,000 9,719,799,355
Pc.200 (unloading barges) 3,655.71 4.00 14,622.84 782,000 9,719,799,355
Dump Truck 3,655.71 6.00 21,934.25 450,000 8,389,852,384 30,259,400,933 31,726.66
3 3
Equipment type 1 PC 300 PC 300 PC 300
Material Ore OB direct dozing (60%) OB Hauling (40%) Total OB
Amount - WMT 461,500 1,164,000 776,000 1,940,000
Bucket cap - CUM (m3) 2.10 2.10 2.10
Bucket fill factor 1.10 1.10 1.10
TF 1.60 1.60 1.60
DT capacity - Ton 25.00 25.00 25.00
N - Number of bucket / truck 5.00 5.00 5.00
Load / truck - T 18.48 18.48 18.48
CP - Bucket cycle / pass - mins 0.50 0.50 0.50
TM - Truck manuevering - mins 1.50 1.50 1.50
FP - First pass bucket ~ mins 0.75 0.75 0.75
LT ~ Loading time / truck - mins 4.25 4.25 4.25
No of truck loaded / hr - ea 14.12 14.12 14.12
PC loading rate / hr - tons 260.89 782.68 782.68
PC total hours to complete 1,768.92 1,487.19 991.46
Eff working hour / day 14.00 14.00 14.00
Equiv number of days to complete 126.35 106.23 70.82
Number of days per week 7.00 7.00 7.00
Equiv week to complete 18.05 per month 15.18 10.12
Prod traget / week - T 25,568 102,270 76,703 76,703
D ~ haul distance - Km 7.00 1.00
S ~ ave truck speed, Km/h 25.00 25.00
TD - dumping time , mins 1.50 1.25
TM - Truck manuevering - mins 1.50 2.00
LT ~ Loading time / truck - mins 4.25 6.85
CT ~ truck cycle time - mins 40.85 14.90
Number of truck required ~ CT/LT 9.61 2.18
85 % PA 11.31 2.56
Rounded 12.00 3.00
Pre-Mining Works Hour-Meter N Total HM Rent cost Total Cost Total Item Cost Rp/Ton
1. Land Clearing
Bulldozer D85/D65 0 2.00 0.00 782,000 0
PC 200 0 2.00 0.00 450,000 0
Mining Works Hour-Meter N Total HM Rent cost Total Cost Total Item Cost Rp/Ton
6. TransShipment
Pc.300 (loading) 1,768.92 1.00 1,768.92 782,000 1,175,799,028
Pc.200 (Loading barges) 1,768.92 4.00 7,075.67 782,000 4,703,196,113
Pc.200 (unloading barges) 1,768.92 4.00 7,075.67 782,000 4,703,196,113
Dump Truck 1,768.92 4.00 7,075.67 450,000 2,706,442,776 13,288,634,030 28,794.44
3 2 1
Equipment type PC 300 PC 300 PC 300
Material OB Cut OB Fill Quary
Amount - m3 141,463 112,680 21,600 General Parameter
Bucket cap - CUM (m3) 2.10 2.10 2.10 Total Cut Vol. 141,463 m3
Bucket fill factor 1.10 1.10 1.00 Total Fill Vol. 112,680 m3
TF 1.00 1.00 1.00 Road - Length 6,000 m
DT capacity - Ton 25.00 25.00 25.00 Road - Wide 12 m
N - Number of bucket / truck 5.00 5.00 5.00 Quary Thick 0.30 m
Load / truck - T 11.55 11.55 10.50 Quary Vol. 21,600 m3
CP - Bucket cycle / pass - mins 0.50 0.50 0.50 Quary distance 6.00 Km
TM - Truck manuevering - mins 1.00 1.00 1.00
FP - First pass bucket ~ mins 0.75 0.75 0.75
LT ~ Loading time / truck - mins 3.75 3.75 3.75 Equipment Requirement
No of truck loaded / hr - ea 16.00 16.00 16.00 Pc.200 1
PC loading rate / hr - m3 554.40 369.60 168.00 Pc.300 4
PC total hours to complete 255.16 304.87 128.57 Bulldozer 2
Eff working hour / day 14.00 14.00 14.00 Rock Breaker 0
Equiv number of days to complete 18.23 21.78 9.18 Grader 1
Number of days per week 7.00 7.00 7.00 Vibro 1
Equiv week to complete 2.60 3.11 1.31 Dump Truck 10
Prod traget / week - m3 54,331 36,221 16,464 Water Truck 1
D ~ haul distance - Km 6.00
S ~ ave truck speed, Km/h 20.00
TD - dumping time , mins 1.25
TM - Truck manuevering - mins 2.00
LT ~ Loading time / truck - mins 6.85
CT ~ truck cycle time - mins 46.10
Number of truck required ~ CT/LT 6.73
85 % PA 7.92
Rounded 10.00
Road Construction Works Hour-Meter N Total HM Rent cost Total Cost Total Item Cost IDR/M3