Division of Responsibility (DOR) for Fabriction of Tank at BPCL

Barghar, Odisha

SN Description Client Bidder

A. DESIGN & ENGINEERING


1. Basic Design and GA drawings 
2 Detailed Engineering / Fabrication drawings 
3 Technical specification 
4 Bill of quantities 
5 As built drawings (6 hard copies & 6 soft copies 
in AutoCAD format CD)

6 Civil Foundation
B. SCOPE OF SUPPLY
1 Tank plates 
2 Structure, spiral staircase, platform, railing, 
gratings, etc
3 Nozzle pipes, flanges and plate material for 
manholes with cover and companion flanges.
4 Tank mountings (Valves, breather valves, 
Instruments etc.)
5 Water for Hydro test (as per 7.2.1) 
6 All other materials and equipment required for 
the job.
C. CONSTRUCTION AIDS / TOOLS
1 All construction Aids & Equipment 
2 Liftig Tools and tackles,Cranes,hydra 
3 Hydraulic jacks / power packs etc. 
4 Temporary ladders, Lighting, scaffolding etc. 
5 Fire screen wall materials including GI sheets, pipes etc. 
6 Hydro test pumps, calibration meters, temporary piping, 
etc.,

7 Temporary material for erection and hydro-testing like 


fasteners, gaskets, blinds, etc.
8 Any other equipment /tools required 

1
D. CONSUMABLES
1 All consumables required for construction like welding 
electrodes, gases, grinding wheel etc
2 Consumables required for inspection and testing work. 
3 Consumable for construction aids like fasteners for rafter 
alignment.

4 Other consumable materials 


E. CONSTRUCTION UTILITIES
1 Land,Electricity 
2 Water 
F. DOCUMENTATION
1 QAP 
2 Project Schedule 
3 Fabrication drawings and BOQ 
4 SOP for Erection, Testing, Welding, etc. 
5 WPS, PQR, WPQ 
6 Daily Progress Report 
7 Handing over documents consisting of internal inspection 
reports, RT films, As Built drawings, MTCs, welding
electrodes certificate, Hydro test certificate, Calibration
Report (duly certified by Weights and Measures
department), tank settlement readings, etc. – in 6 set of
spirally bind file and 6 CD for each tank
G. SCOPE OF WORK
1 Procurement of plates 
2 Unloading and Transportation of plates to required place 
from Storage yard to Tank Foundation.
3 Procurement of Structures, gratings, nozzles, pipes, 
flanges, etc.

4 Construction / Fabrication drawing. 


5 Preparations of material take off schedule. 
6 Overall quality control.  
7 Construction supervision and co-ordination work with 
owner / TPL
8 Tank calibration & certification (Legal metrological 
dept./CPWD)
9 Painting/coating of Tanks outer shell/ roof/ roof structure/ 
nozzle pipes/other structure etc.)

H. SCHEDULING
1 Detailed scheduling, monitoring and progress reporting 

2
I. QA/QC, INSPECTION AT SITE 
1 Carrying out all types of inspection and testing. 
2 NDT (UT, RT, MPT, DP etc.) facility at site (radioactive 
source, storage incl. necessary permissions & handling
facility, RT film developing / review facility etc.)
3 Preparation of inspection test reports 
4 Witnessing of Inspection / Tests & approvals of  
Inspection / Test Reports.
J. REPORTING
All reports required by client. 
K. INSURANCE
1 Bidder’s construction aid and temporary work. 
2 Workmen’s compensation 
3 Any other insurances as per statutory requirement 
4 License from local labour commissioner 