Professional Documents
Culture Documents
Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 166.00 to km 208.00 (Package-4)
on Aizawl-Tuipang section of NH-54 in the State of Mizoram on EPC mode with JICA loan assistance
Change of Scope for Tapering portion at Merging point of 2 Lane and Paved Shoulder to Existing Single Lane at Hnathial
Remarks
Refer Annexure - I
(2-1)
y Seven Only )
Annexure - I
Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 166.00 to km 208.00 (Package-4) on
Aizawl-Tuipang section of NH-54 in the State of Mizoram on EPC mode with JICA loan assistance
Change of Scope for Tapering portion at Merging point of 2 Lane and Paved Shoulder to Existing Single Lane at Hnanthial
Sl. No. Item of Work Unit Quantity Rate Amount (Rs.) Refer Rate Analysis Sl.
no.
A Road Works :-
A3 Granular Sub-Base conforming to Grading 1 as drainage layer Cum 357 3867.00 1381659.77 3
A6 (a) Providing tack coat with bitumen emulsion all complete as per
Technical Specifications Clause 503.
(i) On granular surface treated with primer @ 2.5 kg/10 sq.m. sqm 1700 22.00 37392.85 6.i
(ii) On Bituminous surface. @ 2 kg/10 sq.m. sqm 1686 29.00 48881.53 6.ii
B Retaining Wall :-
C Breast Wall :-
Rate Analysis
Road Works
1 301 Excavation in Soil by mechanical means
Excavation for road way in soil by mechanical means including cutting and
pushing the earth to site of embankment upto a distance of 100 metres (average
lead 50 metres), including trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
Unit = cum
Taking output = 1 cum
a) Labour & Machinery cum 1.00 122.00 122.00 Item No.
b) Labour Welfare Cess @ 1% on (a) 1.22 3.03
Cost for 1 cum = a+b 123.22
Rate per cum = (a+b) 123.22
say 123.00
Unit = cum
Taking output = 1 cum
a) Labour, Machinery & Material cum 1.00 590.00 590.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 5.90 3.16
Cost for 1 cum = a+b 595.90
Rate per cum = (a+b) 595.90
say 596.00
Unit = cum
Taking output = 1 cum
a) Labour, Machinery & Material cum 1.00 3950.00 3950.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 39.50 4.11
Cost for 1 cum = a+b 3989.50
Rate per cum = (a+b) 3989.50
say 3990.00
Unit = sqm
Taking output = 1 sqm
a) Labour, Machinery & Material sqm 1.00 48.00 48.00 Item No.
Annexure - II
Unit = cum
Taking output = 1 cum
a) Labour, Machinery & Material cum 1.00 14971.00 14971.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 149.71 5.04.ii
Cost for 1 cum = a+b 15120.71
Rate per cum = (a+b) 15120.71
say 15121.00
Unit = cum
Taking output = 1 cum
a) Labour, Machinery & Material cum 1.00 16613.00 16613.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 166.13 5.05.i
Cost for 1 cum = a+b 16779.13
Rate per cum = (a+b) 16779.13
say 16779.00
Protection/ Structural Work
9.0 304 Excavation for Structures
Earth work in excavation of foundation of structures as per drawing and
technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom and backfilling with approved material.
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 1 cum
a) Labour & Machinery cum 1.00 123.00 123.00 Item No.
b) Labour Welfare Cess @ 1% on (a) 1.23 12.01.B.i
Cost for 1 cum = a+b 124.23
Annexure - II
10 1500, 1700 Plain/Reinforced Cement Concrete complete as per Drawing and Technical
& 2100 Specifications.
12 1400 & Stone masonry work in cement mortar 1:4 for substructure complete as per
2200 drawing and Technical Specifications
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Labour, Machinery & Material cum 1.00 6930.00 6930.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 69.30 13.04.D
Cost for 1 cum = a+b 6999.30
Rate per cum = (a+b) 6999.30
say 6999.00
13.0 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation complete as per
& 2100 Drawing and Technical Specifications.
14 710.1.4.of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 aggregates satisfying the requirements laid down in clause 2504.2.2. of
and 2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over the
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and Technical
Specification.
Unit: cum
Taking Output = 1 cum
a) Labour, Machinery & Material cum 1.00 2550.00 2550.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 25.50 13.10
Cost for 1 cum = a+b 2575.50
Rate per cum = (a+b) 2575.50
say 2576.00
Annexure - II
Unit = No.
Taking output = 1 No.
a) Labour, Machinery & Material no. 1.00 1733.00 1733.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 17.33 13.08
Cost for 1 no. = a+b 1750.33
Rate per no. = (a+b) 1750.33
say 1750.00
Unit = 1 MT
Taking output = 1 MT
a) Labour, Machinery & Material MT 1.00 111976.00 111976.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 1119.76 12.04
Cost for 1 MT = a+b 113095.76
Rate per MT = (a+b) 113095.76
say 113096.00
17 1600 & Supplying, fitting and placing HYSD bar reinforcement in sub-structure
2200 complete as per drawing and Technical Specifications
Output: MT
Taking output = 1 MT
a) Labour, Machinery & Material MT 1.00 112258.00 112258.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 1122.58 13.06
Cost for 1 MT = a+b 113380.58
Rate per MT = (a+b) 113380.58
say 113381.00
18 2504 Providing and laying Pitching on slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete as
per drawing and Technical specifications
Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material & Labour cum 1.00 2647.00 2647.00 Item No.
b) Labour Welfare Cess @ 1 % on (a) 26.47 15.04.A
Cost for 1 cum = a+b 2673.47
Rate per cum = (a+b) 2673.47
say 2673.00
Quantity Estimation of Road Works
A At Bypass Start
1 a) Additional 2 Lane Section
BC 18 0.04 8.78 cum 6.32 A8
Prime Coat (On Bituminous surface) sqm 158.04 A6.ii
DBM 0.065 8.78 cum 10.35 A7
Prime Coat (On granular surface) sqm 159.21 A6.i
Tack Coat sqm 159.21 A5
WMM 0.2 8.78 cum 32.56 A4
GSB 0.2 8.78 cum 33.28 A3
Earthen Shoulder 0.46 cum 6.44 A2
Subgrade in filling portion 1.55 cum 27.90 A2
Excavation upto top of SG 45.82 cum 824.83 A1
2 b) Taper Section
BC 44 0.04 7.16 cum 12.60 A8
Prime Coat (On Bituminous surface) sqm 315.04 A6.ii
DBM 0.065 7.16 cum 20.66 A7
Prime Coat (On granular surface) sqm 317.90 A6.i
Tack Coat sqm 317.90 A5
WMM 0.2 7.16 cum 65.34 A4
GSB 0.2 7.16 cum 67.10 A3
Earthen Shoulder 0.46 cum 11.04 A2
Subgrade in filling portion 2.67 cum 117.48 A2
Excavation upto top of SG 5.02 cum 220.88 A1
B At Bypass End
1
a) Additional 2 Lane Section
BC 98 0.04 8.90 cum 34.89 A8
Prime Coat (On Bituminous surface) sqm 872.20 A6.ii
DBM 0.065 8.90 cum 57.11 A7
Prime Coat (On granular surface) sqm 878.57 A6.i
Tack Coat sqm 878.57 A5
WMM 0.2 8.90 cum 179.63 A4
GSB 0.2 8.90 cum 183.55 A3
Earthen Shoulder 0.46 cum 45.08 A2
Subgrade in filling portion 7.31 cum 716.11 A2
Excavation upto top of SG 57.96 cum 5679.69 A1
2
b) Taper Section
BC 57 0.04 5.97 cum 13.61 A8
Prime Coat (On Bituminous surface) sqm 340.29 A6.ii
DBM 0.065 5.97 cum 22.36 A7
Prime Coat (On granular surface) sqm 344.00 A6.i
Tack Coat sqm 344.00 A5
WMM 0.2 5.97 cum 71.08 A4
GSB 0.2 5.97 cum 73.36 A3
Earthen Shoulder 0.46 cum 26.22 A2
Subgrade in filling portion 7.92 cum 451.44 A2
Excavation upto top of SG 6.48 cum 369.36 A1
Summary
Sl.No. Item BOQ No. Unit Quantity
Summary
Sl.No. Item BOQ No. Unit Quantity
1 Excavation B1 cum 160.00
2 M-10 B2 cum 5.65
3 M-15 B3 cum 138.00
4 Fe-500 B4 MT 0.33
5 Filter Material B5 cum 28.80
6 PVC Pipe B6 nos. 61.00
7 Stone B7 cum 10.80
RRM Breast Wall
600
Average Height of Breast Wall= 3000 mm = 3 metre
Length of Breast Wall= 41000 mm = 41 metre
Sl.No. Item Grade Unit Length Breadth Height Area Quantity Refer BOQ Item No.
1 Excavation Excavation cum 41.000 2.450 1.715 4.202 172.272 C1
2 Weep Hole PVC Pipe Nos 124.000 C5 3000
3 PCC M10 Foundation M-10 cum 41.150 2.394 0.100 0.239 9.850 C2
4 Breast Wall RRM cum 260.924 C3
Section 1 41.000 0.600 4.200 2.520 103.320
Section 2 41.000 3.360 137.760
Section 3 41.000 0.484 19.844 1
6 Filter Media Filter Material cum 41.000 0.300 3.000 0.900 36.900 C4 4640
Road Level 2
1200
2200
3
440
PCC
2243.569 Thickness 100 mm
Projection 75 mm
Summary
Sl.No. Item BOQ No. Unit Quantity
1 Excavation C1 cum 180.00
2 M-10 C2 cum 9.85
3 RRM C3 cum 260.92
4 Filter Material C4 cum 36.90
5 PVC Pipe C5 nos. 124.00
Quantity Estimation of RCC Cover Drain
1.2
Sl.No. Item Grade Unit Nos. Length Breadth Height Quantity Refer BOQ Item No.
0.1 1 0.1