GUIDELINES
FOR THE IMPORT OF SCHEDULED
WASTESGUIDELINES
FOR THE IMPORT OF SCHEDULED WASTES
Published by:
Deparament of Environment
Ministry of Science, Technology and the Environment
13th Floor, Wisma Sime Darby
Jalan Raja Laut
50662 KUALA LUMPURPREFACE
‘The Guidelines are to assist waste handlers and manufacturers
who intend to apply for a written approval from the Director-
General of Environment, Malaysia to import scheduled wastes.
The importation of scheduled waste into this country for
disposal is not allowed. Waste imported and used as. raw
material by the manufacturing or processing industries may be
allowed under very stringent conditions. For this purpose, the
importers must show proof that the importation of such waste
cannot be avoided. It is to.be noted however, in using such
raw materials, there shall be minimum amount of residues left
for treatment and disposal.
‘The permission granted to the applicant will be on a case-to-
case’basis and the Diréctor-General is by no means obliged to
approve the application unless he is satisfied that there is no
better alternative. In this regard, ‘Malaysia being a party to
the Basel Convention on the Control of ‘Transboundary
Movements of Hazardous Wastes and Their Disposal 1989
(came into force’ for Malaysia on 6 January 1994) is strictly
following the procedures as outlined in the Convention.
‘The guidelines shali-be in addition to aiid not in derogation of
any written law.GUIDELINES
FOR THE IMPORT OF SCHEDULED WASTES
4d
24
Introduction *
‘The import of scheduled wastes as defined under the
Customs (Prohibition of Import) (Amendment) (No.3)
Osder 1993, for recovery or as raw matérial must
obiain prior writen opproval from Director-General of
Environmental Quality, Malaysia.
Submission of Information
The application to import scheduled wastes must be
submitted to the Department of Environment (DOE)
using AS 14 Form detailing inter alia the following
information:
@ names and addresses of waste importer and
receiving parties;
Gi). types and quantities of wastes;
Gi) physical characteristics;
(iv) chemical characteristics;
() justification for the import;wi)
wii)
(viii)
x)
methods of handling including collection,
packaging, labelling, transportation and
transport route. (Note: The method of
handling the wastes, especially packaging and
labelling, must conform to international code of
practice);
@ complete curriculum vitae of the personnel
supervising the collection, packaging, transport
and other related works;
emergency response plan describing steps to be
taken by parties concemed in case of
spill/accident/fire which may occur during
transportation (by land, sea, or air) from the
premises of waste generator to the port of.
entry. (Note: The plan must include a
description on the action to be taken in clean-up
operation, the equipment and safety apparels to
be used, etc);
a written agreement between the exporter,
importer, transport agents (land, sca, and air)
and the party receiving the wastes. This
agreement shall specify inter alia:
@ parties responsible for clean-up
operation in case of spill. and
emergencies; and
Gi) the responsibility. of the exporter to
retrieve the waste when denied entry3.1
3.2
3.3
4.2
5.1
(%) a copy of an insurance coverage for the
shipment.
Conditions of Application
‘The importers must apply to the Director General of
Environmental Quality, at Jeast 90 days prior to
importing scheduled wastes.
All documents such as the agreement, and approvals
submitted to DOE must be of the original-or certified
true copies.
A valid Bank Guarantee for the scheduled waste
shipment process should be deposited ‘with the DOE.
when requested for. The Bank Guarantee will be
returned upon fulfillment of the conditions ‘of the
shipment.
Process of Application
‘The procedure involved in processing an application
for importing scheduled wastes is shown in Appendix
A.
Important Notice
In accordance with the requirement of Basel
Convention on the. Control” of Transboundary
Movements of Hazardous Wastes and Their Disposal
1989, the Competent Authority of the exporting
country should notify the Government of Malaysia of
the intended shipment of the scheduled waste.5.2
5.3
5.4
5.5
5.6
No shipment shall proceed unless the Competent
Authority of the exporting country received the
approval from the Government of Malaysia.
‘The transportation of scheduled waste in Malaysia shall
be carried out by a DOE licenced transporter.
‘The intended transporter can apply the licence from the
DOE by using DOE form AS 1 & AS 13 obtainable
from the Head Office or the DOE State Offices.
‘The importer must ensure that the waste is handled by
a DOE licenced/approved facility,
Failure to submit complete information will result in
the rejection of the application.Appendix A
LOW CHART
FOR THE IMPORT OF SCHEDULED WASTES:
Complete the fore aint
somite BSEiS
Information complete?
No. Fecumy tcenced/approwed
by 00k eaipencica
i
Cc) tages
insu approval later
sS'cpiem
comply?
‘Retr the Bank
Seplicent