(a) Define procurement planning
Procurement planning refers to a process of identifying and consolidating requirements
and determining the timeframes for their procurements with the aim of having them as
and when they are required.
(b) What are the key contents of a typical public procurement planning
The following are the key contents of a typical public procurement plan
Subject of the procurement: This refers to any item of procurement in the form of
goods, services or works that need to be purchased.
Source of funding: This refers to where the funds to be used in the procurement of
goods, works or services are to e got from for example government, donors and grants.
Currency: This refers to ta system of money in general use in a particular country for
example in public procurement we can use shillings, dollars or euros while procuring
goods, works or services.
1|Page
(C ) Using the information provided above (and any other source of information you may require, if you do), prepare
a procurement plan for KDLG for the FY2020/2021
Module 40,0
2(public 00,0
procurement) 1 00
23/
40,0 08/
Module 3(LG 00,0 202
financial mgt) 1 00 0
KDLG/w Installation
orks/2020 Of
/2021/004 Culverts(qua
rter 1)
10,0
4 Points along 00,0
Kidduuka 24 00
3|Page
KDLG/w Drilling of 5
orks/2020 Boreholes
/2021/005 (quarter 2)
15,0
00,0
Kigamba P/S 1 00
kigamba 15,0
Central 00,0
Acadamy 1 00
15,0
00,0
Buganga P/S 1 00
15,0
00,0
Lugando P/S 1 00
15,0
00,0
Ntende P/S 1 00
Drilling of 4
Boreholes
(quarter 4)
15,0 admeas
00,0 GOV uremen
Kafu P/S 00 135,00 ERN Quot t 6/10 10/1 16/1
Muganzirwaz 0,000( MEN ation contrac wor /202 13/10/ 1/20 1/20
za P/S 15,0 UGX) T s t ks 0 2020 20 20 30/12/2020
4|Page
00,0
00
15,0
00,0
Kazzo P/S 00
29/
15,0 11/
00,0 202
Gengera P/S 00 0
KDLG/su
pplies/20
20/2021/0 Office
07 supplies
22,5
00,0
Quarter 1 1 00
22,5
00,0
Quarter 2 1 00
5|Page
22,5 202 20 020 2020 08/
00,0 0 202
00 0
KDLG/w Classroom
orks/2020 Blocks(quart
/2021/009 er 2)
A 4 classroom
block at 600,
Muganzirwaz 000,
za P/S 1 000 admeas
1050,0 GOV uremen 11/
A 3 classroom 450, 00,000 ERN Open t 1/10 24/1 30/1 12/
block at 000, (UGX MEN Biddi contrac Wor /202 28/10/ 1/20 1/20 202
Kazzo P/S 1 000 ) T ng t ks 0 2020 20 20 0 30/12/2020
Design &
KDLG/se dev't of
rvices/20 Architectual
20/2021/0 plans
10 (quarter 1)
A 4 classroom
block at 25,0
Muganzirwaz 00,0
za P/S 1 00 GOV framew
A 3 classroom 43,000 ERN ork Ser 16/0 18/0 24/0 4/9/
block at 18,0 ,000( MEN quota contrac vice 7/20 22/07/ 8/20 8/20 202
Kazzo P/S 1 00,0 UGX) T tion t s 20 2020 20 20 0 30/09/2020
6|Page
00
KDLG/su
pplies/20 Classroom
20/2021/0 Furniture(qu
11 arter 1)
200,
Kigamba P/S 40 000
200,
Kigumba P/S 40 000
200,
Buganga P/S 30 000
Classroom
Furniture(qu
arter 2)
200,
Lugando P/S 40 000
200,
Ntende P/S 30 000
200,
Kafu P/S 30 000
Classroom
Furniture(qu
arter 3) GOV lumpsu
64,000 ERN m Sup
Muganzirwaz 200, ,000( MEN Quot contrac plie
za P/S 50 000 UGX) T ation t s
7|Page
200,
Kazo P/S 40 000
24/
2/7/ 08/
200, 202 8/7/20 4/8/2 11/8/ 202
Gengera P/S 20 000 0 20 020 2020 0 30/03/2021
KDLG/su Purchase OF
pplies/20 Ten Motor
20/2021/0 cycles(Quart
12 er 1)
Sup
7,00
plie
0,00
s
Education 6 0
GOV lumpsu 24/
7,00 70,000 ERN m 2/7/ 08/
0,00 ,000( MEN quota contrac 202 8/7/20 4/8/2 11/8/ 202
Health 4 0 UGX) T tion t 0 20 020 2020 0 30/09/2020
KDLG/w Construction
orks/2020 of maternity admeas
/2021/013 ward at Kazo GOV restri uremen Wor 27/
1
Health centre 400, 40,000 ERN cted t ks 1/4/ 14/0 05/
II (Quarter 000, ,000( MEN biddi contrac 202 14/04/ 10/5/ 5/20 202
4) 000 UGX) T ng t 1 2021 2021 21 1 30/06/2021
KDLG/se
GOV
rvices/20 Compound Ser
100,00 ERN Quot
20/2021/0 Cleaning & vice
0,000( MEN ation
14 Maintenance s
UGX) T
Quarter 1 1
8|Page
25,0
00,0
00
framew
25,0 ork
00,0 contrac
Quarter 2 1 00 t
29/
25,0 6/10 10/1 16/1 11/
00,0 /202 13/10/ 1/20 1/20 202
Quarter 3 1 00 0 2020 20 20 0 30/12/2020
25,0
00,0
Quarter 4 1 00
Purchase Of
KDLG/su Heavy Duty GOV lumpsu 27/
450,
pplies/20 Road Roller 1 450,00 ERN Open m Sup 11/1 14/1 12/
000,
20/2021/0 Truck 0,000( MEN Biddi contrac plie 0/20 11/11/ 8/12/ 2/20 202
000
15 (Quarter 2) UGX) T ng t s 20 2020 2020 20 0 30/12/2020
Purchase Of
KDLG/su Heavy Duty GOV lumpsu Sup 17/
320,
pplies/20 Printing 320,00 ERN Open m plie 5/1/ 26/0 03/
000,
20/2021/0 Machine 0,000( MEN Biddi contrac s 202 1/2/20 2/20 4/3/2 202
000
16 (quareter 3) 1 UGX) T ng t 1 21 21 021 1 30/03/2021
9|Page
(D) Briefly, explain what is meant by “linking the procurement plan to financial
estimates and/or budgets”. What is the source of financial estimates used for such
purpose?
Linking the procurement plan to financial estimates refers to a point where user
departments draw their budgets and procurement components are correlated with those
that they submitted in the departmental procurement plan.
The source of financial estimates used for such purpose is a market survey.
(E) Assuming today was 20th October 2020 (i.e. during the second quarter of
2020/2021) an earth quake hits KDLG causing loss of property such as houses, food
(gardening) etc.…, creating emergency procurement need for construction of
community houses for settling –in of the surviving victims, outline the procedure
you would undertake to undertake such procurement(s) (make reference to the
relevant legal provisions that may apply)
There has to be justification for emergency; Here the procurement officer clearly
explains what happened, what caused the emergency .therefore the emergency should not
have been caused intentionally by an individual or a group of individuals.
Approval from the accounting officer; Here the accounting officer approves the
justification of the emergency as per the evidence provided by the procurement officer
and approves it to be considered and therefore the procurement of the emergencies can
begin.
Receipt of bids or quotations: Here bids are obtained from a list of pre-qualified bidders
who are evaluated there and then and the best bidder is got.
Award of contract: Here the best bidder is awarded the contract immediately after the
evaluation.
1) The legal provisions that apply here are section 85 of the PPDA act which states that
direct procurement will be the method of procurement used under such an emergency
10 | P a g e
situation where exceptional circumstances prevent the use of competition and therefore
goods are procured using a direct procurement method.
2) The other legal provision that applies is that direct procurement shall be used to achieve
timely and efficient procurement where the circumstances like emergencies don’t permit
the use of competitive methods.
3) The other legal provision that applies is that a letter reporting about the emergency
procurement is sent to the public procurement and disposal authority and a copy brief to
the contracts committee informing it about the emergency procurement
ACCOUNTING OFFICER
The accounting officer helps to determine the source of funding that is where the funds to
be used for the purchase of requirements are to be got from.
The accounting officer also carries out market surveys to determine the prevailing market
prices and give estimated costs.
The procurement and disposal unit also helps in giving of submissions to the contracts
committee for approval.
CONTRACTS COMMITTEE
The contracts committee helps in approving of the plan.
11 | P a g e
EVALUATION COMMITTEE
The evaluation committee helps in evaluating the different bidders who have applied to
provide different goods, works and services to the procuring and disposing entity.
The public procurement and disposal authority helps in regulating the procurement and
disposal activities of the entity. that is how the procuring and disposing entity carries out
its procurement plans and activities and whether they are in accordance with the laws.
USER DEPARTMENTS.
They help to draw specifications of the different items needed. The specifications can be
performance specifications and conformance specifications for example in terms of
quality, quantity and design.
User departments also give timelines to the procurement and disposal unit on when the
requirements are needed.
12 | P a g e