Professional Documents
Culture Documents
9/1/2009 1 9/1/2009 2
9/1/2009 3 9/1/2009 4
1
During revamp, further reduction of load may be possible
when cooling water header is in two distinct separate
Cooling Water failure directions. Here by considering pumps and CT fans for both
Whenever there is one cooling water system, cooling directions from two different sources of power may serve to
water failure loads for various units are added to reduce flare load. IOCL Mathura & Baroda have used this
calculate total flare load of the complex. concept during revamp to use their existing flare system.
For a large complex with very high flare load for
cooling water failure case, complex may be segregated
in to two or more cooling water systems and then flare
load of one (controlling ) cooling water system may be
considered for further design.
9/1/2009 5 9/1/2009 6
Power Failure
Power distribution may be from 6-8 substations
which are fed from the main source of power supply.
Main source of power could be captive, grid power or
captive in parallel with grid power. Total power failure
There are three possible situations of power failure. It gives rise to loss of reflux to towers which results in
Local power failure of a reflux pump for a column in relief of gross overheads from each tower.
a particular unit causing reflux failure of that column. It may give rise to cooling water as well as steam
failure.
During tripping of steam generation /BFW system,
9/1/2009 7 9/1/2009 8
2
supply of steam to unit reboilers is limited to system In case of high flare loads, a review is to be
hold. done to check, if by adopting suitable control
philosophy, flare load can be brought down. For
Other considerations are described below: example, tripping source of heat to reboiler by
sensing pressurization of column overhead with
Miscellaneous for Flare load reduction methods
2 out of 3 voting of pressure switches, CRL
In certain cases, by suitably changing the design
pressure of a few equipment, flare load can be brought reduced their CDU flare load.
down. For high temp relief from Hydrogen unit etc
ISBL header is sized as per actual temperature
during relief but OSBL header is maintained of
CS because CS can withstand expected high
temperature for the duration of relief.
9/1/2009 9 9/1/2009 10
3
failure of pump downstream of a vessel. increase in Detailed causes of overpressure are as follows:
heat input (failure of a valve to shut off fuel to a fired Closed outlets on vessels
heater, increase in heat transfer caused by increase in The inadvertent closure of a block valve/ control
LMTD in a re-boiler and fire). valve on the outlet of a pressure vessel (while the
Decrease in heat removal (loss of cooling water, air plant is on stream ) may expose the vessel to a
condenser failure, loss of heat removing circulating pressure that exceeds MAWP. Pressure relief is
side stream). required unless lock open facility are in place.
Accumulation ={IN – OUT } (heat or mass ) Inadvertent valve opening
The inadvertent opening of any valve from a source of
higher pressure , such as HP steam or process fluids.
This action requires pressure relieving unless
provision are made for locking or sealing the valve .
9/1/2009 13 9/1/2009 14
Utility failure
The consequences that may develop from the loss of
any utility must be carefully evaluated. Typical utility
and affected equipment are given in table-1.
9/1/2009 15 9/1/2009 16
4
Partial failure Another example with two pumps in parallel with one
Effect of overpressure due to loss of a utility should be pump providing full flow and second as standby,
studied with chain of developments that could occur Second pump has separate source of energy and is
and reaction time involved. The situation in which the equipped with controls for automatic start up if first
equipment fails but operates in parallel with equipment pump fails. No protective credit is taken for stand by
that has different energy source, operating credit may pump because stand by device is not considered totally
be taken for unaffected and functioning equipment. reliable.
An example of CWS with two pumps in parallel with
Manual cut in of auxiliaries is operator and time
unrelated energy sources, if one of two sources of
energy fails, partial credit may be taken for other dependent and must be carefully analyzed before it is
source that continues to function. Quantity of excess used as insurance for overpressure.
vapor generated depends on quantity of CW lost.
9/1/2009 17 9/1/2009 18
9/1/2009 19 9/1/2009 20
5
Loss of instrument air or Electric Power
The complexity of instrument automation require Reflux failure
continuous sources of air or electric power. To The loss of reflux as a result of pump or instrument
minimize likelihood of overpressure, fail safe position failure can cause overpressure in a column because of
of each control valve should be established as an condenser flooding or loss of coolant in fractionating
integral part of design. process.
Failure position of each control valve is not considered Abnormal heat input from reboilers
adequate relief protection as other failures in an Reboilers are designed with specified heat input. When
instrument system can cause a control valve to move in they are new or recently cleaned, additional heat input
direction opposite its failure position. above normal design can occur. In the event of failure
of temperature controller, vapor generation build up
pressure.
9/1/2009 21 9/1/2009 22
the cause, HP steam will overpressure equipment on the system. It is a type of overpressure that can not be
low pressure side of the exchanger. The possible controlled with pressure relief valve because response
of PSV is normally slow.
pressure rise need to be ascertained to determine
The oscillating peak pressures, measured in
whether additional relief would be required if flow
milliseconds, can rise to many times the normal
from tube rupture were to discharge in to the low operating pressure. These pressure waves damage the
pressure system. pressure vessels and piping.
Water hammer is frequently caused by quick closing
valves. Where water hammer can occur, use of
pulsation dampeners should be considered.
9/1/2009 23 9/1/2009 24
6
Steam Hammer Plant Fires
An oscillating pressure surge, called steam hammer,
Fire is a cause of overpressure in plant equipment.
A provision for controlled shut down or de-pressure
occur in piping that contains compressible fluids.
system for the units can minimize overpressure caused
Most common occurrence is initiated by rapid valve
from exposure to external fire.
closure. To limit vapor generation and spread of fire, facilities
The oscillating pressure surge occurs in milliseconds, should also include removal of liquids from the
with a possible pressure rise to many times the normal systems.
operating pressure, resulting in vibration & violent Normally operating product withdrawl systems are
movement of piping and possible rupture of equipment. considered superior and more effective for removing
Avoiding use of quick closing valves may prevent liquids from a process unit, compared with separate
steam hammer. liquid pull down systems.
2500 M2 plot should be considered for a single fire
zone.
9/1/2009 25 9/1/2009 26
Liquid holdup required for normal plant operations, Process changes/Chemical reactions
including refrigerants or solvents, can be effective in
In some reactions and processes, loss of process
keeping the vessel wall cool & does not require removal
system. control may result in significant change in
Provision may be made either to insulate the vessel, s
temperature and/or pressure .The result could exceed
vapor space and apply external water for cooling or to intended limit of the material selected.
de pressure the vessel using a vapor de pressure system. For cryogenic fluids, pressure reduction can lower
Area design should include adequate surface drainage temperature below minimum allowable design temp
facilities and a means for preventing spread of of equipment, causing low temp brittle failure.
flammable liquids from one operating area to another. For exothermic reaction cases, excessive temp and/or
Easy access to each area and to process equipment for pressure associated with run away reactions may
fire fighting and their equipment. reduce allowable stress level below design point, or
Fire hydrants, fire fighting equipment, and fire monitors increase pressure above MAWP.
should be placed in readily accessible locations. Where normal PSV’s can not protect, controls are
needed to warn of changes outside intended
temp/press limits to provide corrective action.
9/1/2009 27 9/1/2009 28
7
Determination of Individual relieving rates
Sources of Overpressure Effects of Pressure, Temperature , and Composition
Liquid or vapor rates to establish relief requirements Pressure and temperature affect the volume and
are developed by heat input(indirect pressure input composition of liquid and vapor.
through vaporization or thermal expansion) and direct Vapor is generated when heat is added to liquid. The
pressure input from higher pressure sources. rate at which vapor is generated changes with
Overpressure may result from one or both of these equilibrium conditions.
sources.
When liquid is a mixture of components with
The peak relieving rate is the maximum rate that must
different boiling points, heat introduced produces
be relieved to protect equipment against overpressure
due to any single cause. vapor that contains more low boiling components.
Probability of two unrelated failures occurring
With more heat input, successively heavier
together is very remote & normally not considered. components are generated in the vapor.
9/1/2009 29 9/1/2009 30
Effect of Operator Response If all outlets are not blocked, capacity of unblocked
The response to take credit for operator response in may properly be considered.
determining max relieving conditions requires Sources of overpressure include pump, compressor, HP
consideration of those who are responsible for headers, stripped gases from rich absorbent, and
operation and an understanding of the consequences of process heat. In case of heat exchanger, closed outlet
an incorrect action. Commonly accepted time range for can cause thermal expansion or vapor generation.
response is between 10-30 minutes, depending on
complexity of plant. Effectiveness of this response
depends on process dynamics.
1. Closed Outlets
To protect a vessel or system from overpressure when
all outlets are blocked, capacity of relief device must
be capacity of source of pressure.
9/1/2009 31 9/1/2009 32
8
Quantity to be relieved should correspond to set 2.0 Cooling or Reflux failure
pressure plus overpressure instead at normal General
conditions. Required relieving rate is determined by heat and
material balance of the system at relieving pressure.
If source of liquid is pump then flow-head pump In a distillation system, rate may require calculation
characteristics should be used to establish relief with or without reflux.
flow. Frictional losses at relieving flow and static head Instead of detailed calculations, simple bases is as
must also be considered to match pump curve. follows:
The compressor flow- pressure characteristics should 2.1.1 Total Condensing:
be considered in vapor service. Relief load is total incoming vapor to condenser
recalculated at temp that corresponds to new vapor
composition at set pressure plus overpressure, and
heat input prevailing at the time of relief.
9/1/2009 33 9/1/2009 34
9/1/2009 35 9/1/2009 36
9
4.0 Overhead Circuit 6.0 Overhead Circuit plus pump around
In many cases reflux failure due to pump shut down An overhead circuit plus pump around is arranged so
or valve closure can cause flooding of condenser, that simultaneous failure of pump around and
which is equivalent to total loss of coolant with overhead condenser will not occur, part failure of one
capacity established with above mentioned method. with complete failure of other is quite possible.
Compositional changes caused by loss of reflux may Required relieving capacity is similar to above
produce different vapor properties that affect mentioned.
capacity.
7.0 Side stream reflux failure
5.0 Pump Around
Principles similar to overhead circuit and pump around
Relief requirement is vaporization rate caused by an
apply for condenser flooding or changes in vapor
amount of heat equal to heat removed by pump properties resulting from change in composition.
around circuit. Latent heat of vaporization would Relieving capacity should be enough to relieve
correspond to latent heat at relieving conditions of vaporization rate caused by amount of heat removed
temp and pressure. from system.
9/1/2009 37 9/1/2009 38
cause overpressure to relief as downstream may not from liquid to vapor is so fast and large that PSV can not
be provided. So proper design and operation are
be adequate to handle increased flow. Each individual essential. Avoid water pockets, provide steam
case must be studied for its process and condensate traps, and double block with bleed on
instrumentation characteristics. water connections to hot process lines.
9.0 Accumulation of non-condensables
Normally noncondensables do not accumulate, but
with certain piping configuration, noncondensables
accumulate to the point that condenser is blocked.
Effect is equal to total loss of coolant.
9/1/2009 39 9/1/2009 40
10
Capacity Credit
11.0 Failure of process stream automatic controls: For relief evaluation due to any cause, control valve is
General: assumed in normal condition at relieving conditions.
Automatic control devices, directly actuated from Inlet Control Devices
process or indirectly from a process variable (P, T,
There may be single or multiple inlet lines fitted with
Flow, Level) are used at inlets or outlets of vessels or
systems. When transmission signal (or operating control valves, scenario is to consider one inlet valve in
medium to final control element (valve operator) ) fails, fully open position regardless of the control valve
control should assume either fully open or fully closed failure position. Opening of this control valve may be
position. Design of control valve has to be kept in mind caused by instrument failure or mis operation.
for relief evaluation.
9/1/2009 41 9/1/2009 42
9/1/2009 43 9/1/2009 44
11
When process systems involve significant differences Outlet Control Devices
in pressure level and volume of vapor contained by
high pressure equipment side is less than volume of Each outlet control valve should be considered both in
low pressure side, additional pressure may get fully open or fully closed position for purposes of flare
absorbed in some cases without overpressure. load determination. This is regardless of control valve
In the event of loss of liquid level, vapor flow in to failure position and may be caused by instrument
low pressure system depends on Interconnecting failure or mis operation.. If one or more of inlet valves
system, which usually consists of wide open valves
and piping, passes with a differential pressure based are opened by same failure that caused outlet valve to
on normal operating pressure on upstream and close, pressure- relieving device may be required to
relieving pressure downstream equipment, this DP at prevent overpressure.
initial conditions result in critical flow & may cause
rate to be several times higher than normal flow to
HP side. Unless make up equals outflow, as this will
be for short duration, upstream reservoir is depleted,
relief should be sized to handle peak flow.
9/1/2009 45 9/1/2009 46
Relief capacity is difference between max inlet & max If normal instrument operation results in increased
outlet flows @ relieving conditions. Also effect of relieving rate then consider instrumentation to operate, if
inadvertent closure by operator has to be considered. normal instrument operation results in decrease of
For single outlet with control fail close, relief is max relieving rate then consider instrumentation fail to operate.
inlet flow at relieving conditions. Fail Stationary Valves
For application with more than one outlets & one outlet Even though some control devices are designed to remain
with fail close control device, relief is difference stationary in the last controlled position, one can not
between max expected inlet flow and design flow @
relieving conditions. predict the position of the valve during failure. Designer
For applications with more than one outlet each with should consider such devices fully open or closed : no
control device, relief is max expected flow @ relieving reduction in relief capacity should be considered when
conditions. such devices are used.
9/1/2009 47 9/1/2009 48
12
Special Capacity Considerations
Although control valves are specified and sized for
In extreme cases , state of fluid controlled may
normal operating conditions, they are expected to change (from liquid to vapor or from vapor to liquid).
operate during upset conditions, including periods Wide open capacity of control valve selected to
when PSV s are relieving. handle liquid may differ greatly when it handles gas.
Valve design and valve operator capability should be
This becomes a matter of particular concern where
selected to position valve plug properly in accordance loss of liquid can occur, causing the valve to pass
with control signals during abnormal conditions. high pressure gas to a system sized to handle only the
Since the capacity at pressure relieving are not same as vapor flashed from normal liquid entry.
normal conditions, capacity of control valves should be
11.0 Abnormal Process Heat Input
calculated for relieving conditions of temp and pressure
Required capacity is max rate of vapor generation at
in determining required relief capacity.
relieving conditions (including non- condensables
produced from overheating) less the rate of normal
condensation or vapor outflow.
9/1/2009 49 9/1/2009 50
Internal Explosion
Designer should consider potential behavior of system and
Where overpressure against internal explosions caused
each of its components .For example built in over capacity
by ignition of vapor air mixture is to be provided,
of burners capable of 125 % of heater, design input must be rupture discs or explosion vent panels should be used.
considered. Relief valve react too slowly to protect the vessel
Where limit stops are installed, wide open capacity should against the extremely rapid pressure build up caused
be used. However if mechanical stop is installed and is by internal flame propagation.
adequately documented, use of limited capacity may be Vent area required is a function of initial
appropriate. T/P/composition, Flame propagation properties,
In shell and tube heat exchangers, heat input should be volume of vessel, pressure at which vent activates, and
calculated on the basis of clean conditions. maximum pressure that can be tolerated during vented
explosion.
9/1/2009 51 9/1/2009 52
13
12.0 Chemical Reaction
Peak pressure reached during vented explosion is
usually higher than pressure at which vent device Typical methodology for chemical reactions need
pressure relief where possible or other design
activates. strategies like automatic shut down systems, inhibitor
Design should follow NFPA 68 and 69. injection, quench, de-inventorying, alternative power
Inert gas purging may be used when explosion is due to supply, and de pressure.
air 13.0 Hydraulic Expansion
contamination during shut down or start up. It is due to increase in liquid volume due to increase
in temperature. It may be due to blockage of cold
liquid in exchanger with hot liquid on other side,
heating of long pipelines with solar radiation.
Typical relieving device is ¾ inch x 1 inch relief
valve.
If this size appears to be inadequate then procedure
given in API-521 (Section3.14.3 ) may be used.
9/1/2009 53 9/1/2009 54
9/1/2009 55 9/1/2009 56
14
External Fire Vertical Vessel
Effect of fire on wetted surface of a vessel Aw = p L D + N p D2 x1.66/4
The surface area wetted by internal liquid contents of a L- Length of vessel exposed to fire, ft
pressure vessel is effective in generating vapor when D-Diameter of vessel, ft
exposed to fire. To determine vapor generation , only that N-Number of heads exposed to fire (assumes
portion of the liquid which is wetted by its internal liquid elliptical head)
and is equal to or less than 25 ft above the source of flame.
Credit can be taken for insulation, if it is fire proof and
Liquid- vessels-(such as treating vessels )
project specification allows for this credit. It should be Wetted surface of vessels that operate liquid full should
certain that basic insulating material to function effectively be total surface with in 25 ft height.
up to 904 0C during a fire. This period of fire may be up to Fractionating Column-Wetted surface will be based on
two hours, depending on fire fighting provisions. Although high liquid level (API-normal liquid level plus tray draw
jacketing and coating may burn off or disintegrate, off capacity) in the bottom plus wetted surface
insulation must retain its shape. Hence no credit is taken corresponding to four(API-weir height+2 inch) inches of
for any insulation.
liquid for any tray with in a height of 25 ft. from grade.
9/1/2009 57 9/1/2009 58
9/1/2009 59 9/1/2009 60
15
Sizing:
Heat Absorption Equations
Amount of heat absorbed by a vessel exposed to open
fire is affected by type of fuel feeding the fire, degree
Gas Cooling-Surface area is equal to bare tube area. to which vessel is enveloped by flames(function of
Liquid Cooling-Wetted surface area is equal to bare tube vessel size and shape) and fire proofing measures.
area. Fire loading in case of liquid coolers may become Following formula is used to evaluate these
conditions where there are prompt fire fighting
extremely large and in some cases ,dominant loading in efforts and drainage of flammable materials away
sizing major portion of relief system. from vessel.
Exposed Height -Since air coolers tend to produce a Q = 21000 F A 0.82
chimney effect by drawing hot combustion products in to Q-total heat absorption to wetted surface in BTU/hr
their plenums, height limit on fire exposure may not apply. ft2
F=1(No credit for insulation)
A-Total wetted surface in ft2
9/1/2009 61 9/1/2009 62
9/1/2009 63 9/1/2009 64
16
For vessels with hydrocarbon and water as immiscible
phases, both phases exert their individual pressure and
whenever sum of vapor pressures equals relieving
pressure, relief valve opens and temp of liquid at this
point is relieving temp. Vapor composition relieved
would be such that molar ratio of hydrocarbon vapors
and water vapor would be in the ratio of their vapor
pressure.
9/1/2009 65 9/1/2009 66
9/1/2009 67 9/1/2009 68
17
Process engineer to calculate max relieving temp , if Example-For a gas storage vessel(CS) operating at
it exceeds 400 0C,sprinkler system to be provided. 20-40 0C, Specification for relief is as below ;
Following equation may be used for relieving temp Vessel wall temp 593 0C
calculations, Gas Operating temp 20-40 0C
Operating pressure 5.35 kg/cm2 g
T2=P2 x T1/P1 set pressure 38.5 kg/cm2g
P2- 1.2 x Set pressure, kg/cm2 a Vessel surface area Total area including shell and
dished ends
P1-Operating pressure, kg/cm2a
Maximum gas temp @ relieving pressure
T1- Gas Operating temp, 0K
P1/T1=P2/T2
T2-Max gas temp at relieving pressure, 0K T2=1.2x39.5 x(273+40)/6.35
=2336 0K or 2063 0C > 400 0C
Provide automatic sprinkler system besides relief valve
9/1/2009 69 9/1/2009 70
9/1/2009 71 9/1/2009 72
18
Effect of local power failure such as pump failure can
cause loss of cooling water(due to flooding of condenser) Heat Transfer Equipment Failure-Tube Rupture
or loss of reflux. General:
Intermediate power failure may cause more serious effects An internal failure can vary from a leaking tube or tube
than other two failures. Depending on the method of sheet to a complete tube rupture where a sharp break
dividing various pumps and drivers among electrical occurs in one tube. For relatively low pressure equipment,
feeders, it is possible to lose all the fans of an air cooler at tube failure is not a contingency when design pressure of
the same time that the reflux pumps are lost. This can low pressure side is equal to or greater than two thirds the
flood condenser and may void any credit for natural design pressure of high pressure side.
convection of air condenser. Tube rupture is a contingency when design pressure of
Total power failure requires additional study to analyze low pressure side is less than ten by thirteen of design
and evaluate combined effects of multiple equipment pressure of high pressure side. If high pressure side of
failures. Special consideration should be given to effect of exchanger operates at 1000 psig or more and contains a
simultaneous opening of relief valves in several services vapor or liquid that can flash or result in vaporization,
to a closed system. complete tube failure should be considered.
9/1/2009 73 9/1/2009 74
9/1/2009 75 9/1/2009 76
19
Flow of non-flashing liquid, Effect of LP flow on downstream fluid
W=1985 d2 (DP r)1/2 No heat transfer occurs
W= mass flow rate, lb/hr If no heat transfer occurs, high pressure fluid will initially
d= tube ID, inches displace an equal volume of low pressure fluid. As the
DP=pressure differential, p s i casualty progresses, high pressure fluid will be relieved
r= upstream density, lb/ft3 directly. The relieving requirements for both time intervals
should be calculated and the largest requirement chosen.
Flow of vapor or two phase mixture
W=1985 Y d2 (DP r )½ Heat transfer occurs
If heat transfer occurs, the effect of both heat transfer and
W= mass flow rate, lb/hr
volume displacement must be considered. (If the effect of
Y=net expansion factor for compressible flow, Refer
heat transfer is large when compared to displacement,
figure-A21 from Crane , or as conservative approach, use
0.8 effect of volumetric displacement may be ignored).
d= tube ID, inches
r=vapor density, lb/ft3 (for two phase flow, use no slip
density) 9/1/2009 77 9/1/2009 78
20
-Heat transfer with phase change Design pressure of low pressure side=55psig
Usually the volumetric displacement is insignificant in ∆P across all trays= 10 psi
this situation. Pacc @ column bottom=1.1(55)+14.7 +10 =85.2 psia
-Calculate bubble temp of liquid phase at relieving P1=112 psig or 126.7 psia
conditions. Sp Gr=0.815
-Calculate change in enthalpy in the hot phase as it is ρ=0.815 x 62.36= 50.82 lb/ ft3
cooled down to bubble point of liquid phase. Since hot oil is non flashing HP fluid, equation for non
-Use enthalpy change of hot phase to vaporize bubble flashing liquid should be used.
point liquid.
Example
Hot oil is HP fluid, From exchanger specification sheet,
tube diameter=3/4 inch,14 BWG
d= 0.584 inch
9/1/2009 81 9/1/2009 82
W=1985 d2 ( DP r)1/2
=1985(0.584)2 [(126.7-85.2) 50.82]1/2
=31090 lb / hr
THANKS
9/1/2009 83 9/1/2009 84
21