Professional Documents
Culture Documents
Part 1 Page 1
inhaltsverz
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 80
Maintenance schedule Page 1
General 83.1
· All screw connections ·
· Battery ·
· Hydraulic couplings ·
- condition and tightness
· Hydraulic hoses ·
- condition and tightness
Electrics 83.6
· Proper function of the total system ·
After all maintenance tasks and before putting the vehicle / hydraulic power pack into
operation again, a functional check of all items as well as a driving test must be made.
After these single maintenance tasks, the periodic maintenance tasks must be performed
and complied with. (See WA Partl 1, Section 2, Chapter 21.1)
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 81
Maintenance schedule Page 1
Cleaning 82.2
If necessary · · Hydraulic power pack X
General 83.1
· · · All screw connections ·
· · Battery ·
· · · Hydraulic couplings ·
- condition and tightness
· · · · Hydraulic hoses ·
- condition and tightness
· · Air filter · X
Electrics 83.6
· · · · Proper function of the total system ·
· · Battery ·
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 81
Maintenance schedule Page 2
After all maintenance tasks and before putting the vehicle / power pack into operation
again, a functional check of all items as well as a driving test must be made.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 82
Lubrication Chart Page 1
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 82
Lubrication Chart Page 2
82.2.1 General
Regular cleaning of the vehicles is a first essental for a correct maintenance and makes it easier to opera-
te the vehicles and its controls.
The legal requirements are to be complied with as far as the handling and the disposal of cleaning agents
and/or auxiliary means are concerned.
The following points must be observed when cleaning the vehicles with steam
jet:
· do not use any cleaning agents which attack paints, seals, synthetics and chrome or which degrade
the environment.
· do not clean any electric components (plugs, sockets, distributor boxes, etc...)
and their immediate environment with steam jet.
· do not aim at bearing points, lubrication points and hydraulic connecting units with steam jet.
· do not clean chrome parts with steam jet.
· do not clean radiator fins wutg steam jet (high-pressure)
· do not clean bearing points of the steering (”Callasto seals”) with steam jet.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 1
Basically, all maintenance tasks must be performed with the engines switched off and
in a de-energized state and with the vehicle ignition and the battery man switch swit-
ched off.
Exceptions are made for some maintenance steps which are necessary for adjust-
ments, trial runs or driving tests. In this case, the maintenance staff must take suitable
precautions.
During load tests of the hydraulic system (high pressure up to 250 bar) any leaks
which may possibly occur in the high-pressure part can be highly dangerous.
After all maintenance tasks and before putting the vehicle into operation again, a
functional check of all items as well as a driving test must be made.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 2
83.2.1 General
Maintenance tasks on the hydraulic system must be performed by trained and authori-
zed personnel only.
The maintenance tasks on the hydraulic system are mainly limited to the hydraulic reservoirs, the hydrau-
lic valves, the hydraulic filters as well as the hydraulic cylinders. All other components of the system do
not need a special maintenance.
However, the hydraulic pipes and the hydraulic hoses must be checked for damage and leaks at regular
intervals.
We recommend to have the pipes and hoses of your vehicle inspected in a specialist work-
shop after 5 years at the latest. After that period, further inspections must be made every
year.
Only absolutely clean hose couplings ensure the tightness of the system.
In case of long downtimes of the vehicles, the coupling halves must be greased and closed
with protective caps.
Do not pressurize uncoupled loose halves as they stand only maximum 160 bar. That
is why they must be screwed onto blind coupings.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 3
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 4
Working steps: (1 - 4)
1. Loosen filter element (1) and remove it.
2. Replace seal ring and lubricate with hydraulic oil before its installation.
3. Fit the filter element (observe tight fit and tightness).
4. Tighten the filter element so that it can be opened by hand.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 5
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 6
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 7
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 8
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Maintenance and Service Sec 8, Chapter 83
Maintenance schedule Page 9
83.6.1 General
The maintenance tasks on the electric system are mainly limited to a check of the electric connections
and the electric lines.
All other components of the system do not need a special maintenance.
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239
Picture index
part 1 Page 1
bildverz
SK, Kuhn/06.2000/10.2001/12.2002 Goldhofer Aktiengesellschaft ··· Donaustraße 95 ··· D - 87700 Memmingen WA Part 1/2
THP-Allg. Phone +49 (0)8331/15-0 ··· FAX +49 (0)8331/15-239