Professional Documents
Culture Documents
common. Wells are usually directionally drilled parallel to the c. Risks will be categorized as impacting areas of
trapping fault and encounter multiple stacked pay sands. safety, financial, environmental, or combinations
Typically, only one well is required to recover the thereof. Risk mitigations will be identified as well.
relatively small amount of reserves contained in these small e. Comparisons with other industry policies (be they
closures. prescriptive, probabilistic, etc.) will be made as
The current well design consists of a short conductor string much as practical.
(9-5/8”) to 1000’ TVD and surface casing (7”) set just above 4. Perform a professionally facilitated risk assessment on
the Shallowest Evaluation. The Shallowest Evaluation is the the list of scenarios. The risk assessment team would
highest known hydrocarbon, typically between 4000’ and consist of drilling professionals from various
5500’ TVD. The surface hole is drilled with sea water and a ChevronTexaco entities, service companies and field
motor BHA. This hole section has very low compressive personnel.
strength and drills at rate up to 500 feet per hour, including
connections. On wells where the target alignment allows, all Outside Project Scope
the directional work is done in this surface hole section. Up to 1. Geological target sizes and shapes.
8000’ MD of 7” surface pipe is run. A 6-1/8” rotary assembly 2. Redefinition of the existing COTL survey policy.
with adjustable gauge stabilizers is used to drill the reservoir 3. Overall directional planning and survey management.
section to TD’s varying from 9000’ to 13000’ MD. A 2-7/8” 4. Positional uncertainty of the seismic boat.
completion string is cemented in the open hole. 5. Errors in seismic acquisition and processing.
The survey program calls for MWD’s in each hole section 6. Interpretative creative license and or errors in drawing
with a gyro run in the 7” casing prior to drilling out with the 6- the structure maps.
1/8” BHA. All wells are batch drilled and the overall process The exclusions noted above are mainly related to errors
is similar to an automobile assembly line. The current average associated with processes external to well bore positioning
time from spud to rig release is six (6) days. An example practices. For the purposes of this study we assumed that
wellpath is shown in Figure 1. errors do exist for other processes that relate to definition of
any target set. Errors such as those associated with positional
Project Objectives, Work Scope uncertainty of a seismic vessel, seismic acquisition and
The primary objective of the study was to evaluate COTL's processing and interpretations in constructing the maps from
Collision Avoidance policy from design and execution which the targets are based are just a few examples. It was
standpoints, with the intention of developing a risk assessed thought that inclusion of these error types into this study
step change for improvement in overall well construction would add another dimension of complexity that would dilute
efficiency, via the enabling of closer proximity drilling to the effectiveness of the main project scope.
adjacent well bores. The key project driver was defined as For item 3 however, we found it necessary to perform a
enabling the drilling of faster, lower cost wells, for more wells perfunctory review of the process of planning and survey
per rig year, via improved well construction efficiency. The management as they relate directly to one of the main tenets of
following general work scope was developed to achieve this the recommended changes to the policy.
goal.
Review of Existing Collision Avoidance Practices
Within Project Scope As part of the study, a complete review of pertinent industry
1. Use the current survey policy as a given, with the literature relating to Anti-Collision and Collision Avoidance
exception that gyro surveys will now be run in theory, history and practice and was performed. Significant
exploration wells. work in this area by Walstrom(1,2,3), Wolff and deWardt(4,5),
2. Review Collision Avoidance policies from other Thorogood(6,7), Burton(8), Brooks and Wilson(9) and
ChevronTexaco business units, vendors and other Williamson(10,11) were used as the basis for this effort. In
operators. addition to the literature review we solicited several major
3. Develop a tabular list of collision scenarios, for use as a operators, service vendors and other ChevronTexaco business
design & execution guide, using the following criteria. units for their existing Collision Avoidance policies. The
a. All scenarios that deviate from the current Collision purpose of this exercise was to gain some insight to past and
Avoidance guideline will undergo a facilitated risk current industry collision avoidance practices, explore
assessment, whereby the following will be potential improvements, select a collection of the most
assessed; probability of collision occurrence, down effective, and propose a model that best fit the goals of this
side potential of the occurrence, likelihood of study. Another invaluable source of information was data
successfully remediating such an occurrence, and gathered by Coker(12,13) in a survey to ISCWSA participants
potential cost impact. Recommended clearance regarding collision avoidance practices. In a survey of users of
factors for each scenario will be assigned as well. his company’s software, Codling(14) shows the various AC
b. Each scenario will take into consideration the options used in Collision Avoidance planning (Figure 2). It
various hole sections, depths, depth differential is interesting to note that the most frequently used AC option,
between wells, and pore pressure differentials is not to use it at all, but leave it as is.
between wells. While performing the reviews mentioned in the previous
paragraph we found several models/procedures that existed
among the other major operators that could be used to meet
SPE/IADC 92554 3
the goals of the study. However, we also found that the is needed to accommodate a normal drilling program of more
various models that existed were either too restrictive or too than 200 wells per year.
liberal depending upon the location of the reference well to the
offset well in terms of true vertical depth. We believed that it Execution Rules
was necessary to tailor any modifications to the procedure so The well paths generated during the planning exercise were
as to align more closely with the majority of actual operations used in the drilling programs and executed by the offshore
scenarios present in COTL operations. drilling personnel. During the drilling process Clearance
What follows is a review of the process that existed at the Factors were calculated by from the actual surveyed position
time of the study, the proposed alternate process that met the (and tool specific error model) of the drilling well.
project goals and a description of the tools that have been With the extremely high penetration rates seen in Gulf of
developed as a result of this review that aid the new process. Thailand operations, it is not always possible to maintain the
programmed wellpath. The actual wellpath is drilled such that
Previous Collision Avoidance Policy the “spirit” of the plan is maintained so that collision problems
COTL was using a conventional error ratio calculation method would not arise. As with any drilling operation, occasions do
to flag possible well interference problems during the well arise where the drilling well may approach an offset well such
planning process. The industry uses several descriptors for that the Clearance Factor drops below 1.5. For situations such
error ratio, i.e., Proximity Ratio, Separation Factor and as these, a number of decision points (or rules) were set based
Clearance Factor (CF as it will be referred to for sake of on the calculated clearance factor that governed what actions
continuity in this paper). This value is determined by dividing were to be taken should a certain clearance factor be exceeded
the current calculated center to center distance between the while drilling the well.
well being planned (reference well) and an existing offset well The close approach rules (and their triggering clearance
by the sum of the positional uncertainties (calculated at two factors) used while drilling were:
sigma) of the two wells along the horizontal closest approach
distance between the two wells. The error model used for Stop Drilling 1.00
planning the reference well is a good magnetic model which Drilling Manager Approval 1.25
provides an acceptable level of confidence for the error Shut in Adjacent Wells 1.50
ellipses. (Note that for all future planning exercises it was
recommended to incorporate the use of the ISCWSA error This method is appropriate for preventing intersections
models that have been developed for the tool assigned to the where the consequences of a collision could lead to a
well plan.) significant safety or environmental event or major financial
loss. In the majority of cases these problems occur in shallow
The equation for this method is as follows: sections of the wellbore where it may not be possible to
maintain well control should a collision occur. Conversely,
D(Center to Center ) the method is found to be severely restrictive for the optimal
Clearance Factor = CF = …(1) positioning of deeper sections of a well where the magnitude
Er + Eo of outcomes from the intersection of two wells is not as great.
In the particular case where a development well is positioned
Planning Rules close to an exploration well whose reservoir characteristics are
Prior to the study the practice for well design in COTL called understood, the current collision rules when applied at the
for the engineer (well planner) to plan the well trajectory so as reservoir prevent a well being drilled within 200’ of an
to intersect a certain target set provided by the Asset Team. existing well. This can result in a significant amount of
As the wellpath was developed, the well planner would run a reservoir not optimally exploited.
Collision Avoidance scan to determine if there were any
potential problems with adjacent wells, either existing or A Risk Based Collision Avoidance Model
planned. In order to meet the goals of this study we found it necessary
As a guideline, a Clearance Factor of 1.5 was used as the to develop a procedure that could use both the existing
associated allowable approach distance for any well and is the Clearance Factor procedure for confidently avoiding shallow
trigger for Collision Avoidance conflicts. If the Collision (severe outcome) collisions, and a new, less conservative
Avoidance scan showed a conflict then an iterative process procedure for use in deeper sections of wells where the
was initiated that saw the well planner and Asset Team revise outcome of a collision would not be as severe. Through
targets and well plans until there existed a target set that analysis of the data referenced above and with some additional
allowed for the drilling of the well without the existence of a research, we have developed a model that meets the stated
collision issue, i.e., a Clearance Factor of greater than 1.5. The objectives. The methodology of this procedure is described
planning cycle for any new project would progress until a set below.
of wellpaths and their associated targets were produced that fit
the boundary conditions. It is important to note that this Planning Matrix
iterative process was inefficient and created a significant Every nearby well detected by a clearance scan will be
amount of unproductive time to the overall process. classified into its associated scenario via use of the COTL
In any planning cycle it is not uncommon to be working Planning Matrix. This matrix of scenarios was developed
three or more well platforms with 20 wells per platform. This specifically for use in COTL well planning operations and was
4 SPE/IADC 92554
validated via a Quantitative Risk Assessment (QRA). The transition from the current method to a risk based method,
QRA process is described in some detail later in the paper. which is the basis of determining close approach tolerances for
The left side of the matrix is used to identify the scenario that wells at increasing depths. This risk based approach will be
most applicable to the type of collision that could occur discussed later in this section.
between the well being planned and the well identified in the
clearance scan. Table 1 shows this relationship. The four intervals of Clearance Factor and their relative
This compilation of scenarios was developed to address the risk of collision are shown in Table 2.
majority of collision situations that could arise given the
current types of wells that are being and have been drilled in Table 2 – COTL Planning Matrix Clearance Factors
COTL’s operating area. In the future, if a different collision
Results Using Conventional Separation Factor
situation develops due to operational or area changes then this
portion of the matrix will require modification. The authors SF < 1.0 1.0 < SF < 1.25 1.25 < SF < 1.50 SF > 1.5
stress that the QRA effort and resulting planning matrix output P < 400 400 < P < 5000 5000 < P < 90000 P > 90000
is very specific to the operation in Thailand. We believe that
it is repeatable for other operations using the same process.
Note that Probability (P) represents the relative (e.g. 1 in
Table 1 – COTL Planning Matrix Well Scenarios P) risk of collision given the worst case scenario. This is the
most conservative approach to the derivation of Probability as
Collision
Location Pressure Regime it relates to Clearance Factor. This is for a situation where two
Description
wells have equal ellipse sizes at a two sigma confidence level.
MW >= BHP of Offset
Conductor
FG <NMW > BHP of Offset options on the left side and clearance factors at the top resulted
MW >= BHP of Offset
in what is called the COTL Planning Matrix. The complete
Matrix is seen in Figure 3.
Surface
Section
MW < BHP of Offset would carry a significant risk to personnel, the environment
and/or unacceptable financial risk would be classified as High
FG <NMW > BHP of Offset
and those that presented negligible risk to personnel and the
MW >= BHP of Offset environment in the event of a collision would be classified as
Conductor
Low. Some caveat for depth was also included that accounted
Section
MW < BHP of Offset for the fact that shallow collisions were not warranted under
Collision with Abandoned Well
Table 3 – COTL Collision Avoidance Planning Category 2 captures two types of mitigation. The first
Categories being physical, for example the interfering offset well has its
QRA Risk SCSSV closed and the well is depressurized. The second type
Resulting Action
Score of mitigation would be economic such that below a certain
depth, risk of a deep collision can be understood from the
costs associated with the possible loss of the offset well plus
1 No action required.
the costs to control and sidetrack the current well verses the
economic gain associated with drilling closer to the offset.
Even in this case it would be prudent to follow a standard
Drillable well based on physical mitigation if required shut-in / bleed-off procedure for a close production or
(barriers below collision point, annulus pressure, etc.) injection well. The process for determining the economic
2
and/or validation by economic model. Requires
Drilling Manager approval. based minimum well separation is discussed below.
For the specific case of COTL, there are several other
mitigating factors that were determined that would not allow a
Not drillable due to risk to personnel, facility or well to be identified as a Category 1 (Clearance Factor greater
3
reservoir damage or reputation than 1.5) well no matter the circumstance. These factors were
also verified during the QRA of the Collision Matrix. Firstly,
the very high penetration rates seen in the upper sections of
This categorization tool was developed with input from the wells would not allow ample time for categorization via
COTL operations personnel. During its development it was the economic risk based system. Secondly, the fact that
stressed that the final product could be used by Asset surveys may not be taken (while drilling) at each stand could
Management personnel as a planning tool or guide and still increase the potential for a collision should less conservative
provide clear direction towards the safest path that is clearance distances be used. Finally, it may be more efficient
ultimately supervised by and the responsibility of the Drilling from a well planning standpoint to use the error based rules
department. The following caveat was also put in place to since the additional work associated with risk based planning
provide a clear path of responsibility for the overall planning may not be cost effective.
and execution phases. Additionally, it could be the case where a well is classified
In the course of evaluating well planning scenarios with as category 3 along its entire length as a result of the analysis
this tool a situation may arise where a classification conflict described above.
occurs. An example would be a situation where an Asset
Team evaluates a scenario one way and the drilling Category 1 – No Action Required
department another. In situations like this it is stressed that This category is used for wells that require no additional
the drilling department has the responsibility for safe action as they are currently planned. Some examples of
operations and is therefore the ultimate decision making collision scenarios with offset wells are:
authority. They will have the final decision on any An offset well that was identified during a clearance
classification conflict. scan but does not encroach with a Clearance Factor of
Each category is described in detail below. less than 1.5 at any depth.
An offset producing well where the closest approach is
Considerations Relating to Depth – Classifications 2 and 3 in the reservoir section, the mud weight in the planned
For the purpose of this study it is necessary to define an well is greater than the mud weight in the offset well
acceptable vertical depth for each planned well where a and the Clearance Factor is greater than 1.25.
collision below that depth can be determined not to present a An offset abandoned exploration well where the closest
significant risk of surface damage or escape of hydrocarbons. approach is in the surface section, the mud weights are
This vertical depth may be at an intermediate casing point or equal and the Clearance Factor is greater than 1.0.
below where a SCSSV is set for producing or injection wells.
For the drilling well, it will be a depth where a reservoir (or Category 2 – Drillable Well with Mitigation
offset well) pressure kick can be safely detected and This category is used for wells that are deemed drillable based
controlled. Calculations involving programmed mud weight, on the presence of physical mitigation if required (barriers
shut-in pressure and fracture gradients will be required to below collision point, annulus pressure, etc.) and/or validation
establish at which depth the risk classification changes. by economic model. If the economic model is used then
Above this depth the well would be classified into either approval from the Drilling Manager is required.
category 2 or 3 and the traditional Clearance Factor or no-go An example of a physical mitigation requirement would be
type rules will apply. Clearly collisions above this depth could an interfering offset well where the SCSSV is closed and the
potentially lead to blow-outs resulting in loss of property, life well is depressurized. As a result of the QRA analysis some
and/or reputation. The traditional ‘no-go’ and ratio type scenarios that required mitigation previously now do not
collision procedures where properly implemented have never require it as long as the distinct Clearance Factor (and
resulted in a collision to our knowledge. “Properly” means associated distance) is maintained.
that the procedures are followed and the correct survey The second type of mitigation would be economic such
instrument error models are applied. that depending on the scenario, the risk of a collision can be
determined through an analysis of the risk associated costs of
6 SPE/IADC 92554
drilling closer to an offset verses the beneficial economic gain than the level of economic risk which is very difficult to
associated with drilling closer to the same well. The process quantify.
for determining the economic based minimum well separation In his paper, Williamson(10) also discusses the need for
is discussed below. consideration of ‘off-design’ events, or ‘gross’ errors, the
distribution of survey errors and the imprecision of the risk
Category 2 – Economic / Risk Based Separation assessment itself. While these are still unquantifiable, the
Minimum Separation Distance following points are provided as a qualitative guideline for the
A risk based separation distance must be determined along the user to aid in determining an overall weighting factor that is
vector between the two wells of interest. (The appropriate applied to the pure economic assessment. Values for this
selection of this vector is discussed in Appendix B.) This is weighting factor, in practice, have ranged from 20 to 200
the minimum allowable distance that a reference well can depending on the circumstance and the user.
approach an offset well. Williamson(10) outlines a method for
determining the minimum safe distance (S) a drilling well Geometry of Collision. While a close approach 90
(reference) can approach an offset well. degree intersection may be more risky (more likely)
than a parallel one, it is also short lived in that once you
are past the well the risk is gone. Parallel and high
⎛ dr + do ⎞ dr + do
S = σ 2 ln ⎜⎜ ⎟⎟ + …(2) angle intersections present a greater window of
⎝ ACRσ 2π ⎠ 2 collision opportunities from an along the well depth
standpoint.
Where: Consequences of a Collision. How would a collision
impact the current planned operations? Is there a
σ = σ r2 + σ o2 critical path for this well with regard to the drilling
program? Will a bad outcome affect the reservoir
Several efforts (entailing considerable analysis) were made management strategy? Basically, what is the intangible
to devise a more refined probability of intercept but when the effect on the overall operation?
results were compared to this method the differences were Well Planning and Execution. What is the confidence
negligible. This method has two advantages level in the definitive database? How could the
misapplication of survey references, corrections or
a) It can be reversed to determine the probability of survey tool error model codes affect the outcome? Are
collision based on actual calculated separation your survey management and quality control
distances. procedures of good quality? How confident are you in
dr + do ⎧ [S − (d r + d o ) / 2 ]2 ⎫ the people executing the work? What experience do
P= exp ⎨ − ⎬ …(3) they have in situations of a similar nature? How likely
σ 2π ⎩ 2σ 2 ⎭ is it that they will recognize an encroachment and take
the proper action before a collision takes place or be
b) It is conservative when it needs to be, i.e., when the able to deal with the consequences of a collision if one
casings are wide and the combined survey errors are does occur?
tight. This is necessary for collision analysis at Quality of QRA Analysis. How much confidence do
shallower depths. you have in the estimation of costs of collision, costs of
avoidance and overall value of the well?
Allowable Collision Risk Risk and Reward. What additional risk associated
Allowable collision risk, ACR (also referred to as cost are you willing to assume in order to achieve your
Tolerable Collision Risk(10)) is the value of collision goals? What fraction of the value of the well are you
probability which is used to determine the minimum well willing to forfeit in order to achieve them?
separation for a close approach between wells. It represents
the maximum probability of collision considered acceptable As a result of our study a worksheet was developed to aid
for a particular close approach. For example, the economic the Drilling Engineer (well planner) and Asset Team derive a
risk of a deep collision can be understood from the loss of the reasonable and defendable value of this probability depending
offset well plus the cost to control and sidetrack the current on the specific circumstances of each operation.
well and potential loss of production. For rapidly drilled wells
and for ones that have a short lifespan, the level of purely Use of the Model in Commercial Well Planning Software
economic risk can be alarmingly low. Example calculations The well planning program that is used by COTL has been
for several scenarios in our area of interest showed risk values modified to calculate values of P as defined in equations (2)
of 1 chance in 4. At these levels of risk and dealing with the and (3). Inputs to the program include ACR, minimum TVD
position uncertainty below the transition depth it is possible to from which to apply the rule (transition depth) and a default
drill right through the offset wellbore. Fortunately, most distance should the separation distance drop below a
drilling engineers are of the mindset that says “you must not calculable level.
drill into another well” or one must at least actively take some
avoiding action. So there is a perceived level of risk higher The software’s Collision Avoidance report shows the
calculated values of Minimum Separation Distance, actual
SPE/IADC 92554 7
1
CF * ( E r + Eo ) + * (d r + d o ) …(6)
2
The well radii have been added to the equation for continuity
sake with the calculation of the risk based separation distance
described in the previous section.
8 SPE/IADC 92554
Table 4 – Planning Matrix Notes Based on this categorization, the drilling group proceeded with
Notes the analysis.
1 New Mud Weight required in new well at collision point to Fortunately, the previous operator had kept good records
control Bottom Hole Pressure (BHP) on offset well
exceeds last shoe test in new well.
which allowed for good confidence in performing a risk
2 The following factors should be used to determine if the analysis on the situation. The well history indicated that 7”
classification (2) is valid for the specific collision issue. casing had been run and cemented to TD, and that 9’5/8”
a What is the confidence level of the data from the casing had been set where we the current operator would
offset well in question? If it is an abandoned normally set 7” casing. DST data indicated that none of the
well, was it drilled by COTL?
b What is the actual Probability of Collision as
zones of interest were above expected pressures. The
calculated by the Well Planning Software? abandonment program was sound with cast iron retainers and
c What is the collision geometry? Is it a sharp cement plugs. A 500’ cement plug had also been set across
approach where there is only a brief chance of the 9-5/8” shoe, below our potential collision point. Given
collision or are the wells near each other this data it was deemed that the only exposure at the closest
providing a prolonged chance of collision?
d Is there a method other than well surveying that
approach point of 3930’ TVD would be economic, i.e, risk to
can validate the position of the two wells? I.e., people, environment, or reputation was not expected.
Lithology. The planner had produced two wellplans that could
e If the offset well has been abandoned or shut-in, intersect the desired target sets. One required an extra trip in
what methods, barriers etc., were installed above the 6-1/8” hole for directional work, estimated at $100,000.
and below the targeted collision point.
f Is the offset well cased at the targeted collision This well path maintained a CF of 1.0. The preferred well
points? plan accomplishes all the turn in the 8-1/2” hole, and had a CF
g If collision with the offset well would require of .4. The cost of collision was estimated at $500K,
increasing the mud weight, what is the feasibility accounting for plug back & sidetrack if realized.
of increasing the mud to the desired weight?
Uisng a risk factor of 50 the team arrived at an Allowable
h The shoe design of the current well is sufficient
to handle a kick Collision Risk of 1 chance of collision in 250. This value was
3 Evaluation must consider the potential additional costs then input into the well planning software and run again for
validation.
a Costs associated with setting physical barriers in The results of the analysis showed that at the closest point
this hole section of approach, the actual distance between the two wells was
b Costs associated with not being able to retrieve a
plug from an offset well
150 feet, and the minimum separation allowed (given the
c Costs for added drilling complexity to achieve a bounds of 1:250) was 82 feet, indicating a Risked Clearance
desired SF Factor of 1.83. Instructions were then inserted into the
4 Assumes that current mitigation policies as outlined in wellplan that guided the close drilling rules (and allowable
Section 1 of the Collision Avoidance procedure are approach distances) for this particular instance.
followed regarding physical barrier placement and
depressuring requirements for offset wells.
5 Classification is driven by economic understanding rather Study Results & Conclusions
than physical mitigation 1. As a result of the study, the current planning and
Minimum separation distance to facilitate execution is execution guidelines for wells with respect to
based on a calculated acceptable risk tolerance Collision Avoidance considerations have been
6 Special mitigation methods are required if close approach
drilling is chosen modified. The revised method provides for more in-
COTL Drilling Operations is responsible for developing depth analysis of a unique potential collision scenario
these methods based on the following parameters; collision type,
7 Collision Avoidance with respect to Abandoned wells is potential collision location (TVD), pressure regime
only for valid for open water wells
Wells abandoned on platforms have many variations and
and Clearance Factor determined in an initial
need to be addressed on case by case basis and are not Collision Avoidance scan. Depending on the
in the scope of this template. combination of these parameters a well is placed into
one of three categories outlined in Table 3. The
Case History colors used to highlight each category are significant
During a typical platform site well planning exercise, the well in that they represent a stop light approach to well
planner identified a potential conflict between a planned and planning. The outline for the new Survey and
an abandoned exploration well. The exploration well had Collision Avoidance Policy is seen in Table 5.
been drilled by a previous operator in 1994. The collision
scan showed a Clearance Factor of 1.25 occuring in the
surface section of the well. Using the matrix (Figure 3), a
scenario was identified as follows; collision with an
abandoned well in the surface section with the possibility that
the mud weight used in this section could be less than the
bottomhole pressure in the abandoned well. The matrix
guideline indicated that the well could be drilled (Category 2,
with mitigation) as designed if the risk analysis supported it.
SPE/IADC 92554 9
x
ε − x2 / 2
FP ( x ) = ∫
−∞ 2Π
dx …(A.2)
Appendix B - Projected Vector Discussion The Direct Vector method assumes that there is no
This study diverged from the standard techniques used in confidence in the direction of the two wellbores relative to
determining the Projected Vector between wells. An alternate each other. Generally the directions are normally known to
method for computing the survey error in the direction better than 1 degree (1 sigma), while the position uncertainties
between the two wellbores and used in the probability are commonly worse than 100ft (30m) for a deep collision
calculation is proposed here. scenario.
It was found that the standard Direct Vector method (also The Projected Vector method (for ellipse bisection) that
commonly known as Pedal Curve method) for bisecting the gives the most consistent results is the cross (vector) product
ellipsoid of uncertainty gave misleading results on a crossing of the two wellbore vectors at the two points of interest. A
of wells before and after the closest point. The Direct Vector limitation with this method is that singularity problems are
method is used to extract the ellipse dimension in the same encountered where the two wellbores are nearly parallel. This
direction as the closest approach vector between the two is solved by using the direct vector where the angle of
wellbore points. convergence between the two wells is less than 5 degrees.
The alternative method is called the Projected Vector. In a
normal crossing of wells the shortest line connecting the 2
wellbores will be perpendicular to both. The Projected Vector
method takes the direction to bisect the ellipsoid as the vector
perpendicular to both wellpath directions at the points of
interest seen in Figure B.1.
Figure B.1 – Projected vs. Direct Vectors Illustration
Combined EOU
Direct Vector takes a tangent in the on Reference Well
direction between points of interest
Reference Well
Direction of
Travel
Offset at 5100 Offset at 5400
Offset at 5300
Sum of
Error
Using Direct Vector
Figure 1 – Typical wellpath for accessing fault stacked hydrocarbon accumulations in Gulf of Thailand.
SPE/IADC 92554 13
QRA Risk
Resulting Action
Score
1 No action required.
Drillable well based on physical mitigation if required (barriers below collision point, annulus pressure, etc.) and/or validation by economic
2 model.
Requires Drilling Manager/Operations Manager approval.