Professional Documents
Culture Documents
Product and
Wavin PE
Technical Guide
Content
Introduction
1 General page 14
1.1 Quantities page 14
- Domestic waste water page 14
2 Principles of waste water discharge page 16
2.1 General design principles page 16
- Overpressures and underpressures
- Primary discharge system
- Secondary discharge system
- Restricted secondary discharge system
- Air admittance valves
- Direct separated discharge system
- Balancing lines
2.2 Filling of pipework page 17
2.3 Fall page 17
2.4 Access fittings page 18
3 Peripheral requirements for removal of waste water page 19
3.1 Traps page 19
3.2 Connecting pipes page 19
3.3 Collecting pipes page 19
3.3.1 General requirements page 10
3.3.2 Connections to collecting pipes page 11
3.3.3 Connection separations and sequence page 13
3.4 Stacks page 13
3.4.1 Connections to stacks page 14
- Method
3.4.2 Angled sections page 14
3.4.3 Stack foot and connection-free zones page 14
3.4.4 Stack diameter page 15
3.5 Underground pipes page 15
3.6 Ventilation pipes page 15
3.7 Roof penetrations page 16
3.8 Discharge of waste water page 16
4 Dimensioning for waste water page 17
5 Noise page 18
5.1 The generation of noise page 18
5.2 Noise transmission page 18
5.3 Noise reducing measures page 19
5.4 Fittings page 19
6 Casting in heat cured concrete and extrusion shrinkage page 20
7 Installation page 20
7.1 Design page 20
7.1.1 Fixings
- PE
7.1.2 Brackets page 20
- support bracket
- clamping bracket
- fixed point bracket
7.1.3 Freely suspended pipework page 21
- temperature differences
• cold pipework
• warm pipework
• hot pipework
7.2 Installation methods page 21
7.2.1 Flexible installation page 22
- flexible installation with expansion sleeves and couplers
- flexible installation with flexible connectors
- bracket separations for flexible installation
- bracket distribution for flexible installation
7.2.2 Rigid installation (PE) page 24
- brackets and bracket separations for rigid installation
7.2.3 Cast-in pipework page 26
8 Assembly page 28
8.1 General page 28
8.1.1 Pipework in the waste removal system page 28
8.1.2 Fixing equipment (brackets) page 28
8.1.3 Storage page 28
8.1.4 Oval pipe ends page 28
8.1.5 Shortening pipes page 28
8.2 Brackets page 28
8.2.2 Joints in PE page 28
- butt welding
- electro-weld sockets
- electrical spigot welding
- preparation work
- welding procedure
- use of non-standard pipe
- rubber seals
- expansion sockets
9 Situations during construction page 32
10 Pressure testing page 33
11 Maintenance page 34
12 Product list page 35
2
Wavin PE Soil, Waste & Vent
Introduction
Introduction
1. General
Water is supplied by means of enclosed charges of varying kinds, temperatures, purpose the rainwater may also be used
pipework systems using internal pres- quantities, frequencies and so on. On for flushing toilets, washing clothes or
sure. Waste water is generated when the health, hygiene and odour control consi- cleaning purposes. In that case the
supplied water is used for cleaning, was- derations the system is sealed with traps rainwater is stored in a tank which must
hing, cooking and for flushing away or siphons. When discharges take place, be provided with an overflow. Before
human waste. In discussing waste water air in the system has to make way (ven- proceeding to investigate the principles of
a distinction is made between black ted) for waste water. The principal drainage it will be as well to determine
water (from toilets) and grey water (from problems of drainage are as follows: the nature and quantity of the drainage
washing machines, showers and similar). intermittent drainage, enclosed open requirements.
The black water presents a direct hazard system, complete removal of soil and
to health, grey water does not. Black and water is required. Excess rainwater is also 1.1 Quantities
grey water are generally discharged led away to the external sewer, nowadays
together into the above-ground drainage generally to a separate storm drain. If the Domestic waste water
system which carries the water to the water is relatively clean it may be led from The quantities of water consumed and
underground private sewer (U-drain) into the storm drain to balancing ponds or requiring removal vary appreciably
the public sewer or local treatment facility waterways. Alternatively, clean rainwater throughout the day and depending on the
(septic tank). The above-ground drainage may also be discharged onto the land source of the discharge. 120 to 130 litres
system is an open system which is around the property or into a collective per person per day are used as the basis
accessible at several locations for dis- facility. Where the roof is suitable for the of calculations for supplies required for
domestic use. The assumption is that the
water used will be led off at the rate of 10
to 12 litres per person per hour.
Illustration 1.1 shows the discharge pat-
tern for a 3 to 4 person household over
24 hours. Basic discharge rates (Q¡) to
determine the required capacity for a
given section of pipework are included in
NEN 3215 (see illustration 1.2). Illustration
1.2 also shows the required diameters for
the trap and for the pipe connecting to
the source of the discharge. The quantity
of waste water in collecting pipe stacks,
that is, those containing discharges from
several fittings, can be determined by
means of the formula:
4
Wavin
Wavin PE
PE Soil,
Soil, Waste
Waste &
& Vent
Vent
General
Contents
50
40
30
25
20
15
10
9
8 1,4
7 p=
Illus. 1.2 Baseline discharge, required
Q o (design discharge) (l/s)
6
1,2
diameter for traps and (reduced) 5
p= 7
4 0 ,
connecting pipework for a 3,5 p=
3 05
,
variety of fittings. 2,5 p=
2
1,5
1,0
0,9
0,8
0,7
0,6
Qo can be read off for different values of 0,5
0,4
p in illustration 1.3 if the sum of Q¡ is
1 1,5 2 3 4 5 6 7 8 910 15 20 30 40 50 70 100 150 200 300 400 500 700 1000
known. Qo may never be lower than the
∑ Qi (sum of baseline discharge (l/s)
highest value for baseline discharge Q o may never be less than the largest of the baseline discharges
rates.
Illus. 1.3. Relationship between Q o, p and Q i.
Example:
Calculated using table in 2 gives Q i = 52 l/s
Office (p = 0,7) hence Q o= 5 l/s
In houses and other residential properties cause compression of air, and overpres- this chapter goes on to discuss the
waste water and rainwater must be sures and underpressures will be created. waste water system from the fitting to the
collected separately and led to the These must be kept within limits. Steps building boundary. Requirements and
exterior of the building, or at least up to must also be taken to prevent excessive problems are examined and solutions
the location of a discharge construction overpressures or underpressures created suggested.
for the rainwater. It is important in by hydraulic sealing, whereby little or no
removing waste water that the pipework air can pass over or through a flowing 2.1 General design
empties thoroughly, that any soil is mass of water. The principles and stipula- principles
carried along by the water and that no tions for the removal of waste water are In order to prevent traps being emptied
waste water or sewer gases enter the based upon these assumptions. Having by suction or pressure, overpressures
building via the trap. Discharges will dealt with general construction principles, and underpressures must not exceed
300 Pa (30 mm water column). Air must
be able to escape from the system
(venting) and to enter the system
(admittance). A ventilated discharge pipe
is used for this purpose. Good practice is
to create a primary discharge system
extending the discharge stack above roof
level (see illustration 2.1). This system
allows air to continually enter and vent
from the main sewer. In the case of a
secondary discharge system, each fitting
or branch pipe is connected to a separa-
te ventilation system. A secondary dis-
charge system may be taken through the
roof or connected to a primary discharge
system prior to this being taken through
the roof (illustration 2.2). An unavoidably
long branch pipe may give rise to pro-
blems in a primary system. The section of
the branch pipe furthest from the stack
may then be connected to a restricted
secondary discharge pipe. This may
either be led directly through the roof or
connected to the stack or to the primary
discharge stack. This may be referred to
as a circulating or end discharge system
(illustration 2.3). In this case an internal air
admittance vent on the end of the branch
pipe may be useful. However these can
only admit air to the system, not release
it.
Where overpressure occurs in the system
a membrane is pressed closed, otherwise
sewer stench would enter the room.
The air admittance surface area must be
as close as possible to the cross
sectional area of the collection stack. For
Illus. 2.1 Principles of the primary discharge system. ease of maintenance the air admittance
vent must be fitted in accessible place
6
Wavin PE Soil, Waste & Vent
Principles of waste water discharge
above the level of the fittings. An air airflow is possible, a balancing line may Equal discharge and flow are assumed.
admittance valve may also be useful in be provided. This line allows the balan- This will not be the case immediately
solving problems associated with sepa- cing of overpressures and underpres- downstream of the fittings, but the wave
rate discharging fittings. However they sures. One common example arises if of water will be equal after some time
cannot take the place of the (primary) the stack is not fully vertical but has (and some length of pipe) has passed.
vent pipe. horizontal sections (illustration 2.5). The
A separate direct discharge system (or uppermost example, a restricted secon- 2.3 Fall
direct parallel discharge system) may be dary discharge system, is the most A certain flow rate is required to correctly
employed to solve problems where addi- common solution. The recommendations remove foul water. A lower limit of 1:200
tional fittings are connected to an existing in this manual are based upon the has been established for this purpose.
system. This may facilitate air movement, presence of a primary discharge system. 1:400 or 1:500 may be possible with
while hydraulic sealing has less effect and shorter runs, on condition that a calcula-
the capacity of the stack may increase. 2.2 Filling of pipework tion is provided. In practice the installa-
Such a discharge pipe will be connected In order to allow a free flow of air the tion will then have to be carried out with
exclusively to the stack, that is, no pipework must be designed to take great care. Further, any hydraulic distur-
branch pipe will be connected (illustration account of the quantities to be removed, bances must be minimised: a fitting
2.4). In places in the system where the fall (= gradient or hydraulic slope) and upstream that is frequently used and/or
hydraulic sealing may be caused occur the diameter, so that the pipes are no has a fairly large baseline discharge is an
because of bends, transitions from more than 70% full (water depth is 0.7 x advantage in this case. In general a maxi-
vertical to horizontal or where insufficient the internal pipe diameter). mum fall of 1:50 is maintained to prevent
alternative
Illus. 2.2 Principles of secondary discharge system. Illus. 2.3 Example of restricted secondary discharge system.
water flowing away too quickly, which Stacks can often be cleaned from the
can give rise to hydraulic sealing. roof provided the vent cap can be
removed. With high buildings it is
2.4 Access fittings recommended that an access fitting be
Blockages may occur even in well- provided every 3 to 4 storeys. Ventilation
designed discharge systems, for example lines, including secondary ventilation, may
as a result of deposits (e.g. solidified fat) become (partly) blocked when rainwater
or improper use of the drain (paint residu- gets in or by deposition of dry matter
es, food remnants, cat litter, potting com- from the environment. Vent lines should
post, small objects, etc). Access fittings therefore also be provided with access
should therefore be provided at strategic fittings.
locations in the pipework, taking account
of the fact that clearing equipment can
only cope with limited changes in direc-
tion. Access fittings should be easily
accessible and placed in such way that
hoses or springs can easily be inserted.
The access fitting should where possible
be located on top of the pipe so that in
the case of blockages the whole pipe
does not empty if the cap is removed. Acces Fitting
Illus. 2.4 Principles of the direct separate discharge system Illus. 2.5 Examples of balancing pipework.
(the stack discharges directly). The uppermost method is most commonly applied.
8
Wavin PE Soil, Waste & Vent
Peripheral requirements for removal of waste water
As well as proper calculation and selec- ted using a connecting pipe. During
tion of the appropriate diameter, a num- discharge the connecting pipe must be
ber of other factors are important to completely filled with water. No require-
achieve good operation and prevent ments are therefore set down for the
hydraulic seals, fouling of pipes and minimum fall. Some fall is certainly requi-
excessive overpressures and under- red however as the pipe must empty fully.
pressures. This chapter deals with these If the pipe is completely filled a plug of
peripheral requirements. For this purpose water is created which can cause under-
we now follow the pipework from the pressure. This empties the trap by suc-
source of the discharge onwards. tion and gives rise to gurgling sounds
(illustration 3.1). Complete filling of the
3.1 Traps pipe must therefore make way as rapidly
Each discharging fitting must be provided as possible for partial filling. Significant
with a trap. A certain diameter will be here are the length of the connecting
required, depending on the baseline pipe, its diameter, whether the pipe runs
discharge level (see illustration 1.2). If too vertically or horizontally and the number
small a diameter is chosen then emptying of changes in direction. The required dia-
of the fitting will take too long. Self- meter is stated in illustration 1.2. If the
siphoning (emptying of the trap through total length of the connecting pipework
suction when the fitting is discharged) from the trap to the common stack is
may occur, and noise will increase. On greater than 3.5 metres then a diameter
the other hand, an excessive diameter required for the excess must be determi-
will lead to a lower speed of flow. This ned as if it were a collecting stack, using
results in greater difficulty in carrying 3.3 and illustration 4.1. The total length of
away soiling and blockages may result. a connecting section may not exceed 12
There must be at least 50 mm of water metres. The diameters of parts a and b in
(500 Pa) in a trap. The seal will remain illustration 3.2 may be smaller provided
intact if a maximum underpressure of 300 the following conditions are met:
Pa arises in the system, even if some of total length less than 3.5 metres
the water in the trap has evaporated. part a less than 0.5 metres
Traps with rubber seals are to be part b less than 1.5 metres
preferred because of easier cleansing and (total of the vertical sections).
Illus. 3.1 Self-siphoning or suction replacement. This also prevents problems
emptying of the trap. arising from the use of different materials. The diameter thereby permitted is stated
There are two main types of trap, the in illustration 1.2. In view of the possibility
tubular (M,D,P,S types) and the bottle of damage and for maintenance it is
type (which includes floor-mounted varie- recommended that a rubber sleeve
ties). Each type has its advantages and should be used in the floor (at location x).
disadvantages. The bottle types are more
readily blocked, but also more easily 3.3 Collecting pipes
cleared. The bottle types lose less water Many different factors may affect collec-
to evaporation and are less sensitive to ting pipes.
pressure differences (there is more water This accounts for the many conditions
to be put into motion). A tubular trap is set down to achieve the problem-free
less prone to blocking because the removal of waste water.
speed of flow is higher and the shape These requirements serve two main aims:
allows freer flow. To ensure that free-flowing air remains
available above the water.
3.2 Connecting pipes To ensure that no fouling takes place.
Every fitting must be separately connec-
Where these limits are exceeded, the next diameter up should be selected for the extra length, unless discharge takes place
upstream.
Illus. 3.3 Maximum permissible sum of changes of direction for a particular fall in collecting pipes.
10
Wavin PE Soil, Waste & Vent
Peripheral requirements for removal of waste water
Illus. 3.5 Horizontal connection to collecting pipe with eccentric reducer. Horizontal collecting pipe
45° reducing T-piece with connec-
ting pipe between 30°and 45° with
horizontal section
< 30° as in illustration 3.5.
> 45° conditions as in illustration 3.7
12
Wavin PE Soil, Waste & Vent
Peripheral requirements for removal of waste water
3.3.3 Connection
separations and
sequence
(illustration 3.8)
In order to prevent interactions as much
as possible there are requirements set
down for separation distances. The dis-
tances are so selected that a subsequent
connection smoothes out the flow from A B
Fitting Fitting L
the previous connection, allowing ade-
quate air to remain above the water level. 1 any, unless a toilet any, unless a toilet ≥5xD
The separation must be at least 5 x D 2 any, if Q¡ ≤ 0,75 l/s any, unless a toilet ≥ 2 x D, if D ≥ 110 mm
of the collecting pipe. If the collecting 3 toilet, dishwasher or
pipe is at least 110 mm and the washing machine floor gully shower ≥ 1 m (L1)
calculated Q¡ of the pipe furthest 4 toilet toilet ≥5xD
upstream is no more than 0.75 l/s
any, (no floor gully shower)
then the distance may be 2 x D. 5 toilet if with secondary ≥5xD
If a toilet, dishwasher or washing discharge to B
machine is connected upstream of a if connected
floor-gully shower connection, then 6 any (not a toilet) toilet ≥ 1 m downstream
of B, illustration 3.9
the separation must be at least 1
metre to prevent hydraulic sealing Illus. 3.8 Connection separations and sequences.
through the large quantities of water
and siphoning of the shower trap 3.4 Stacks speed of flow will be between 7 and 11
seal. Since the upwardly extended section of m/s after 10 to 15 metres and will not
No other connection may be made the stack also serves as the vent line in a increase beyond this. 5 to 12 times as
for a length of 1 metre downstream of primary discharge system, great care much air as water is required. The supply
a toilet connection unless that other must be taken to ensure that no hydraulic of air via the ventilating pipe is therefore
connecting pipe is provided with a sealing or excessive pressure differences essential. It is important here that the
discharge. arise. A free flow of air, including the col- stack is as straight as possible. An
Only toilets and no other fitting may lecting pipework, is of crucial importance. underpressure will be created in the
be connected upstream of a toilet The vulnerable areas are: the in-flow from upper section of the stack. This may not
connection, unless the connecting the collecting pipework and any bends, exceed 300 Pa for stacks used for remo-
pipe is provided with a discharge. The including that at the foot of the stack val of waste water (traps must be 500 Pa
upstream fitting (not being a toilet) where this enters the underground pipe, = 50 mm). The determination of diameter
may be connected (at least 1 metre) and any angled bends or horizontal as shown in illustration 4.2 is based on
downstream of the toilet connection branches in the stack. When waste water this. The diameter of the stack may not
(illustration 3.9). is discharged into the stack it will flow be smaller than that of any one of the
Strive to connect fittings with a high down, after passing a short length, more collecting pipes connected upstream.
Q¡ to the upstream section of the col- or less along the pipe walls. A column of Overpressure will exist lower in the stack.
lecting pipe, so as to prevent fouling air with some water will also be drawn In general no attempt is made to limit
and deposition as much as possible downwards. The air and the pipe wall will this, but its effect (the forced emptying of
in that section. In order to prevent slow the falling water. Depending on the traps) is eliminated by establishing zones
interactions as much as possible diameter and the quantity of water, the where no connections may be made.
there are requirements set down for
separation distances.
14
Wavin PE Soil, Waste & Vent
Peripheral requirements for removal of waste water
Illus. 3.13 Transition between stack / Illus. 3.14 Connection in a connection-free Illus. 3.15 Example of a balancing line.
horizontal pipe and connection- zone. See also illus. 2.4 and 2.5.
free zones.
16
Wavin PE Soil, Waste & Vent
Dimensioning for waste water
Illus.4.1 Capacity of horizontal PE pipework; 70% full, k = system wall roughness = 1 mm.
Illus. 4.2 Capacity of PE stacks with a maximum pressure difference of 300 Pa (30 mm of water).
5. Noise
In general, it is considered good practice gravity and a thick wall are therefore
to keep the noise caused by discharge, appropriate. Contact noise is a trouble-
as low as possible. In the Netherlands, some phenomenon. All materials in
requirements are set for noise reduction contact with one another will vibrate
in NEN 1070 and NPR 5075. together, little damping takes place and
An optimal situation can be achieved by amplification may even occur. As the
chosing a low noise pipe in combination E-modulus of a material falls there is less
with good installation practices. In living spreading of noise. In order to reduce
areas in an adjacent residence the level contact noise it is important that pipe
may not exceed 30 dB(A) while for edu- walls do not make contact with one
cational and working areas the figure is another or with other bodies.
35 dB(A). The Wavin range includes a ASTOLAN®, the material used to make
special low-noise waste removal system Wavin AS combines a number of positive
designed to meet these requirements, characteristics in a unique way: it has a
Wavin AS. In this chapter we investigate low specific gravity, a thick wall and a
the generation and transmission of noise relatively low E-modulus. The expansion
in waste pipework and the measures that compensator ensures that a Wavin AS
can be taken to limit noise nuisance. pipe has no direct contact with the next Noise from stacks
pipe. The pipes must be secured with
5.1 The generation of brackets with rubber inserts so that 1 = PVC without jacketing, pipework in
noise minimal noise is transmitted to walls and test area.
Noise is generated in various ways in a floors. These walls and floors should 2 = Wavin AS without jacketing,
pipe with flowing water: the sounds of preferably be of substantial mass so that pipework in test area
flowing water and air, the noise of water it is difficult to bring them into vibration. 3 = PVC with cellular concrete duct
impacting on water and of water impac- A notorious source of noise is the (56 kg/m2)
ting on the tube wall. Combating noise transition from a vertical stack to 4 = Wavin AS with cellular concrete duct
nuisance in waste pipework requires a horizontal pipework. The Wavin AS range (56 kg/m2)
combination of measures, the most includes a variety of accessories to allow
important of which is: to prevent as far as this transition to take place smoothly and
possible that noise is generated. The few sharp changes in direction.
design for a waste pipework installation Additionally this section is freely suspen-
must therefore ensure an optimal layout: ded in rubber in the Wavin AS range and
little impact (so good pipe routing) with there are no brackets. Even with all these
proper ventilation to ensure that the water measures in place waste pipework may
can flow unhindered to counter bubbling not pass through frequently occupied
and differences in flow rates. The pipe areas. Try to arrange routing so that
wall must be smooth to prevent pipework is kept as far as possible away
irregularities in flow. from areas that must be kept low-noise.
There must be at least one intervening
5.2 Noise transmission wall between pipework and a frequently
Noise will occur even with correctly occupied room.
routed pipework. Transmission of noise
takes place in two ways: through the air
(airborne noise) and through solid bodies
in contact with one another (contact
noise). A heavy intervening wall is
required to limit the transmission of noise
through the air. The lighter the pipe wall,
the more easily the airborne noise
escapes to the outside. High specific
18
Wavin PE Soil, Waste & Vent
Noise
5.3 Noise reducing 7. Fixing to a heavy wall damps down 5.4 Fittings
measures contact noise (preferably > 220 Noise from fittings can be limited by:
1. Waste pipework should not be located kg/m2). anti-vibration insulation and anti-vibra-
in the vicinity of occupied areas, and 8. No brackets should be located in tion fixing of the toilet pan
must never be led openly through impact zones. removal of reverberation by placing
occupied areas. 9. A (heavy) intervening wall damps damping material below baths and
2. Good routing and ventilation cut down down transmission by air. shower trays
noise generation: 10. With dummy wall constructions the reduce noise from water jets by using
Falling waste water should be led pipework should be secured to the a small angle against the wall or by
down smoothly in stages, abrupt bearing wall rather than to the means of a perlator.
descents are bad from a noise point dummy wall.
of view. 11. All wall and ceiling penetrations
At the foot of the stack a calming should be provided with rockwool or
section of 250 mm should be used at other elastic materials. This prevents
the transition from the stack to the direct contact between the pipework
horizontal pipework. The use of 2 and the wall and the transmission of
bends of 45° with long legs is airborne noise from one room to
recommended here. another along the pipework.
Waste pipework should be dimensio- 12. Where a pipe duct is present, the
ned so that air can circulate freely inside of the duct wall must be
along with the waste water. provided with absorbent material
A gradually tapered reducer creates (mineral wool).
less noise than an inserted reducer 13. With horizontal pipework below a
does. false ceiling, provide extra insulation
Connections to collecting pipework or with lead foil at bends and connec-
to underground pipes should prefera- tions.
bly be by means of side connections.
Where top connection is unavoidable, Since the method of installation affects
then an angle should be employed. the generation of noise it is recommen-
At the foot of the stack the axis of the ded that the installation is carried out by
horizontal pipe can be shifted around well-trained fitters. Where the measures
1 x D with respect to the axis of the outlined above are implemented
stack. This allows the water to cling consistently, no additional noise
better to the walls creating less noise. insulation will generally be required.
3. A plastic pipe wall is and remains
smooth so that flows are not
disturbed.
4. The special ASTOLAN® pipe wall
(Wavin AS) prevents airborne noise
and contact noise.
5. The Wavin AS expansion compensa-
tor prevents transmission of contact
noise.
6. A rubber insert in the brackets
prevents transmission to the wall,
pipework must never make contact
with walls or other materials.
PE pipework gives excellent results when limits are set down in the standards The degree of extrusion shrinkage
cast into concrete floors and walls (see against set temperatures, and are for PE: depends on the maximum temperature
Chapter 7, Installation). Concrete is at 110°C max. 3%. achieved.
sometimes brought to very high tempera- It is clear that the temperature of the
tures in order to allow shuttering to be The pipe will expand during heating of pipes may be no higher than 80 to 90°C
struck the following day, particularly in the liquid concrete. The degree of expan- to cut out all risk. Since the variation in
tunnelling work. The temperature gauge sion is limited as the pipework is fixed at temperature in the concrete can be fairly
controlling the burners may sometimes various points and (the mass of) the great, it is stipulated that the measured
be defective. It is also sometimes the concrete restricts expansion. Once the temperature shall be no higher than 50 to
case that the control of the burners is concrete has hardened the pipe will 60°C. Higher temperatures are in any
carried out using the outermost tunnel shrink due to thermal shrinkage and case not good for the quality of the
sections, because these cool most rapid- extrusion shrinkage. This is resisted by concrete.
ly. The temperature in the enclosed tunnel the hardened concrete as the pipework is
may then be appreciably higher. Extrusion held fast by bends, sleeves, T-pieces and PE pipes for above-ground drainage
shrinkage becomes significant for plastic similar, so that tensile forces arise in the are sometimes "tempered" for safety
pipework in these circumstances. pipe. The tensile forces give rise to con- reasons. That means that they are heat
Extrusion shrinkage is the single- centrations of stress which may lead to treated during or following manufacture
occurrence shrinkage measurable when breakage. T-pieces are particularly (extrusion), largely removing extrusion
the pipe is heated and then cooled. The susceptible to stress concentrations. shrinkage.
7. Installation
The installation of waste pipework can be Butt welding creates ridges on the interior without excessive deflection.
divided into the installation design and and exterior of the pipe. The internal This method allows any changes in
the installation itself with the actual work ridges can hinder the proper flow of foul length to be transferred to places where
of fitting. The installation must be such water. An experienced welder will be able these can be dealt with by means of
that the pipework system can fulfil its to make a sound welded joint with only bends, flexible pipe, expansion sleeves
function without problems and with the minimal ridging. Electro-welded sleeves and so on. With PE pipework systems
minimum of maintenance. The system can be applied in critical situations. the pipes can be fixed so that no
must be able to handle changes in use, changes in length can occur. The forces
such as changes to the frequency of 7.1.2 Brackets generated can be taken up by the pipe-
discharges or the temperature of the Brackets must have sufficient strength to work itself and transferred to the
medium. The most important condition is carry the weight of the complete pipe- structure via fixed point brackets. We
that the system must be able to with- work when full. Illustration 7.1 shows the then talk about "rigid installation" with
stand the loading generated in installation suspension forces for filled PE pipework fixed point brackets. Rigidly installed
and use. These include: loading through for various bracket separations. Brackets pipework has a tendency to undulate.
the contents and the weight of the may have different functions: support, This can be prevented with the use of
pipework itself; flotation forces when clamping or fixing. A support bracket rails or bearers (see 7.2.2).
casting into concrete floors and in some serves to carry the weight of the pipe-
cases with underground pipework; forces work. If the pipework expands or shrinks
arising from changes in length due to it must be able to slide through the
fluctuations in temperature. This imposes bracket (or the bracket must be able to
a number of requirements on the design follow the movement with little resistance,
and installation of the system. for example through the use of a long,
slender suspension leg which will easily
7.1 Design bend). Clamping brackets serve to fix the
7.1.1 Fixings pipe with respect to the structure. The
Welded connections in PE may be either bracket must therefore hold the pipe
butt welds or electro-welded sleeves. securely and be attached to the structure
20
Wavin PE Soil, Waste & Vent
Installation
Hence
∆L = L x 0.75 x l x ∆T
∆L = Change in length in mm.
L = Length between two points in m.
l = coefficient of expansion
(PE 0.2 mm/m °C)
∆T = temperature difference in °C
∆ T depends on the type of pipework:
cold pipework ∆T = 20°C
warm pipework ∆T = 40°C
hot pipework ∆T ≥ 60°C
22
Wavin PE Soil, Waste & Vent
Installation
- Flexible installation with flexible Apart from brackets at fixed points, all
connectors brackets must be support brackets.
For horizontal pipework this method is Another solution is to select (threaded)
preferred over expansion sockets. In support clamp suspension legs of
general only a small change in alignment materials and dimensions that will bend
is required (illustration 7.4). For long to follow the changes in length. This does
sections of pipework it may be necessary however open the way to undulation of
to create horizontal "jumps" (illustration pipework. This last point need not
7.5). If this is appreciated in good time present a functional problem provided the
there need be no difficulties with any fall is not reversed. It is however often
other pipework or cables. As with regarded as less pleasing to the eye.
expansion sockets, support brackets are The change in length (∆L) for a particular
Illus. 7.4 Minor changes in alignment to used, with clamping brackets for fixed length of PE pipework and the required
create flexible pipe sections. points. The permissible pipe length from length (L) of a flexible section for various
the fixed point (clamping bracket) to the temperature differences can be read off
flexible section is dependant on the from illustration 7.7.
bending the flexible section can take.
The pipes should be bent so as to - Bracket separations with flexible
provide the maximal flexible length. installation
This gives clarity in assembly and Clamp separations are selected so that
maximum flexibility. Halving the permis- the pipe does not sag enough to prevent
sible clamp separation distance will give proper emptying even when hot water is
the permissible length for the flexible carried. The pipework must still be able
section (illustration 7.6). to slide through the support brackets.
The pipework must also be prevented
from excessive sagging for aesthetic
Illus. 7.5 Horizontal "jump" to create reasons.
flexible section in long stretch From strengh point of view horizontal
of horizontal waste pipework. pipework in PE can be suspended with
clamp separations from 20 to 25 x D.
Illus. 7.6 Flexible installation with flexible connectors, and distribution of brackets.
24
Wavin PE Soil, Waste & Vent
Contents
Installation
Illus. 7.9 Bracket and band separation for PE waste pipework, flexible installation.
26
Wavin PE Soil, Waste & Vent
Contents
Installation
PE
calculated
SDR HPE resistance
Du/e pipe size (kPa)
13,3 40x3 635
50x3; 63x3,6; 75x4,3
17 90x5,1; 110x6,3; 125x7,1 348
160x9,1; 200x11,4
21 63x3 178
75x3; 90x3,5; 110x4,3
26 125x4,9; 160x6,2; 92
200x7,7
30 90x3 58
32 110x3,5; 125x3,9; 50
160x5,0; 200x6,2
8. Assembly
As well as the design of the installation oval shape. Oval pipes create extra work tension-resistant connection. There are
there is also the actual assembly. The when welding joints. Bear in mind that two methods of welding: hot plate
design is complete, but many decisions pipes can get very hot in the sun. Once welding and electro-welding using fittings
remain to be taken by the fitter which will out of the sun they will shrink again. If the with integral heating elements. Flange
impact on the quality of the work and the pipe is at 70°C and the temperature joints are also resistant to tension, but
problem-free operation of the waste inside is 20°C, a 5 metre long PE pipe this technique is very rarely used in
removal system. will be 0.2 x 50 x 5 = 50 mm shorter. above-ground drainage work. Rubber
Leave accessories in the packaging as O-ring joints are found in insertion
8.1 General long as possible. PE electro-weld sleeves couplings and expansion sockets in PE.
should be stored indoors and left as long
8.1.1 Pipework in the as possible in the packaging to prevent
waste removal oxidation from sunlight. Oxidation on the
system interior can badly affect welds.
The pipework must be installed with a
particular fall as indicated on the 8.1.4 Oval pipe ends
drawings using brackets, bands and Excessively oval shape PE pipe ends
supports. They must not be fitted should first be made rounder. This can
horizontally, but there must not be too be done by clamping the pipe with one
great a fall. Excessive fall leads to the or two brackets with one or two pieces
complete closure of the pipe and to poor of padding between, placed a little back
ventilation. Where reducing pieces are from the eventual coupling insertion Butt welding
used the top of the pipework should be depth at the end of the pipe. Both pipe ends are placed against a
at the same level. The desired installation The brackets are only removed after the hot plate at a constant temperature
method must be known (see 7.2). weld has cooled. and pressure. The plastic pipe ends
are now pressed together so that the
8.1.2 Brackets 8.1.5 Shortening pipes molecules of the material are
All types can be used with support The best and simplest method is to use transferred between them. Wavin PE
brackets; from light nylon band brackets, a proper pipe cutter. The cut is then pipes and accessories can be hot
light or heavy PVC brackets to galvanised straight and no burrs are generally plate welded with good results. Hot
sewer brackets, and suspension bands. created. If a saw is used, care needs to plate welding creates small ridges
Ensure that any sliding brackets do be taken to ensure that the cut is inside and outside the pipe. It is
actually slide (avoid over-tightening). straight: mark the cut, use a stiff saw recommended that a training course
Brackets used for clamping must be blade and use a saw horse with Ø above should be followed. Before starting
strong. For fixed point brackets (only 50 mm. Remove internal and external with hot plate welding the equipment
with PE) galvanised steel brackets must burrs with steel wool or a knife. For should be checked over.
be used. sawing PE use a fairly coarse-toothed - The hot plate temperature should be
blade with a wide set. 210° C.
8.1.3 Storage - The hot plate must be clean and
Rubber O-rings must be kept in a cool 8.2 Joints free of grease; clean as necessary
and dark place and not exposed to Joints fall in principle into two categories, with a clean cloth and alcohol.
sunlight (not even behind glass). those resistant to tension and those not - Ensure that the two pipe brackets
Pipes must be stored as flat as possible resistant to tension. Welded and flanged and the two pipe supports are
to prevent sagging. It is difficult to joints are resistant to tension. Expansion correctly aligned. This can be
produce neat, straight work with bent sockets and connections using rubber achieved by clamping 1 section of
pipes. Keep pipes as clean as possible; seals are not resistant to tension. pipe in both clamps and both pipe
this saves time when preparing and supports. If necessary adjust the
making connections. Covering is 8.2.2 Joints in PE two pipe supports until they are
recommended during extended storage PE pipes can not be joined using solvent correctly aligned with the pipe.
outdoors. Ensure that PE pipes, and cement as PVC can. However welding of - Both pipe clamps must be adjusted
particularly the ends, do not take on an PE gives excellent results. This creates a so that they hold the pipe tightly
28
Wavin PE Soil, Waste & Vent
Assembly
1 2 3
1. Check that the hot plate is up to 2. Clamp the pipes and use the trimmer 3. Check that the pipe ends match
temperature. on the ends. Stop the trimmer only precisely. If necessary clamp and trim
when the pipes no longer contact the again.
blade; this prevents "hooking".
4 5 6
4. Press the pipe ends against the hot 5. Quickly remove the hot plate and slow- 6. Hold the welding pressure steady and
plate by briefly applying a high pres- ly increase the welding pressure (see allow the weld to cool.
sure. Continue heating with very low the table on the machine for the wel-
pressure until an upstand of 1 mm has ding pressure).
formed.
Before welding:
7 A. The hot plate temperature should be 210° C.
B. The hot plate must be clean and free of grease; clean as necessary with a clean
cloth and alcohol.
C. Ensure that the two pipe brackets and the two pipe supports are correctly aligned.
This can be achieved by clamping 1 section of pipe in both clamps and both pipe
supports. If necessary adjust the two pipe supports until they are correctly aligned
with the pipe.
D. Both pipe clamps must be adjusted so that they hold the pipe tightly enough to
withstand the force of the welding process. The pipe clamps can be used to make
an oval pipe round (but they will also do the opposite). The tension must therefore
7. Remove the joint and inspect the weld. not be either too high or too low.
An irregular weld seam should be
rejected. Most important data for hot plate welding of waste pipework:
enough to withstand the force of the welding sleeve has projections to plastic layers together. However this is
welding process. The pipe clamps allow their exact distance apart to be only possible if the PE surface is
can be used to make an oval pipe determined. This is particularly completely free from contamination.
round (but they will also do the important with prefabrication. Welding Pipes in storage develop an oxidised
opposite). The tension must there equipment is required. layer in production and storage which
fore not be either too high or too Also required are: impedes welding. This must be
low. - A pipe cutter or a saw with teeth set removed before welding by cutting,
wide. scraping or abrasion, followed by
Welding itself is carried out as follows: - Clean, lint-free cloths or white crepe cleaning. Furthermore the material
1. Check that the hot plate is up to paper (not printed). must be free of moisture and must
temperature. - Emery cloth, grit 40. not move during and for a brief period
2. Clamp the pipes and use the trimmer - A scraper or knife for de-burring. after the welding. If these conditions
on the ends. Stop the trimmer only - Felt tip pen or crayon. are not met there will be adhesion but
when the pipes no longer contact the - Tape measure or ruler. without fusion. The weld will be
blade; this prevents "hooking". - The electro-weld sleeve. weaker and high loading or bending
3. Check that the pipe ends match The PE electro-weld sleeve is provi- may later cause leaks. In order to
precisely. If necessary clamp and trim ded with 2 socket ends which can be achieve an even weld all round the
again. welded in a single operation. The pipe must be stress-free. Bent or oval
4. Press the pipe ends against the hot welding equipment sends current pipes may require support. The
plate with a brief application of high through the resistance wires in the components to be welded must be
pressure, then continue with electro-weld socket for a set period. fixed with respect to one another,
application of very low pressure until a Both electro-weld sockets are welded particularly when welding accessories
ridge of 1 mm has formed. at the same time. The electro-weld and short sections of pipe.
5. Quickly remove the hot plate and socket has stops on the interior. In
slowly increase the welding pressure order to use the socket as a slide-on Preparation work
(see the table on the machine for the collar the stops can easily be remo- Select the appropriate welding equip-
welding pressure). ved with a knife or screwdriver. The ment. Check that the welding
6. Hold the welding pressure steady and socket has two contact pins on the equipment is suitable for the diameter
allow the weld to cool. outside for connection of the welding to be welded. The welding equipment
7. Remove the joint and inspect the equipment. There are also two wel- must be protected from moisture and
weld. An irregular ridged seam should ding indicators which appear during dirt. The voltage required is 220 Volts.
be rejected. and after the welding operation. In case of doubt the welding time can
These indicate that the welding be checked. Full instructions for use
Electrical spigot welding temperature has been reached and should be provided with the welding
PE accessories are provided with that the welding pressure has been equipment.
spigot ends to allow butt and sleeve applied. They do not however give
welding. The spigot ends are provided any indication of the quality of the Welding equipment, tools and
with low irregularities (ribbing) and the weld. The quality of the weld is pipework components must be in
dependent on a great many other good condition. That means:
factors. See "Principles and - The welding equipment must be
Preparation". regularly inspected and the welding
time must be correct.
Principles of electro-welded sockets - The contact shoes on the welding
in PE cables must not be oxidised.
During welding the surface of the - The contacts on the electro-weld
interior of the socket and the exterior sockets must be clean.
of the pipe are brought to a plastic - The pipe end to be welded must
state. Expansion of the pipe and not be excessively oval.
shrinkage of the socket (the shrinkage - The cloths used must be clean and
is built in during manufacture) fuse the lint free.
30
Wavin PE Soil, Waste & Vent
Assembly
- The pipe end must be free of burrs. Welding procedure of pipe ends may call for modified
- If a spigot end is very dirty it must A user manual describing the welding processing.
first be cleaned with PE cleaner. procedure should accompany every
If this is not done the dirt will be item of welding equipment. Rubber seals
ground into the pipe when it is - First connect to the power. Two types of rubber seal are in use
abraded later. - The "voltage" indicator lamp will with PE waste systems.
- A layer must be removed from the illuminate. If the lamp flashes check 1 With a round O-ring:
spigot end. This is always required!! voltage and connections. - The O-ring housing and the ring
PE oxidises in air and in light. The - Attach the connector cables to the itself must be clean.
oxidised layer must be removed to electro-weld socket. Note: for safety - The PE pipe must be cut square,
achieve an optimal weld. The oxidi- reasons these cables must not be bevelled off at around 30° and
sed layer can easily be seen after extended. deburred.
extended storage in the open air. - The "connection" indicator lamp will - Introduce the components to one
Extra care will then be required. illuminate. another, up to the stop.
The outer layer is best removed by - Press start button. The welding 2 Sealing sleeve connection:
abrading with clean emery cloth, indicator lamp will illuminate. Once - The sleeve and the chamber
grit 40. Remove the abraded welding time is complete this lamp behind it must be clean.
particles. automatically extinguishes and the - Apply Wavin lubricant to the
The following points are also current supply switches off. sleeve.
significant: - Check the weld indicators. They - Insert the deburred, square cut
- Electro-weld sleeves have a short should have emerged by around and bevelled pipe.
insertion depth, so that a pipe 2 mm.
which is not cut square will weld Note 1: If the welding indicator lamp Expansion sockets
poorly and provides a risk of fire. flashes the welding process Unlike the twin sockets used with
- Check the fit between sleeve and has been interrupted for one PVC, expansion sockets in PE are in
spigot end. If this is oval refer to reason or another. Identify a single piece into which the pipe is
"Oval Pipe ends" (8.1.4). and rectify the cause, allow inserted. A rubber sleeve is used as a
- The pipe and fitting must not move the joint to cool completely seal.
during welding and cooling. If (1 hour) and repeat the
necessary fix with clamps. If the entire procedure. - Install expansion socket at
pipe or fitting sags or creeps the Note 2: The welding process may previously determined locations and
welding threads in the sleeve may only be interrupted by use brackets as for a fixed point.
sag inward. This may cause a fire. switching off the supply. - With the socket end facing
- With large installations a powerful upwards in vertical pipework.
stream of air may flow through the If the use of an isolating transformer is - Attach the PE pipe firmly to the
pipework which can act as a flue. required for safety reasons, say in a spigot end of the expansion socket
This may cause appreciable damp area, then this may be done (using a welded joint).
cooling to the interior. The without problems. Extensive testing has - Align the expansion socket and
pipework should therefore be shown that this does not affect the weld pipework correctly at both ends.
sealed with a protective cap. quality. Fit an extra support bracket if
- The exterior of the electro-weld required. The pipe end to be
socket will become warm only after Use of non-standard pipe inserted must be correctly bevelled
welding has commenced. The joint Electro-weld sockets are designed for (min. 4 mm, 15°).
may only be loaded after the use with PE waste pipes from KOMO - Apply Wavin lubricant to the rubber
socket has cooled. series I and II (see table in Illustration ring and the end of the spigot.
- The ends of pipes and fittings must 7.14). Pipes with thicker walls may - Where a stack is to be enclosed in
be bone dry. If necessary pre-heat also be welded using the electro-weld a duct, protect the joint from mate-
to prevent condensation. socket. Liaison with the supplier rials like mortar that might fall in.
would then be recommended, since - Temperature indications appear on
varying tolerances and greater rigidity the outside of PE expansion
sockets. The pipe must be inserted Ambient Table showing insertion depths for pipe of length 5000 mm
into the expansion socket up to the temperature
ø63 ø75 ø90 ø110 ø125 ø160 ø200 ø250 ø315
temperature indication point for the Insertion depth in mm
then prevailing ambient temperature -10°C 60 60 65 70 75 90 100 115 135
(measure and mark on the pipe). 0°C 65 65 75 80 85 100 110 125 145
- The following maximum lengths +10°C 75 75 85 90 95 110 120 135 155
+20°C 85 85 95 100 105 120 130 145 165
apply to pipe sections between 2
expansion sockets: "cold" pipework
13.2 metre; "warm" pipework 6.6 Illus. 8.1 Insertion depth for PE expansion sockets with "hot pipework" for a range of
metres and "hot" pipework 4.4 to ambient temperatures.
5 metres (see also flexible installa-
tion with expansion sockets 7.2.1).
32
Wavin PE Soil, Waste & Vent
Pressure testing
Pressure testing is carried out most The pipework must not be exposed
quickly and simply using air under a to radiant heat, including the heat of
limited overpressure. This is also possible the sun.
with internal rainwater systems. The Where this nevertheless occurs
simplest procedure is to close off all (usually prior to pouring of concrete)
openings, apply air pressure of 2 to 3 then pressurisation with air and soap
kPa (0.2 to 0.3 metre water column) and testing of the joints is a good
apply soapy water to the joints. alternative.
Specialised companies sometimes use A test is carried out immediately prior
smoke-testing. to the pressure test in order to
demonstrate that the equipment is in
It is recommended that sections to be good order. For this purpose the
cast in concrete be pressure tested internal pressure in an enclosed
before pouring. This is not only because pipeline or hose of say ø10 mm and
repairs are so difficult afterwards, but also 2 metres in length, with the pressure
to establish whom is to bear the cost of meter attached, is brought up to
any subsequent repairs. If it is decided to 400 kPa. The pressure drop may not
carry out pressure testing (to NEN 3215) exceed 10 Pa (1 mm water column)
then the procedure is as follows: in a period of 15 minutes. When that
The system is pressure tested with an is the case the waste removal system
air pressure of 400 Pa (40 mm water may be placed under pressure and
column). Where the total capacity of the actual test carried out.
the system to be tested is greater
than 0.3 m3, then it must be tested in
sections of 0.3 m3.
All open joints are to be sealed with
ball-type valves and all traps are to be
filled.
After 15 minutes the drop in pressure
must not exceed 50 Pa (= 5 mm
water column). If the drop in pressure
exceeds that, the test must be
continued up to 60 minutes. After that
period the drop in pressure may not
exceed 200 Pa (= 20 mm water
column).
The drop in pressure may be caused
by moving connections, such as toilet
sealing sleeves and sealing sleeves
between horizontal pipes and
connecting pipes, as well as by
temperature differences during the
test.
The temperature difference may be
up to 0.3°C, measured in the spaces
occupied by the waste pipework.
11. Maintenance
A well-designed, properly installed and This means that a section of the blocked
correctly used waste removal system will pipework does not need to empty
require little or no maintenance. through the opened access fitting. Where
Inadequacies in design and installation, the access fitting cap is more than
and above all incorrect discharge around 100 to 150 mm from the exterior
activities may cause poor or slow removal of the pipe, the use of a 45° fitting is
of water or a blockage. Usually no action recommended. Obstruction of drainage
is taken until the water begins to drain from roofs, gutters, gullies, overflows,
slowly or there is a complete blockage. rainwater drainage and other drainage
Checks on drainage and periodic constructions must be prevented by
maintenance are therefore recommen- means of periodic maintenance.
ded. In the event of blockages or Special attention must be paid to
threatened blockages which are not drainage where granular roof coverings
located in the traps, a clearing spring are installed after the drainage system is
may be used. Care must be taken to in place. Grit which enters horizontal
prevent damage, especially in bends. pipework is difficult to flush away using
High pressure cleaning with a jet head is the normal speed of flow, and
a better approach. The use of explosive encourages fouling. Flushing clean
charges to cause pressure shocks in the before handover and after around a
pipes is not recommended. year is strongly recommended.
The usual drain-clearing agents may be
used provided the instructions on flushing
are followed.
Roof channels, roofs, roof gullies and the
like should be periodically cleared of dirt,
leaves etc.
34
Wavin PE Soil, Waste & Vent
Product List
Product list
Pipes:
From Ø 75 to Ø 160 pipe series S12,5 / PN 5
From Ø 200 to Ø 315 pipe series S16 / PN 4
Nominal diameters according to DIN 19535
Art.nr. d1/d2 X1 X2 H
Concentric reducer
920 508 40/132 30 30 80
920 516 50/140 30 30 80
920 525 63/140 30 30 80
920 526 63/150 30 30 80
920 530 75/140 30 30 80
920 531 75/150 30 30 80
920 533 75/163 30 30 80
920 535 90/140 30 30 80
920 536 90/150 30 30 80
920 538 90/163 30 30 80
920 539 90/175 30 30 80
920 542 110/140 30 30 80
920 543 110/150 30 30 80
920 545 110/163 30 30 80
920 546 110/175 30 30 80
920 547 110/190 30 30 80
920 550 125/150 30 30 80
920 552 125/163 30 30 80
920 553 125/175 30 30 80
920 554 125/190 30 30 80
920 555 125/110 30 30 80
920 558 160/110 32 29 100
920 560 160/125 32 32 100
920 562 200/160 100 100 250
920 564 250/200 120 120 270
920 566 315/250 130 130 325
CUSTOMER SERVICES
36 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Product list
CUSTOMER SERVICES
38 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Product list
CUSTOMER SERVICES
40 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Product list
Spherical branches,
2 stubs
Type A - 180°
Type B - 90°
Type C - 135°
CUSTOMER SERVICES
42 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Spherical branches,
3 stubs
Type D - 135°
Type E - 90°
Product list
CUSTOMER SERVICES
44 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Art.nr. d1 X1 X2 Connecting
921 139 190 270 50 elbow 90° - smooth
921 140 110 300 60
*with notch
Product list
CUSTOMER SERVICES
46 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Product list
CUSTOMER SERVICES
48 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
To be welded with:
Electro-fusion welding box Code 700020, or other universal welding machine for
electro-fusion couplers Ø 40 to Ø 160.
Product list
The expansion sockets with Ø from 40 to 315 mm absorb the expansion and the con-
traction of a 5000 mm long pipe. 10°C temperature difference = 2 mm expansion
or contraction per meter. Expansion socket
On the expansion socket the push-in depth of the pipe at a room temperature of 0°C Ø 110 mm
and + 20°C is mentioned.
Push-fit depth in mm
Ø -10° 0° +10° +20°
40 - 160 70 80 90 105
200 - 315 170 180 190 205
The expansion socket with Ø 110 has an external ring for fixed-point bracket.
Art.nr. d1 X1 H Bushes
924 363 40 29 62
924 366 50 33 70
924 370 63 37 79
924 371 75 38 81
924 372 90 48 101
924 373 110 52 110
CUSTOMER SERVICES
50 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Flange connections
Product list
N.B. for diameter 50-200 mm, use the gasket EPDM out of the
Wavin PE80-PE100 product range. Please see below.
EPDM
Art.nr. d1 de S
904 402 132 170 3
904 403 140 182 3
904 404 150 192 3
904 405 163 107 3
904 406 175 127 3
904 407 190 142 3
904 408 110 162 3
904 461 140
904 462 160 218 3
904 463 200/225 273 4
904 467 280
CUSTOMER SERVICES
52 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Other Ø on request.
Product list
Roof gullies
CUSTOMER SERVICES
54 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Bracketing system
Art.nr. Description
982 610 Guiding rail 6 mt
982 611 Fixing system 6 mt, ø 40
982 612 Fixing system 6 mt, ø 50
982 613 Fixing system 6 mt, ø 63
982 614 Fixing system 6 mt, ø 75
982 615 Fixing system 6 mt, ø 90
982 616 Fixing system 6 mt, ø 110
982 617 Fixing system 6 mt, ø 125
982 618 Fixing system 6 mt, ø 160
The fixing system includes the guiding rails and fixing brackets.
Product list
Art.nr. Sheet in TG 66
982 514
CUSTOMER SERVICES
56 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
Art.nr. D O-ring
982 621 50
982 622 63
Art.nr. Sheet
982 513
Art.nr.
982 507
Product list
Art.nr. Hexacon
982 528 screws/bolts,
M6 x 20 mm
CUSTOMER SERVICES
58 +31/523-624600
WAVIN PE SOIL & WASTE
Product List
Product list
- with termostat
- teflon-coated
- complete with supports
- metal carrying case
- 800 W
- supply voltage 220 V ~ 50 Hz
Product list
CUSTOMER SERVICES
60 +31/523-624600
Product and
Wavin PE
Technical Guide