9GRAND 2ND FLOOR ROOF CASTING

TIME SCHEDULE
SL DATE PARTICULAR JOBS ASSIGN TOTAL REMARK
15/07/2020 1ST FLOOR ROOF CASTING
DAY-1 17/07/2020 LAY OUT OF COLUMN 10 NOS 10 NOS
DAY-2 18/07/2020 LAY OUT OF COLUMN 10 NOS 20 NOS
STARTER CASTING 5 NOS 5 NOS
DAY-3 19/07/2020 LAY OUT OF COLUMN 14 NOS 34 NOS
STARTER CASTING 0 NOS NOS
COLUMN STEEL BINDING 5 NOS NOS
DAY-4 20/07/2020 LAY OUT OF COLUMN 15 NOS 15 NOS
STARTER CASTING 8 NOS NOS
COLUMN STEEL BINDING 4 NOS NOS
COLUMN SHUTTERING 5 NOS 5 NOS
DAY-5 21/07/2020 LAY OUT OF COLUMN 10 NOS 10 NOS
STARTER CASTING 8 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
DAY-6 22/07/2020 LAY OUT OF COLUMN 10 NOS 20 NOS
STARTER CASTING 10 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
DAY-7 23/07/2020 STARTER CASTING 10 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
DAY-8 24/07/2020 STARTER CASTING 10 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
BEAM RING MAKING 1ST &2ND FLAT BEAMS
DAY-9 25/07/2020 STARTER CASTING 10 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
BEAM RING MAKING 3RD & 4TH FLAT BEAMS
BOARD MAKING IF REQURE
DAY-10 26/07/2020 STARTER CASTING 10 NOS NOS
COLUMN STEEL BINDING 10 NOS NOS
COLUMN SHUTTERING 10 NOS 10 NOS
COLUMN CASTING 8 NOS 8 NOS
BEAM RING MAKING 5TH & 6TH FLAT BEAMS
DESHUTTERING WORK 1ST &2ND FLAT BEAM & SLAB
SHUTTERING WORK 1ST &2ND FLAT BEAMS
DAY-11 27/07/2020 COLUMN SHUTTERING 10 NOS NOS
COLUMN CASTING 8 NOS NOS
BEAM RING MAKING 7TH & 8TH FLAT BEAMS
DESHUTTERING WORK 3RD & 4TH FLAT BEAM & SLAB
SHUTTERING WORK 3RD & 4TH FLAT BEAMS
DAY-12 28/07/2020 COLUMN CASTING 8 NOS NOS
BEAM STEEL CUTTING 1ST &2ND FLAT BEAMS
DESHUTTERING WORK 5TH & 6TH FLAT BEAM & SLAB
SHUTTERING WORK 5TH & 6TH FLAT BEAMS
SLAB CENTERING 1ST &2ND FLAT SLAB
DAY-13 29/07/2020 BEAM STEEL CUTTING 3RD & 4TH FLAT BEAMS
DESHUTTERING WORK 7TH & 8TH FLAT BEAM & SLAB
SHUTTERING WORK 7TH & 8TH FLAT BEAMS
SLAB CENTERING 3RD & 4TH FLAT SLAB
SLAB CHECK 1ST &2ND FLAT SLAB
DAY-14 30/07/2020 BEAM STEEL CUTTING 5TH & 6TH FLAT BEAMS
SHUTTERING WORK 7TH & 8TH FLAT BEAMS
SLAB CENTERING 5TH & 6TH FLAT SLAB
SLAB CHECK 3RD & 4TH FLAT SLAB
BEAM STEEL PLACING 1ST &2ND FLAT BEAMS
DAY-15 31/07/2020 BEAM STEEL CUTTING 7TH & 8TH FLAT BEAMS
SLAB CENTERING 7TH & 8TH FLAT SLAB
SLAB CHECK 5TH & 6TH FLAT SLAB
BEAM STEEL PLACING 3RD & 4TH FLAT BEAMS
DAY-16 01/08/2020 SLAB STEEL CUTTING 1ST &2ND FLAT BEAMS
SLAB CHECK 7TH & 8TH FLAT SLAB
BEAM STEEL PLACING 5TH & 6TH FLAT BEAMS
DAY-17 02/08/2020 SLAB STEEL CUTTING 3RD & 4TH FLAT BEAMS
SLAB STEEL PLACING 1ST &2ND FLAT SLAB
BEAM STEEL PLACING 7TH & 8TH FLAT BEAMS
DAY-18 02/08/2020 SLAB STEEL CUTTING 5TH & 6TH FLAT BEAMS
SLAB STEEL PLACING 3RD & 4TH FLAT SLAB
DAY-19 03/08/2020 SLAB STEEL CUTTING 7TH & 8TH FLAT BEAMS
SLAB STEEL PLACING 5TH & 6TH FLAT SLAB
SHUTTERING WORK MISC. ALL SLAB
DAY-19 03/08/2020 STEEL MISC. ALL SLAB
SHUTTERING WORK MISC. ALL SLAB
ELECTRICAL WORK 50%
DAY-20 04/08/2020 ELECTRICAL WORK COMPLETE
ROOF SLAB CHECK
DAY-21 05/08/2020 CASTING COMPLETE