1 4 Integration Management 1 1 Initiating 4.1 Develop Project Charter
2 4 Integration Management 2 2 Planning 4.2 Develop Project Management Plan
3 4 Integration Management 3 3 Executing 4.3 Direct & Manage Project Work
4 4 Integration Management 4 4 Monitoring & Control 4.4 Monitor & Control Project Work
5 4 Integration Management 5 4 Monitoring & Control 4.5 Perform Integrated Change Control
6 4 Integration Management 6 5 Closing 4.6 Close Project or Phase
7 5 Scope Management 1 2 Planning 5.1 Plan Scope Management
8 5 Scope Management 2 2 Planning 5.2 Collect Requirements
9 5 Scope Management 3 2 Planning 5.3 Define Scope
10 5 Scope Management 4 2 Planning 5.4 Create WBS & WBS Dictionary
11 5 Scope Management 5 4 Monitoring & Control 5.5 Validate Scope
12 5 Scope Management 6 4 Monitoring & Control 5.6 Control Scope
13 6 Time Management 1 2 Planning 6.1 Plan Schedule Management
14 6 Time Management 2 2 Planning 6.2 Define Activities
15 6 Time Management 3 2 Planning 6.3 Sequence Activities
16 6 Time Management 4 2 Planning 6.4 Estimate Activity Resources
17 6 Time Management 5 2 Planning 6.5 Estimate Activity Durations
18 6 Time Management 6 2 Planning 6.6 Develop Schedule
19 6 Time Management 7 4 Monitoring & Control 6.7 Control Schedule
20 7 Cost Management 1 2 Planning 7.1 Plan Cost Management
21 7 Cost Management 2 2 Planning 7.2 Estimate Costs
22 7 Cost Management 3 2 Planning 7.3 Determine Budget
23 7 Cost Management 4 4 Monitoring & Control 7.4 Control Costs
24 8 Quality Management 1 2 Planning 8.1 Plan Quality Management
25 8 Quality Management 2 3 Executing 8.2 Perform Quality Assurance
26 8 Quality Management 3 4 Monitoring & Control 8.3 Control Quality
27 9 Human Resource Management 1 2 Planning 9.1 Plan Human Resource Mangement
28 9 Human Resource Management 2 3 Executing 9.2 Acquire Project Team
29 9 Human Resource Management 3 3 Executing 9.3 Develop Project team
30 9 Human Resource Management 4 3 Executing 9.4 Manage Project Team
31 10 Communications Management 1 2 Planning 10.1 Plan Communications Management
32 10 Communications Management 2 3 Executing 10.2 Manage Communications
33 10 Communications Management 3 4 Monitoring & Control 10.3 Control Communications
34 11 Risk Management 1 2 Planning 11.1 Plan Risk Management
35 11 Risk Management 2 2 Planning 11.2 Identify Risks
36 11 Risk Management 3 2 Planning 11.3 Perform Qualiative Risk Analysis
37 11 Risk Management 4 2 Planning 11.4 Perform Quantative Risk Analysis
38 11 Risk Management 5 2 Planning 11.5 Plan Risk Responses
39 11 Risk Management 6 4 Monitoring & Control 11.6 Control Risks
40 12 Procurement Management 1 2 Planning 12.1 Plan Procurement Management
41 12 Procurement Management 2 3 Executing 12.2 Conduct Procurements
42 12 Procurement Management 3 4 Monitoring & Control 12.3 Control Procurements
43 12 Procurement Management 4 5 Closing 12.4 Close Procurements
44 13 Stakeholder Management 1 1 Initiating 13.1 Identify Stakeholders
45 13 Stakeholder Management 2 2 Planning 13.2 Plan Stakeholder Management
46 13 Stakeholder Management 3 3 Executing 13.3 Manage Stakeholder Engagement
47 13 Stakeholder Management 4 1 Initiating 13.4 Control Stakeholder Engagment
48 14 Safety Management 1 2 Planning 14.1 Plan Safety Management
49 14 Safety Management 2 3 Executing 14.2 Conduct Safety Mangement
50 14 Safety Management 3 4 Monitoring & Control 14.3 Control Safety Management
51 15 Environment Management 1 2 Planning 15.1 Plan Environment Management
52 15 Environment Management 2 3 Executing 15.2 Perform Environment Assurance
53 15 Environment Management 3 4 Monitoring & Control 15.3 Control Environment Management
54 16 Financial Management 1 2 Planning 16.1 Plan Financial Management
55 16 Financial Management 2 4 Monitoring & Control 16.2 Control Financial Management
56 17 Claim Management 1 2 Planning 17.1 Claim Identification
57 17 Claim Management 2 2 Planning 17.2 Claim Quantification
58 17 Claim Management 3 4 Monitoring & Control 17.3 Claim Prevention
59 17 Claim Management 4 5 Closing 17.4 Claim Resolution