Example 2

 Ambrex, Inc., has received an order for 70 units of product


20 and 50 units of product 40, to be delivered in 12 weeks.
The product structure trees for products 20 and 40 are
shown in Figure 4. Ambrex has on hand 300 units each of
components 31 and 37; there is no stock on hand or on
order for other components. Determine the sizes and timing
of planned order releases necessary to meet delivery
commitments for products 20 and 40.
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
Example 2

20 1 2 3 4 5 6 7 8 9 10 11 12

GR 70
SR 0
AVL 0
NR 70
POREC 70
POREL 70

40 1 2 3 4 5 6 7 8 9 10 11 12

GR 50
SR 0
AVL 0
NR 50
POREC 50
POREL 50
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
Example 2

20 1 2 3 4 5 6 7 8 9 10 11 12

GR 70
SR 0
AVL 0
NR 70
POREC 70
POREL 70

29 1 2 3 4 5 6 7 8 9 10 11 12

GR 140
SR 0
AVL 0
NR 140
POREC 140
POREL 140
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
Example 2

30 1 2 3 4 5 6 7 8 9 10 11 12

GR 420
SR 0
AVL 0
NR 420
POREC 420
POREL 420

29 1 2 3 4 5 6 7 8 9 10 11 12

GR 140
SR 0
AVL 0
NR 140
POREC 140
POREL 140
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
Example 2

45 1 2 3 4 5 6 7 8 9 10 11 12

GR 50
SR 0
AVL 0
NR 50
POREC 50
POREL 50

40 1 2 3 4 5 6 7 8 9 10 11 12

GR 50
SR 0
AVL 0
NR 50
POREC 50
POREL 50
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
20 1 2 3 4 5 6 7 8 9 10 11 12

GR 70
SR 0
AVL 0
NR 70
POREC 70
POREL 70

45 1 2 3 4 5 6 7 8 9 10 11 12

GR 50

SR 0

AVL 0

NR 50

POREC 50

POREL 50

31 1 2 3 4 5 6 7 8 9 10 11 12

GR 140 150
SR
AVL 300 300 300 300 300 300 300 160 10
NR 0 0
POREC 0 0
POREL 0 0
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
29 1 2 3 4 5 6 7 8 9 10 11 12

GR 140
SR 0
AVL 0
NR 140
POREC 140
POREL 140

45 1 2 3 4 5 6 7 8 9 10 11 12

GR 50

SR 0

AVL 0

NR 50

POREC 50

POREL 50

37 1 2 3 4 5 6 7 8 9 10 11 12

GR 280 50
SR 0
AVL 300 20 20 20 20
NR 0 30
POREC 30
POREL 30
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
29 1 2 3 4 5 6 7 8 9 10 11 12

GR 140
SR 0
AVL 0
NR 140
POREC 140
POREL 140

40 1 2 3 4 5 6 7 8 9 10 11 12

GR 50

SR 0

AVL 0

NR 50

POREC 50

POREL 50

27 1 2 3 4 5 6 7 8 9 10 11 12

GR 140 200
SR 0 0
AVL 0 0
NR 140 200
POREC 140 200
POREL 140 200
Example 2

20 40
LT = 4 LT = 2

29 (2) 31 (2) 45 (1) 27 (4)


LT = 3 LT = 3 LT = 1 LT = 4

30 (3) 37 (2) 27 (1) 31 (3) 37 (1)


LT = 2 LT = 2 LT = 4 LT = 3 LT = 2
29 1 2 3 4 5 6 7 8 9 10 11 12

GR 140
SR 0
AVL 0
NR 140
POREC 140
POREL 140

40 1 2 3 4 5 6 7 8 9 10 11 12

GR 50

SR 0

AVL 0

NR 50

POREC 50

POREL 50

27 1 2 3 4 5 6 7 8 9 10 11 12

GR 140 200
SR 0 0
AVL 0 0
NR 140 200
POREC 140 200
POREL 140 200