Professional Documents
Culture Documents
Edition 1
Published by
Editions
Edition 1 September 2020 First release as guidance A.
Note the resources text first appeared in
ISO 19650 Part 2 guidance edition 3
Nothing in this guidance constitutes legal advice or gives rise to a solicitor/client relationship.
Specialist legal advice should be taken in relation to specific circumstances.
The contents of this guidance are for general information purposes only.
Permission to reproduce extracts from the ISO 19650 series is granted by BSI Standards Limited (BSI) and the copyright in Figure 3 used
in this report belongs to BSI. No other use of this material is permitted.
British Standards can be obtained in PDF or hard copy formats from the BSI online shop: http://www.bsigroup.com/Shop or by contacting
BSI Customer Services for hard copies only: Tel: +44 (0)20 8996 9001, Email: cservices@bsigroup.com
Any data or analysis from this guidance must be reported accurately and not used in a misleading context. If using any information
from this report, then its source and date of publication must be acknowledged.
Table of contents
Message from the UK BIM Alliance Chair 2
Acknowledgments3
About BS EN ISO 19650 4
Abbreviations and acronyms 5
About this guidance document (executive summary) 6
1.0 About the information management function 8
1.1 Information management and why it is needed 8
1.2 T he information management function 9
1.3 The information management function in the context of multiple lead appointed
parties11
1.4 Developing ISO 19650-2 information management activities into a detailed matrix of
tasks14
1.5 What are the competencies that need considering? 17
1.6 Delegating the information management function 18
1.6.1 Delegation of authority in ISO 19650-2 clauses 5.1.1 and 5.3.1 18
1.6.2 Probity arrangements 18
1.7 Engaging a third party to undertake the information management function 19
1.7.1 Principles 19
1.7.2 Information to be provided to the third party 19
1.7.3 A proposed structure for an invitation to tender when appointing a third party 20
1.8 Conclusion 21
2.0 About ISO 19650 resources 22
2.1 ISO 19650 resources 22
3.0 Summary28
List of figures
Figure 1: ISO 19650 guidance framework 6
Figure 2: Information management process responsibilities and activities 9
Figure 3: Interfaces between parties and teams 12
Figure 4: Example approach for a main contractor - expanded information management
function assignment matrix 15
Figure 5: Example approach for a building services sub-contractor - expanded information
management function assignment matrix 16
Figure 6: ISO 19650-2 resources map 26
List of tables
Table 1:
Abbreviations and acronyms 5
Resources to be prepared by a lead appointed party
Table 2: 11
ISO 19650-2 resources
Table 3: 23
2 | Guidance Part A Edition 1 - September 2020
The information management function and resources
The UK BIM Framework provides the the “end in mind” and consideration from an
fundamental step towards digital organizational, whole life perspective. This
transformation of the UK’s built environment then informs the detailed requirements right
industry. The Framework is based on the ISO down to appointment level.
19650 series, which first developed out of the
UK’s former BIM Level 2, but incorporates The work behind developing this Guidance
and anticipates global and future digital has been considerable. I would like to thank
perspectives. Sarah Davidson and David Churcher for their
tireless commitment in continuing to bring this
The UK BIM Framework embraces and assists work together – I so enjoy working with you
in the implementation of the standards both. Secondly, I would like to thank the many
for managing information for the whole authors who have contributed so generously
life of assets of the built environment. The to the writing of the Guidance – and been so
Framework anticipates the potential for patient in the criticisms and changes that have
integration across portfolios. The Framework been required of them. Finally, I would like to
provides extensive Guidance which continues thank the many people who have spared time
to be developed, including the addition of to review and feedback on the Guidance – the
supplementary tools and materials to enable Focus Groups in particular, but also those who
a firm basis for the evolving National Digital have contacted us separately. Without this
Twin Programme. feedback we would not be able to incorporate
the wide-ranging experience and testing which
This Guidance has been developed to help is occurring around the industry.
industry to implement the concepts and
principles of the ISO 19650 series upon which We welcome your continued feedback and
the UK BIM Framework is based. It has shared experiences. You can provide this via
been continually updated to keep track of guidancefeedback@ukbimframework.org.
the publication of the different parts of ISO
19650, and to reflect lessons learnt as further
experience is gained in its implementation.
Acknowledgments
This guidance represents the collaborative efforts of
the following people and organizations
Editors
David Churcher Hitherwood Consulting Ltd
Sarah Davidson University of Nottingham
Anne Kemp Atkins
Authors
Andy Boutle Kier Author: Section 1
Sarah Davidson University of Nottingham Author: Section 2
Rob Jackson Bond Bryan Author: Section 1
Contributor
Mo Shana’a Morta
Production
Centre for Digital Built Britain
4 | Guidance Part A Edition 1 - September 2020
The information management function and resources
The BS EN ISO 19650 series of standards Standards within the ISO 19650 series are
(herein after referred to as the ISO 19650 available at www.bsigroup.com.
series) is an international standard of good Visit www.ukbimframework.org to see how the
practice. It defines information management ISO 19650 standards plus other standards
principles and requirements within a within the UK BIM Framework map to the
broader context of digital transformation design, build, operate and integrate process.
in the disciplines and sectors of the built
environment (including construction and asset
management industries). Its implementation
in the UK is supported by UK National
Forewords in ISO 19650 Parts 1 and 2, and a
UK National Annex in ISO 19650 Part 2.
This guidance includes a number of abbreviations and acronyms as set out in Table 1.
Table 1: Abbreviations and acronyms
IT Information technology
ISO 19650
Guidance Part 1
Concepts
ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650
Guidance A Guidance B Guidance C Guidance D Guidance E Guidance F
The Open data, Facilitating the Developing Tendering and Information
information buildingSMART CDE (workflow information appointments delivery
management and COBie and technical requirements planning
function & solutions)
resources
1.0 A
bout the information
management function
Author: A
ndy Boutle
Kier
Rob Jackson
Bond Bryan
In recent years, the importance of good It is essential that the industry focuses on
information management with documented “information as an asset” as much as the
responsibility and accountability for the physical asset itself. At both a business
activities and tasks involved has become vital. and project level, outcomes are determined
A proper focus on information management by decisions, and decisions are based on
can help to achieve better project outcomes information. We therefore need to make sure
through, for example: that information management is embedded
and treated with the same importance as
• Improved coordination and communication design, project, and asset management.
• Better quality information production
• Timely information delivery
• Mitigated rework, unnecessary waste and
cost
• Effectively informed decision making
• More accurate audit trails/record keeping.
9 | Guidance Part A Edition 1 - September 2020
The information management function and resources
Activities undertaken
per appointed party
appointment
Appointing party clauses Lead appointed party clauses Appointed party clauses
Every party within the project team has Key points to note
information management functions they will
need to fulfil by assigning the associated • The appointing party (client) has overall
activities to appropriate individuals within accountability for assigning responsibility
their organization. See section 1.4 in this of information management functions to
guidance. their lead appointed parties and should
be vigilant to these being carried out as
Wherever possible it is recommended that required.
individuals within organizations are upskilled • Lead appointed parties could be asked
for self-delivery and continuous improvement. to support and input to appointing party
However, a third party can be appointed resources (for the purposes of information
under an agreed scope of services to carry out management) where the client needs
all or some of these information management assistance but is not willing to formally
activities. appoint a third party.
• Individuals in existing roles that are
Readers familiar with superseded PAS 1192-
assigned information management
2:2013 will recall information management
activities may consider these secondary
responsibilities defined under specific roles
in importance to their usual role when
assumed by members of the project team
particularly busy or under pressure. This
(project information manager, task team
risk needs to be recognized and managed.
manager, task information manager etc.).
The ISO 19650 series moves away from this
approach and intends that the information
management function is embedded into
existing roles.
11 | Guidance Part A Edition 1 - September 2020
The information management function and resources
1.3 T
he information management function in the context of multiple
lead appointed parties
A lead appointed party (tier 1) is any The project wide information resources
organization that has a direct appointment (specifically the project’s information standard
with the appointing party (client). Therefore, and the project’s information production
at any one stage in a project there will methods and procedures) along with each
often be more than one lead appointed exchange information requirements (EIR)
party. Even on small projects the client will received by each lead appointed party,
appoint separate consultants and advisers should drive consistency when preparing
during the design stage, each will therefore their required resources (see Table 2). This
be a lead appointed party. Some lead should enable collaborative working practices
appointed parties (e.g. client appointed design with commonality across the lead appointed
consultants, main contractor) will appoint parties and their delivery teams. If lead
other organizations or internal teams, as task appointed parties are required to work
teams, to form their delivery teams. Other in very close collaboration (such as client
lead appointed parties (e.g. client’s project appointed design consultants), it would be
manager, cost consultant) will be the only considered good practice for the authors of
organizations in their delivery teams, therefore the required resources from each organization
their information management functions will to communicate during the information
be proportionally simpler. planning stage (especially when developing
each delivery team’s BIM execution plan).
Lead appointed party information This will drive out potential inconsistencies
management functions are at an appointment when finalizing their own resources. This
level and on behalf of their delivery team, should be done via the project’s common data
so each lead appointed party must prepare environment.
the resources required as part of their tender
response, and if successful the resources For example, consider a scenario where
required during their appointment, as shown there are three lead appointed parties at
in Table 2. a particular work stage on a project, as
indicated in Figure 3.
Table 2: Resources to be prepared by a lead
appointed party
Tender (Pre-appointment) BIM execution
response plan
phase (5.3) Capability and capacity summary
Mobilization plan
Risk register
Appointment BIM execution plan
phase (5.4)
Detailed responsibility matrix
1
3 2
C
C
C
Main Contractor 2 B ...
Key:
Architect ... B A Appointing Party
Client 3
A
B Lead Appointed Party
C Appointed Party
Client’s project B 2
manager 1 Project Team
3 2 Delivery Team
C
3 Task Team(s)
Figure 3: Interfaces between parties and teams
1.4 D
eveloping ISO 19650-2 information management activities into
a detailed matrix of tasks
ISO 19650-2 includes an information An example of how a lead appointed party
management assignment matrix in Annex such as a main contractor might approach
A, as noted in clause 5.1.1. This is a useful a more detailed information management
resource for an appointing party to use to function assignment matrix is shown in Figure
help form a scope of services when appointing 4. This example shows how a list of tasks
a lead appointed party or third party to carry might be developed under the activity clause
out all or part of the information management 5.4 from ISO 19650-2.
function. It provides a summary of the
clause activities involved in the information An example of how an appointed party
management process in the form of a RACI such as a building services sub-contractor
(responsible, accountable, consulted, informed) might approach a more detailed information
matrix. management function assignment matrix is
shown in Figure 5. This example shows how
Some clause activities from ISO 19650-2 a list of tasks might be developed under ISO
may cover one task, for example preparing 19650-2 activity clauses 5.3, 5.4, 5.6 and 5.7
exchange information requirements. Other 2. Clause 5.6.2 (generate information) is not
activities may involve many tasks, for example included as assigning tasks associated with
the activity of generating information this clause should be via the responsibility
could include tasks such as producing matrices and the TIDPs and MIDP.
models, drawings, schedules, clash detection
procedures, programme simulations and
COBie.
Next page
Figure 4: Example approach for a main contractor - expanded information management function assignment matrix
Information
15 | management
Guidance Partfunction
A assignment matrix: Appointing Lead appointed party
Edition 1 - September 2020
Appointed
party party
Main contractor (lead appointed
The information party)function and resources
management
Document controller
R Responsible for undertaking activity/task
Quantity surveyor
Quality manager
Temporary works
Project manager
Design manager
Sub-contractors
A Accountable for activity/task completion
SHE manager
Site manager
Bid manager
C C onsulted during activity/task
Consultants
Estimator
I Informed following activity/task completion
manager
Planner
advisor
Client
ID Activity/task
5.4 Information management process - Appointment
5.4.1 Establish the delivery team's BIM execution plan
1 Develop the delivery team's BIM execution plan in agreement
A/R C C
with the supply chain, including:
2 Confirm the names of the individual(s) who will undertake the
C C C C A/R C C
information management function
3 Update the delivery team's information delivery strategy (as
A/R C C
required)
4 Update the delivery team's high-level responsibility matrix (as
A/R C C
required)
5 Confirm and document the delivery team's proposed
A/R C C
information production methods and procedures
6 Agree with the client any additions or amendments to the
C C C A/R C C
project's information standard
7 Confirm the schedule of software, hardware and IT
C C C C C C C A/R C C
infrastructure the delivery team will use
5.4.2 Establish the delivery team's detailed responsibility matrix
Key:
R Responsible for undertaking activity/task
Ductwork subcontractor
Third party information
Lagging subcontractor
Controls subcontractor
A Accountable for activity/task completion
Mechanical engineer
Document controller
Electrical engineer
C Consulted during activity/task
CAD technician(s)
Quantity surveyor
Project manager
Main Contractor
Design manager
I Informed following activity/task completion
manager
manager
Client
ID Activity/task
5.3 Information management process - Tender response
5.3.3 Assess task team capability and capacity
1 Assess and confirm team(s) capability and capacity based
on information requirements and delivery team's proposed
(pre-appointment) BIM execution plan
/ R R C C C C R A/R C C C
/
2 Establish and maintain the electrical services task
A I R I C C I C
information delivery plan
3 Establish and maintain the public health services task
information delivery plan / A I R I C C I C
Figure 5: Example approach for a building services sub-contractor - expanded information management function assignment matrix
17 | Guidance Part A Edition 1 - September 2020
The information management function and resources
Non-technical
1.7 E
ngaging a third party to undertake the information
management function
1.7.1 Principles 1.7.2 Information to be provided to the
third party
Where an organization requires assistance
with all or part of their information In order to appoint a third party, it is
management function, they may choose important to provide sufficient information
to engage a third party to assist. In this about the project at the invitation to tender
situation, the third party will be responsible stage to enable a comprehensive proposal
for completing agreed tasks on behalf of to be returned by the prospective third
the appointing organization. However, as party. This should include general project
noted earlier the organization appointing the information along with an anticipated project
third party still retains the accountability to duration and the procurement methodology (if
satisfy the information management functions known).
identified by ISO 19650.
In terms of delivery of the information
Where a third party is engaged, they are management activities, it is also important to
effectively a lead appointed party under the share details of any other parties involved in
ISO 19650 series. However, they would not the project and their capabilities (if known),
be expected to submit a tender response any existing processes and any specific
containing the same information resources technology being used or intending to be
that other lead appointed parties would used. This is so that the third party fulfilling
provide (i.e. they would not need to provide the information management activities and
the resources identified in Table 2). This is tasks can consider the delivery strategy as
because they are carrying out activities on part of their own appointment.
behalf of the appointing party and are not an
information provider in the same context as a Where a third party is being appointed by
delivery team lead appointed party. a lead appointed party, the lead appointed
party will need to include all relevant
information management resources including
the appointing party’s exchange information
requirements, the project’s information
standard and so on.
1.7.3 A
proposed structure for an invitation to tender when appointing a third
party
1.8 Conclusion
Information management is a critical
component of successful project delivery
and asset operation. The information we
produce during the lifecycle of an asset
informs decision making throughout; we
therefore need to treat information with the
same importance as the physical asset(s) it
represents.
Author: S
arah Davidson
The University of Nottingham
Resource ISO
Resource/content Created by 19650 Originating clause
Level Status Part
Summary of the delivery Lead Appointment For 2 5.3.4 Establish the delivery
team’s capability and appointed information team’s capability and
capacity party capacity
Proposed mobilization plan Lead Appointment For 2 5.3.5 Establish the delivery
appointed information team’s mobilization plan
party
Risk register Lead Appointment For 2 5.3.6 Establish the delivery
appointed information team’s risk register
party
Delivery team’s BIM Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s
execution plan appointed BIM execution plan
party
Detailed responsibility matrix Lead Appointment For 2 5.4.2 Establish the delivery team’s
appointed information detailed responsibility
party matrix
Information delivery strategy Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s
appointed BIM execution plan
party
Schedule of software, Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s
hardware and IT appointed BIM execution plan
infrastructure party
Lead appointed party’s Lead Appointed Appointment 2 5.4.3 Establish the lead
exchange information appointed party appointed party’s exchange
requirements party appointment information requirements
Task information delivery Appointed Task team Appointment 2 5.4.4 Establish the task
plan party information delivery plan(s)
Master information delivery Lead Appointment Appointment 2 5.4.5 Establish the master
plan appointed information delivery plan
party
Lessons learned Appointing Appointment For 2 7.8.2 Capture lessons learned for
party information future projects
25 | Guidance Part A Edition 1 - September 2020
The information management function and resources
26 | Guidance Part A Edition 1 - September 2020
The information management function and resources
2. The prospective
Prospective lead appointed party tender response lead appointed
party submits their
Delivery team’s (pre-appointment) BEP considering: tender response
Details of individuals
Proposed information delivery
undertaking the information
strategy
management function
High level responsibility
Proposed federation strategy
matrix
Proposed adds/amends
to project’s information Proposed adds/amends to
production methods and project’s information standard
procedures
Proposed schedule of software, hardware and IT infrastructure
+
Summary of the prospective delivery team’s capability +
capacity
+
Proposed mobilization plan
+
Risk register
+
Delivery team’s BEP including: Delivery team’s BEP
Information
Details of +
delivery strategy
individuals (updated as Task information delivery plan (TIDP)
undertaking required)
the information
management Federation
function strategy (updated
as required)
High level responsibility matrix
(updated as required)
Confirmed schedule of software,
hardware and IT infrastructure
+
Master information delivery plan
(MIDP)
Key:
Created by the appointing party Created by the (prospective) lead appointed party.
Resources do not progress to become appointment resources
Created by the (prospective) lead appointed party.
Resources progress to become appointment resources Created by the (prospective) appointed party
Created by the lead appointed party and inform project level To indicate how one resource informs another
resources To indicate static resources
28 | Guidance Part A Edition 1 - September 2020
The information management function and resources
3.0 Summary
The Centre for Digital Built Britain is part of the Construction Innovation Hub programme,
funded by UK Research and Innovation through the Industrial Strategy Challenge Fund.