Professional Documents
Culture Documents
a) How long does it take the process to produce 100 units starting with an empty
system? (Ans. 626 minutes)
b) What is the average labor content? (Ans. 32 minutes/unit)
c) What is the average labor utilization? (Ans. 88.88%)
d) What is the cost of direct labor? (Ans. $6/unit)
Q 4.2 (Assign Tasks to Workers) Consider the following six tasks that must be assigned to four
workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each
worker must perform at least one task:
The current conveyor-paced assembly line configuration assigns the workers in the following
way:
Worker 1: Task 1
Worker 2: Task 2
Worker 3: Task 3, 4
Worker 4: Task 5, 6
a) What is the capacity of the current line? (Ans. 48 units/hour)
b) Now assume that tasks are allocated to maximize capacity of the line, subject to the
conditions that (1) a worker can only perform two adjacent operations and (2) all
tasks need to be done in their numerical order. What is the capacity of this line
now? (Ans. 65.45 units/hour)
c) Now assume that tasks are allocated to maximize capacity of the line and that tasks
can be performed in any order. What is the maximum capacity that can be
achieved? (Ans. 65.45 units/hour)
Because of a drastically reduced forecast, the plant management has decided to cut
staffing from nine to six workers per shift. Assume that (i) the nine tasks in the above
table cannot be divided; (ii) the nine tasks are assigned to the six workers in the most
efficient way possible; and (iii) if one worker is in charge of two tasks, the tasks have to
be adjacent (i.e., one worker cannot work on tasks 1 and 3).
f) How would you assign the nine tasks to the six workers?
g) What is the new capacity of the line (in toy trucks per hour)? (Ans. 24.83
units/hour)
Q 4.4 (12 Tasks to 4 Workers) Consider the following tasks that must be assigned to four
workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each
worker must perform at least one task. There is unlimited demand.
The current conveyor-paced assembly-line configuration assigns the workers in the following
way:
o Worker 1: Tasks 1, 2, 3
o Worker 2: Tasks 4, 5, 6
o Worker 3: Tasks 7, 8, 9
o Worker 4: Tasks 10, 11, 12
The firm is hiring a fifth worker. Assume that tasks are allocated to the five workers to
maximize capacity of the line, subject to the conditions that (i) a worker can only
perform adjacent operations and (ii) all tasks need to be done in their numerical order.
e) What is the capacity of this line now? (Possible Ans. 51.43 units/hour)
Again, assume the firm has hired a fifth worker. Assume further that tasks are allocated
to maximize capacity of the line and that tasks can be performed in any order.
f) What is the maximum capacity that can be achieved? (Possible Ans. 65.45 units/hour)
g) What is the minimum number of workers that could produce at an hourly rate of 72
units? Assume the tasks can be allocated to workers as described in the beginning (i.e.,
tasks cannot be done in any order). (Ans. 8 workers)
These six workers begin their workday at 08:00 a.m. and work steadily until 04:00 p.m.
At 04:00, no new watch parts are introduced into station A and the conveyor belt
continues until all of the work-in-process inventory has been processed and leaves
station F. Thus each morning the workers begin with an empty system.
a) What is the bottleneck in this process? (Ans. Station E)
b) What is the capacity, in watches per hour, of the assembly line (ignore the time it
takes for the first watch to come off the line)? (Ans. 48 watches/hour)
c) What is the direct labor content for the processes on this conveyor belt? (Ans. 395
sec.)
d) What is the utilization of the worker in station B (ignore the time it takes for the
first watch to come off the line)? (Ans. 80%)
e) How many minutes of the idle time will the worker in station C have in one hour
(ignore the time it takes for the first watch to come off the line)? (Ans. 4
minutes/hour)
f) What time will it be (within one minute) when the assembly line has processed 193
watches on any given day? (Ans. 12:07:30)
Q 4. 6 (Yoggo Soft Drink) A small, privately owned Asian company is producing a private label
soft drink, Yoggo. A machine-paced line puts the soft drinks into plastic bottles and
then packages the bottles into boxes holding 10 bottles each. The machine-paced line
is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a
bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling
machine takes 5 seconds to apply a label to a bottle, and (4) the packaging machine
takes 4 seconds to place a bottle into a box. When a box has been filled with 10 bottles,
a worker attending the packaging machine removes the filled box and replaces it with
an empty box. Assume that the time for the worker to remove a filled box and replace it
with an empty box is negligible and hence does not affect the capacity of the line. At
step 3 there are two labeling machines that each process alternating bottles, that is, the
first machine processes bottles 1, 3, 5, … and the second machine processes bottles 2,
4, 6, … Problem data are summarized in the table below:
a) What is the process capacity (bottles/hour) for the machine paced line? (Ans. 900
bottles/hour)
b) What is the bottleneck in the process? (Ans. The packaging machine)
c) If one more identical labeling machine is added to the process, how much is the
increase in the process capacity going to be (in terms of bottles/hour)? (Ans. Nil)
d) What is the implied utilization of the packaging machine if the demand rate is 60
boxes/hour? Recall that a box consists of 10 bottles. (Ans. 66.67%)
Q 4. 7 (Atlas Inc.) Atlas Inc. is a toy bicycle manufacturing company producing a five inch small
version of the bike that Lance Armstrong rode to win his first Tour de France. The
assembly line at Atlas Inc. consists of seven work stations, each performing a single
step. Stations and processing times are summarized below:
Step 1 (30 sec.): The plastic tube for the frame is cut to size.
Step 2 (20 sec.): The tube is put together.
Step 3 (35 sec.): The frame is glued together.
Step 4 (25 sec.): The frame is cleaned.
Step 5 (30 sec.): Paint is sprayed onto the frame.
Step 6 (45 sec.): Wheels are assembled.
Step 7 (40 sec.): All other parts are assembled to the frame.
Under the current process layout, workers are allocated to the stations as shown below:
Worker 1: Steps 1, 2
Worker 2: Steps 3, 4
Worker 3: Step 5
Worker 4: Step 6
Worker 5: Step 7
Q 4. 8 (Worker-Paced Line)
U1 U2 U3 U4 U5
involves a specially designed packaging unit. After the plant has been operational for a
couple of hours, the manager inspects the plant. He is particularly interested in cutting
labor costs. He observes the following. The process is capacity constrained and the
entire process produces 36 units in one hour. U1 through U5 denote the utilization at
steps 1 through 5 respectively. Currently, there is a single worker at each step and the
utilizations are as follows:
Answer the following questions based on the above data and information.
Q 4.9 (Glove Design Challenge) A manufacturer of women’s designer gloves has employed a
team of MBA students to redesign his manufacturing unit. They gathered the following
information. The manufacturing process consists of four activities: (1) fabric cutting; (2)
dyeing; (3) stitching, done by specially designed machines; and (4) packaging. Activity
times are shown below. Gloves are moved between activities by a conveyor belt that
paces the flow of work (machine-paced line).
**Happy Learning**