You are on page 1of 13

Test Report No :- BBI/006 15/02/2018

Date :- 27/02/2018 Date of Testing To


23/02/2018
Sample Description
1. 38 kV 300ht Floating Insulator
Drg. No.: DEV-0413-001, Rev.: 00 01 No.
Make:- M/s Baroda Moulds & Dies

Test Details :- Temperature Cycle Test


Test Performed Before Temperature Cycle:-
Sr. Test Test Obtained Results Remarks
No. Conducted Requirements
1. HV Test 80 kV For One Withstood The Sample
Minute CONFORMS to
the Test
Requirement
2. Radiography Test Bushings Should No Cracks, Pin Holes, The Sample
(X-RAY) Be free from Blow Holes CONFORMS to
Cracks, Pin Holes Observed. the Test
Requirement
and Blow Holes.

3. Visual Inspection Bushing Should Be No Cracks, Pin Holes, The Sample


free from Cracks, Blow Holes & other CONFORMS to
Pin Holes, Blow Moulding defects the Test
Requirement
Holes and observed on the
Moulding defects Bushings.
etc. Surface Finish
Should Be Smooth.

GAURANG PATEL HARISH MACHHI

PREPARED BY APPROVED BY

Page 1
TEMPERATURE CYCLE TEST:-

1. Test :- Temperature Cycle Test


conducted
2. Test :- 6 Cycle in -20°C ± 5°C to +150°C ± 5°C Temperature & 10
Requirements hours Shock Time Requirements.
3. Obtained :- The Sample Withstood the Test for Test Requirements.
Results
4. Remarks :- The Sample CONFORMS the Test Requirements

Waveforms Recorded During Temperature Cycle Test on

Epoxy Resin Cast Bushing

Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Test Performed After Temperature Cycle:-

Sr. Test Test Obtained Remarks


No. Conducted Requirements Results
1 HV Test 80 kV for One Withstood The Sample
Minute CONFORMS to
the Test
Requirement
2 Radiography Test Bushings Should Be No Cracks, Pin The Sample
(X-RAY) Free from Cracks, Holes, Blow Holes CONFORMS to
Pin Holes and Blow Observed. the Test
Requirement
Holes.
4 Visual Inspection Bushing Should Be No Cracks, Pin The Sample
free from Cracks, Pin Holes, Blow Holes & CONFORMS to
Holes, Blow Holes, other Moulding the Test
Requirement
and Moulding defects observed
Defects etc. Surface on the Bushings.
Finish Should Be
Smooth.

Page 12
REMARKS:-
From the observation of the enclosed oscillographic records, it is concluded that the above
sample CONFORMS to the requirement of above mentioned test specification with respect to
the test carried out.

GAURANG PATEL HARISH MACHHI

PREPARED BY APPROVED BY

Page 13