Progres Pekerjaan Per Tanggal : Senin, 21 September 2020

MONITORING BALOK CORBELT TOWER 3


ZONE 1 ( TANGGA 3 ) ZONE 2 ( TANGGA 2 ) ZONE 3 ( TANGGA 1 ) ZONE 4 ( TANGGA 4 ) KETERANGAN
LANTAI
PEK. BOR PEK. BESI PEK. BEKISTING PEK. COR PEK. BONGKAR PEK. BOR PEK. BESI PEK. BEKISTING PEK. COR PEK. BONGKAR PEK. BOR PEK. BESI PEK. BEKISTING PEK. COR PEK. BONGKAR PEK. BOR PEK. BESI PEK. BEKISTING PEK. COR PEK. BONGKAR
32
31
30
29
28
27
26
25
24
23 Done
22 Done
21 Done
20 Done Done Done Done
19 Done Done Done Done
18 Done Done Done Cor (22/09/20 ) Done Done Done Done Cor (22/09/20 )
17 Done Done Done Cor (22/09/20 ) Done Done Done Done Done Done Done Done Done Done Done Done
16 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
15 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
14 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
13 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
12 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
11 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
10 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
9 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
8 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
7 Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
6
5
4
3
2
GF
BASEMENT

Keterangan Belum dikerjakan


Target pekerjaan
Sudah selesai dikerjakan