Sequence of Drilling and Consolidation Grouting


Setting of Drilling machine

Drilling (0-3000 mm) and installation of slotted


PVC casing

Confirmation on Hole Length

Washing of Hole

Setting of Packer

Perform
Water Loss
Test. No Grout 0-3000 as per step-7 shown below
Is Lugeon
value <3?

Yes Re-drilling 0-3000 & Drill 3000-6000

Drilling from 3000 to 6000

Perform
No Water Loss
Grout 0-6000 as per step-7 shown below Test.
Is Lugeon
value <3?

Re-drilling 0-6000 & Drill 6000-9000 Yes

Drilling from 6000 to 9075

Perform
Water Loss
Test.
No
Is Lugeon Grout 0-9000 as per step-7 below and stop
value <3?

Yes
Stop - Plug the hole and leave it

Work instruction of steps for drilling, water loss test and grouting

1 1st stage drilling and installation of slotted PVC casing (3000 mm fromsoil/ rock surface/founding level)

2 Water loss test - if < 3 lugeon - Proceed to Drill 3000-6000.

3 If > 3 lugeon - grout 0 mm to 3000 mm (Step-7). Wait for 12 hrs. Re drill up to 3000 mm and fresh drill from 3000 mm to 6000 mm

4 Water loss test for 3000 mm to 6000 mm section- if < 3 lugeon - Proceed to Drill 6000 mm-9000 mm.

5 If > 3 lugeon - grout 0 to 6000 mm (Step-7). Wait for 12 hrs. Re drill up to 6000 mm and fresh drill from 6000 mm to 9000 mm

6 Water loss test for 6000 mm to 9000 mm section- if < 3 lugeon - O.K.Plug the hole and stop.
if > 3 lugeon grout 0 to 9000 mm (Step-7). Wait for 12 hrs.

7 Grouting in case water loss > 3 lugeon - 1:10, 1:5, 1:3, 1:2, 1:1 CM in stages upto refusal (<2 ltr/min for 10 min.)