Professional Documents
Culture Documents
3.8
Adjacent buildings
Eastern Boundary
On the north-eastern corner is 255 Kensington High St, which based
on record information has a single basement with four storeys above
ground. It is assumed to be load bearing masonry construction with
shallow strip footings.
Southern Boundary
Numbers 27 to 32 Pembroke place sit directly adjacent to the
southern site boundary, whilst numbers 1,4, 5 and 32a sit on the
other side of the Pembroke place access but are in close proximity to
the site. These buildings are 2-3 storey Victorian terrace houses and
therefore most likely to be load bearing masonry construction with
shallow strip footings.
Western Boundary 255 Kensington High St, north west corner 12-14 Earls Court Rd, east elevation
To the south of Leonard Court runs the rear wall of the Edwardes
Square dwellings gardens. This is defined by a masonry wall on
shallow strip footings which has been extended vertically and/or
incorporated into single storey buildings on the other side of the wall.
11.3 m
8.8 m
3 STOREY RETAIL & RES.
BH A
BUILT CIRCA 1950
267 High Street Kensington BH1 TP 9
BH 9
TP 9a
TP 1
SRMcA 2
TP 9b
BUILT CIRCA 1924
A A
4 STOREY
SRMcA 4
3 STOREY OFFICE BLOCK
TP 2
30.2 m
TP 8
63.5 m
1 Edward Square
BUILT CIRCA 1930
.
RETAIL & RES
TP 3
A 1990
2 STOREY
BUILT CIRC
CINEMA
5 STOREY
BH C
B B
TP 4
SRMcA 3
.
9 Edward Square
RETAIL & RES
BH B
A 1990
SRMcA 1 BH 7
5.9 m
TP 7
BUILT CIRC
BH 5 TP 6
4 STOREY
TP 5
28 Pembroke Place 29 Pembroke Place
HOUSE
BUILT 1874-1896
PUBLIC HOU
3 STOREY TERRACE
CA 1830
5.5 m
BUILT CIR
3 STOREY
C
27-32 Pembroke Place, south elevation Garden wall to the rear of Edwardes Square houses, with south elevation of Leonard Court beyond
3256 - The Kensington 16
4.0
Proposed Block 2
4.1 TH 7
Overview
Town Houses 1 - 6
Block 4
The proposed development comprises a mixture of uses spread
across different blocks above ground.
4.2
Existing structure
With the exception of the Odeon facade, the existing structures
on the site will be demolished.
4.3
Superstructure
The superstructure of all buildings will be of in-situ reinforced
concrete construction. Lateral stability will be provided by shear
walls and where required augmented by frame action.
4.4
Retained facade
Due to its historical significance and architectural merit, it is
proposed to retain the existing facade of the Odeon Kensington.
It is not listed.
Image illustrating the basement volume with internal structure omitted for clarity
3256 - The Kensington 19
4.5.3
Foundations and basement
structure
The basement depth, ground conditions and irregular column
layout make The Kensington well suited to raft foundations
and this is the solution proposed beneath all blocks. Piled
foundations are also a viable option and may be suitable
for some parts of the development depending on the final
construction sequence selected (see below).
4.6
Construction
4.6.2
Construction Sequence
The sequence shown adjacent outlines the initial principles
for constructing The Kensington based on raft foundations
STAGE 8: BLOCK 4 CONSTRU
and a ‘bottom-up’ sequence. Mace have taken these principles
SUPERSTRUCTURE FULLY C
and developed a more detailed sequence based on logistical
constraints and their construction expertise. This can be found
in the separate construction management plan prepared by
Mace.
Stage 4 - Complete excavation and installation of piles Stage 8 - Completion of Block 4 superstructure fully constructed
3256 - The Kensington 21
4.7 4.7.1 •• Stage 2b: Short term settlement due to construction after
application of brittle finishes
Case 2: 0.90ψ2Gk
4.7.2 In summary:
Ground Water Flow ULS (STR & GEO) Design Cases: normal conditions γf = 1.35
accidental conditions γf = 1.00
On the basis of the findings from site investigations as outlined Figure 24: Plan diagram showing existing and proposed basement in the
ULS (UPL) Design Cases: normal conditions γf = 1.10 context of the wider ground plane, demonstrating it’s isolated nature. .
elsewhere in this report, a perched water table is thought to
exist on the site overlying the relatively impermeable London
SLS (ALL) Design Case: normal conditions γf = 1.00
Clay deposit. Perched water levels can vary seasonally and are
prone to rapid changes through heavy rain events on permeable
It is expected that the upper layers of the London Clay deposits
surfaces, accidental events (such as burst water mains) and
will contain fissures, leading to penetration of the perched water
the introduction of new underground construction causing
in the long run and the potential to form an increased head
blockages to natural perched water flow. The River Thames is
of water. The depth of penetration is subject to engineering
located approximately 3km to the South and it is assumed that
judgement based on knowledge of the surrounding ground
the ground water flow would be in this direction. The presence
conditions and on site investigation results.
of open green space in nearby Holland Park may also impact on
the prevailing groundwater flow regime. Concrete Basements – Guidance on the design
In common with the existing Odeon basement, the proposed and construction of in-situ concrete basement
basement will extend down into relatively impermeable London structures (Narayanan & Goodchild)
Clay deposits. In contrast to the existing basement, but in With reference to BS EN1991-4, the use of a partial factor of
common with the consented scheme the proposed the basement 1.2 on the most unfavourable or accidental ULS design case is
will extend laterally for the complete width of the site. In order recommended, this level being taken as ground level unless
to assess the potential impact on peak groundwater levels of there is high confidence in the water table. The factor of 1.2 is INDICATES
interruption of flow within the gravel strata and the need for in accordance also with the provisions of BS81101:1997 Table 2.1
PREDOMINANTLY
GREENFIELD SITE
any resulting mitigation measures groundwater monitoring for water retaining structures. This additional provision shall be
(PARKLAND)
has continued. It is noted however that the impact of the adopted in design as the only variation to the Eurocode 7 design
proposed development is not anticipated to be significant procedure, with the exception that the accidental groundwater
due to the isolated nature of the proposed basement, the level will be taken as 1m below ground level as per BS8102,
low flow rates in the terrace gravels and the background of which has been the adopted figure in UK construction for many
fluctuating groundwater levels. Any significant effect which years. It is considered that taking the accidental level at the
NO SHADING INDICATES NO
is isolated will be mitigated through the construction of a free ground surface would be unduly conservative. SIGNIFICANT BELOW GROUND
OBSTRUCTION
draining layer to the north of the proposed basement which
will drain any elevated peak groundwater and return it to the
downstream perched water table in a controlled manner.
4.7.3 DARKER RED INDICATES BASEMENT
LIKELY TO SEVERLY IMPEDE
SURFACE AQUIFER FLOW IE
BASEMENT EXTENDING TO LONDON
The design philosophy in relation to ground water levels to be With reference to section 3.0, according to the Environment
assumed in design of the permanent works is outlined below Agency flood map, the site is not at risk of flooding and
for reference. Analysis will be completed upon receipt of the consequently lies in flood zone 1 with a return period of event LIGHTER RED INDICATES BASEMENT NOT
EXPECTED TO EXTEND TO LONDON CLAY
outstanding site investigation information. of 1 in 1000 years. No change or increase to the extent of THUS ALLOWING FLOW UNDER
5.0 Conclusions This document presents the Subterranean Construction Method Statement, which records the process undertaken to demonstrate the feasibility
of the proposed development in accordance with RBKC planning requirements. As noted above, the design philosophy and procedures set out
above will form the basis for the detailed analysis and assessment works that will subsequently be required to secure the necessary third party
approvals prior to commencing works on site.
Appendix
Site Constraints Drawings
NOTES:
11.3 m
EXTENT OF BASEMENT
1990
267 High Street Kensington BH1 BH 9
TP 9 MOVEMENTS DUE TO RETAINING WALL DEFLECTION.
BUILT CIRCA
TP 9a (= 1.5 x RETAINED HEIGHT)
6 STOREY RE
TP 1
SRMcA 2
TP 9b
ADJACENT FOOTINGS WITH SITE INVESTIGATION
4 STOREY
SRMcA 4 ADJACENT FOOTINGS WITHOUT SITE INVESTIGATION. T.B.C. BASED
ON RECORD INFO AND FURTHER S.I. INVESTIGATION.
EXTENT ESTIMATED AT THIS STAGE
A 1990
2 STOREY
RETAIL
BUILT CIRCA 1924
5 STOREY
SITE CONSTRAINT REFERENCE
B B
BGS BOREHOLES BGS WEBSITE
TP 4
BUILT 1811-12
A 1990
SRMcA 1 BH 7
RETAIL
5.9 m
TP 7
LUL TUNNELS LUL TUNNELS LOCATION PLANS
BH 5 TP 6
4 STOREY
TP 5
POST OFFICE TUNNELS POST OFFICE TUNNELS
28 Pembroke Place 29 Pembroke Place
UXB LOCATIONS BOMB DAMAGE MAP OF HAMMERSMITH &
E HOUSE
A 1830
5.5 m
PUBLIC
TOPOGRAPHICAL LEVELS GROUND ENGINEERING EXPLORATORY HOLE
LOCATION PLAN C10761 GI REPORT APRIL 2007
3 STOREY
C SITE BOUNDARY S&P DESIGN AND PLANNING STATEMENT APRIL 2007
& OPTION 4a JULY 2012
REV P2 DATE 13/03/2014 DESCRIPTION FOR INFORMATION BY GV CHECKED RH DRAWN GV CHECKED RH PROJECT No. 3256 DRAWING No. S-SK-004 REV P3
NOTES:
SITE BOUNDARY
355mm TRUNK
63mm - 180mm WATER WATER MAIN
FOUL SEWER 1200x800mm
DISTRIBUTION MAIN
BH A BH D
BH1 BH 9 TP 9
A
TP 1 SRMcA 2
TP 9a A
63mm WATER TP 9b
DISTRIBUTION MAIN
SRMcA 4
TP 2
TP 8
FOUL SEWER 2100x1000mm
REV P1 DATE 29.08.12 DESCRIPTION FOR INFORMATION BY AW CHECKED DW DRAWN AW CHECKED DW PROJECT No. 3256 DRAWING No. S-SK-005 REV P1
Appendix 2.0
Borehole Logs