MS PROJECT 2010
Course Topics
Managing Task
Managing Resources
Course Topics
Managing Project Cost
Lesson 2
Managing Resources and Cost
Objectives:
Additional Information for tasks
Task Constrains
Deadline of the task and Timeline
Entering Resources to the Project Plan
Assigning Resources to different tasks
Adding Fixed Cost for the resources
Setting Vacation time of the resources
Changing base rate of the resources
Constraints Type
Constraints Type
As later as Possible
Project forces task to start on the last date possible,
so the tasks ends no later than the END DATE
Finish No Earlier than or Finish no Later
Project makes sure that the task finishes no sooner or later
than a date you supply
Must Start On or Must Finish On
Project forces the task to start or finish on a date we supply
Start no Earlier Than or Start No Later Than
Project makes sure task starts no sooner or later than
supplied date
Resources
RESOURCES – anybody is a resource like
programmer, plumber, electrician, laborer and
others
You can track all of the resources
From Task Tab click on Gantt Chart pull down
menu bar and select Resource Sheet
Then enter all the resources for the project
Resource name
Type of resource
Rate
Regular rate
overtime
Resources Types
Work
Usually means People, based on time
Material
Based on some unit of measurement, per /sq. ft. ex 1 tile
or paper 10 cents a paper
Cost
Cost are incurred which are not depend on amount of
work or duration. Like taxi fare, hotel’s day and others
Cost can be Accrued At either
Start (of the task) - End (of the task) - or Prorated
(distributed evenly over the life of task)